UNDP-GEF Midterm Review of the project “Conservation and sustainable use of Pamir Alay and Tien Shan ecosystems for snow leopard protection and sustainable community livelihoods”

Report Cover Image
Evaluation Plan:
2016-2020, Tajikistan
Evaluation Type:
Mid Term Project
Planned End Date:
01/2020
Completion Date:
02/2020
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
45,000

Share

Document Type Language Size Status Downloads
Download document UNDP-GEF-MTR-TOR-Snow Leopards'_PIMS 5437 project_final.pdf tor English 477.41 KB Posted 40
Download document MTR-Tajikistan-Report-FINAL.pdf report English 1982.36 KB Posted 76
Title UNDP-GEF Midterm Review of the project “Conservation and sustainable use of Pamir Alay and Tien Shan ecosystems for snow leopard protection and sustainable community livelihoods”
Atlas Project Number: 00085264
Evaluation Plan: 2016-2020, Tajikistan
Evaluation Type: Mid Term Project
Status: Completed
Completion Date: 02/2020
Planned End Date: 01/2020
Management Response: Yes
UNDP Signature Solution:
  • 1. Sustainable
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021)
  • 1. Output 2.4.1 Gender-responsive legal and regulatory frameworks, policies and institutions strengthened, and solutions adopted, to address conservation, sustainable use and equitable benefit sharing of natural resources, in line with international conventions and national legislation
SDG Target
  • 15.1 By 2020, ensure the conservation, restoration and sustainable use of terrestrial and inland freshwater ecosystems and their services, in particular forests, wetlands, mountains and drylands, in line with obligations under international agreements
  • 15.2 By 2020, promote the implementation of sustainable management of all types of forests, halt deforestation, restore degraded forests and substantially increase afforestation and reforestation globally
Evaluation Budget(US $): 45,000
Source of Funding: project funds
Evaluation Expenditure(US $): 24,262
Joint Programme: No
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
Jean-Joseph Bellamy Evaluation Consultant
Tahmina Akhmedova Local Evaluation Consultant
GEF Evaluation: Yes
GEF Project Title: “Conservation and sustainable use of Pamir Alay and Tien Shan ecosystems for snow leopard protection and sustainable community livelihoods”
Evaluation Type: Mid-term Review
Focal Area: Biodiversity
Project Type: FSP
GEF Phase: GEF-1
GEF Project ID:
PIMS Number: 5437
Key Stakeholders: National Biosafety and Biodiversity Center, Committee for Environmental Protection under the Government of Tajikistan
Countries: TAJIKISTAN
Lessons
Findings
Recommendations
1

It is recommended to conduct capacity assessments and allocate project resources to consolidate capacities during the remaining implementation period of the project.

2

It is recommended to increase the communications among stakeholders to disseminate more evenly the knowledge accumulated by the project.

3

It is recommended to review/expand the micro-grant programme with a greater focus on alternative sources of income.

4

It is recommended to explore the possibility to open an office in Khorog with one Project Officer based in Khorog.

5

It is recommended to review/assess the TV programmes supported by the project and expand the broadcast during the remaining period of the project

6

It is recommended to undertake a socio-economic valuation study of high-mountain ecosystems

7

It is recommended to provide uniforms to all Rangers in organizations collaborating with the project.

8

It is recommended to develop an exit strategy for the project.

9

It is recommended to monitor the financial status of the project and request a no-cost time extension of the project if the GEF grant will not be expended by August 2021.

10

It is recommended to monitor project management expenditures in order to keep them aligned with the allocated budget of 4.8% of the total GEF grant.

11

It is recommended to review co-financing commitments and request yearly estimates from Partners of the project.

12

It is recommended to increase coordination between snow leopard projects in Kyrgyzstan, Uzbekistan, Kazakhstan and Tajikistan to exchange best practices and lessons learned.

1. Recommendation:

It is recommended to conduct capacity assessments and allocate project resources to consolidate capacities during the remaining implementation period of the project.

Management Response: [Added: 2020/05/15]

Recommendation accepted. Terms of Reference will be developed, and national consultants will be employed to conduct capacity assessment of project partners and relevant gap analysis in 1) protected areas (SPNAs in project areas), and 2) outside protected areas on a wider landscape within snow leopard range (Environment Protection Departments, Forestry Departments, PUUs, etc.).  Based on the priorities identified in the course of the assessment at least 3 demonstration workshops/trainings will be offered to strengthen, in the first instance, the partners’ capacities in ownership of project innovation products (practicing smart patrolling, wildlife inventory, usage of camera traps, etc.) 

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Develop 2 TORs and employ national consultants to conduct capacity assessment of project partners
[Added: 2020/05/15] [Last Updated: 2020/10/08]
• Khisravshokh Shermatov, Project Field Coordinator on Protected Areas 2021/01 Initiated History
Identify priorities for capacity development of SPNA staff
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas 2020/11 Initiated
Conduct at least 3 demonstration workshops/trainings to strengthen, in the first instance, the partners’ capacities in ownership of project innovation products (methods and practice of smart patrolling, wildlife inventory, usage of camera traps) in the areas of Sangvor, Lakhsh, Sarikhosor, Iskanderkul, Tajik NP in Pamir, Alichur.
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas. 2021/08 Initiated
2. Recommendation:

It is recommended to increase the communications among stakeholders to disseminate more evenly the knowledge accumulated by the project.

Management Response: [Added: 2020/05/15]

Recommendation accepted. The project will offer at least 6 technical workshops per annum in each target area devoted to pasture and forest management, protected area management, smart patrolling, community engagement, snow leopard conservation and sustainable livelihoods as well as on the results of the project Midterm Review. Technical review of project achievements will be annually prepared and presented during national workshops/SC meeting.  Relevant project knowledge products will be disseminated among all partners including SPNAs in the form of publications/brochures and through the dedicated webpage to be developed on the website of the National Executing Entity (NBBC).

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Prepare technical review of project achievements to be annually presented at national workshops/SC meetings
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Tatiana Novikova, Project Field Coordinator on Knowledge Management • Vladimir Lekarkin, Project Administrative Assistant; • Dilovarsho Dustov, Project Finance Assistant 2021/08 Initiated
Conduct technical workshops on project best practices and lessons learned in every project target area (at least 6 workshops annually)
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Tatiana Novikova, Project Field Coordinator on Knowledge Management • Vladimir Lekarkin, Project Administrative Assistant; • Dilovarsho Dustov, Project Finance Assistant 2021/08 Initiated
Disseminate knowledge in the form of brochures and through NBBC website (news/operative updates on project interventions, new information on snow leopard ecosystems collected from rangers, project partners and local population)
[Added: 2020/05/15]
• Expert on communication; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Tatiana Novikova, Project Field Coordinator on Knowledge Management 2021/08 Initiated
3. Recommendation:

It is recommended to review/expand the micro-grant programme with a greater focus on alternative sources of income.

Management Response: [Added: 2020/05/15]

Recommendation accepted. To ensure a greater focus on alternative sources of income, the micro-grant programme will be expanded through inclusion of additional thematic areas (beekeeping, gardening and primary processing of agrobiodiversity products, ecotourism) and new geographical areas (buffer zones of targeted protected areas). Along with that, the project will conduct joint field trips on monitoring of SGP Big Cat Conservation programme to learn best practices of projects aimed at generating income by local communities.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Conduct assessment of SGP alternative benefits once the following SGP cycle is implemented
[Added: 2020/05/15] [Last Updated: 2020/10/08]
• SGP expert 2021/07 Initiated History
Conduct joint field trips on monitoring of SGP Big Cat Conservation programme to learn practices of projects, which address generating income by local communities
[Added: 2020/05/15]
• SGP expert 2021/03 Initiated
Expand SGP thematic areas (beekeeping, gardening and primary processing of agrobiodiversity products, ecotourism) and coverage (buffer zones of targeted protected areas)
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Project Field Coordinator on Component 2; • SGP expert 2020/04 Completed the action has been completed and approved by the Project Steering Committee History
Increase SGP funding (up to US $300,000) in the project AWP 2020
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • UNDP CO 2020/03 Completed
4. Recommendation:

It is recommended to explore the possibility to open an office in Khorog with one Project Officer based in Khorog.

Management Response: [Added: 2020/05/15]

Recommendation accepted. The project will explore the possibility to open an office with one Project Officer in Khorog.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Assess the possibility to open project office with one Project Officer in Khorog and deliver proposals in accordance with the project strategy and based on the assessment results, which to be further submitted to the Project Steering Committee for decision making.
[Added: 2020/05/15] [Last Updated: 2020/10/08]
• Neimatullo Safarov, Project Manager; 2020/11 Initiated History
Develop a TOR for Project Officer if deemed necessary by the results of the situation assessment
[Added: 2020/05/15] [Last Updated: 2020/10/08]
• Neimatullo Safarov, Project Manager; 2020/11 Initiated History
5. Recommendation:

It is recommended to review/assess the TV programmes supported by the project and expand the broadcast during the remaining period of the project

Management Response: [Added: 2020/05/15]

Recommendation accepted. The interventions planned by the project to address this recommendation will include assessment of project coverage by thematic TV programmes in 5 key mountainous areas, collection of thematic short stories and interviews from project areas, developing a project video on the importance of conservation of snow leopard ecosystems. US $30,000 are envisaged in the project budget to support communication interventions in 2020

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Review the coverage by thematic TV programmes of the public living in 5 key mountainous areas within snow leopard range (topics related to conservation of snow leopard, its prey and ecosystems)
[Added: 2020/05/15]
• Expert on communication 2020/12 Initiated
Disseminate project video materials via Youtube and Facebook
[Added: 2020/05/15] [Last Updated: 2020/10/08]
• Expert on communication; • Neimatullo Safarov, Project Manager; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Tatiana Novikova, Project Field Coordinator on Knowledge Management; • Vladimir Lekarkin, Project Administrative Assistant; • Dilovarsho Dustov, Project Finance Assistant 2021/08 Initiated History
Collect thematic short stories and interviews in project areas.
[Added: 2020/05/15] [Last Updated: 2020/10/08]
• Expert on communication 2020/08 Completed the action completed History
Develop a short project video highlighting the importance of conservation of snow leopard ecosystems and contribution of local communities.
[Added: 2020/05/15] [Last Updated: 2020/10/08]
• Expert on communication; • Neimatullo Safarov, Project Manager; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Tatiana Novikova, Project Field Coordinator on Knowledge Management • Vladimir Lekarkin, Project Administrative Assistant; • Dilovarsho Dustov, Project Finance Assistant 2020/07 Completed the action completed History
6. Recommendation:

It is recommended to undertake a socio-economic valuation study of high-mountain ecosystems

Management Response: [Added: 2020/05/15]

Recommendation accepted. The project will undertake a socio-economic valuation study, that will be focused on the support of the population temporarily and permanently living in highland snow leopard ecosystems, including grasslands and forests

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Undertake a socio-economic valuation of snow leopard ecosystems
[Added: 2020/05/15] [Last Updated: 2020/10/08]
• Neimatullo Safarov, Project Manager 2020/12 Initiated History
Dedicate a special workshop to disseminate the results of the socio-economic valuation.
[Added: 2020/05/15] [Last Updated: 2020/10/08]
• Neimatullo Safarov, Project Manager 2021/02 Initiated History
7. Recommendation:

It is recommended to provide uniforms to all Rangers in organizations collaborating with the project.

Management Response: [Added: 2020/05/15]

Recommendation accepted. The project will procure uniforms in quantity needed to meet the demand of SPNA, environmental bodies staff and community representatives

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Increase the number of environmental staff members and community representatives (by 40 individuals), provided with uniforms with snow leopard logos, which will be distributed in project target protected areas.
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Project Field Coordinator on Pastures and Forests 2020/10 Overdue-Initiated
8. Recommendation:

It is recommended to develop an exit strategy for the project.

Management Response: [Added: 2020/05/15]

Recommendation accepted. The development of the project exit strategy will be included in the Terms of Reference of National Technical Advisor.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Include the task to develop a project exit strategy in the Terms of Reference of the expected National Technical Advisor; the exit strategy to be developed by April 2021.
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • National Project Director 2021/04 Initiated
9. Recommendation:

It is recommended to monitor the financial status of the project and request a no-cost time extension of the project if the GEF grant will not be expended by August 2021.

Management Response: [Added: 2020/05/15]

Recommendation accepted. Request for no-cost extension of the project for the period of at least 6 months will be developed by 31 December 2020, which will as well take into account the specific force-majeure situation due to COVID19 that is taking place since January 2020.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Develop delivery strategy with timelines
[Added: 2020/05/15] [Last Updated: 2020/10/08]
• Neimatullo Safarov, Project Manager; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Tatiana Novikova, Project Field Coordinator on Knowledge Management; • Vladimir Lekarkin, Project Administrative Assistant; • Dilovarsho Dustov, Project Finance Assistant 2020/12 Initiated History
Prepare and maintain a checklist of documents/requests sent for approval, and track time taken for preparation by project team, and approval by UNDP CO of all major disbursement requests
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Tatiana Novikova, Project Field Coordinator on Knowledge Management; • Vladimir Lekarkin, Project Administrative Assistant; • Dilovarsho Dustov, Project Finance Assistant 2021/08 Initiated
Prepare Plan B (alternative plan) and relevant budget and justification for no-cost project extension until 31 December 2021
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Tatiana Novikova, Project Field Coordinator on Knowledge Management; • Vladimir Lekarkin, Project Administrative Assistant; • Dilovarsho Dustov, Project Finance Assistant 2020/12 Initiated
10. Recommendation:

It is recommended to monitor project management expenditures in order to keep them aligned with the allocated budget of 4.8% of the total GEF grant.

Management Response: [Added: 2020/05/15]

Recommendation accepted. Additional analysis of project delivery pace per budget lines, components and objectives will be carried out, and the project delivery strategy will be developed subject to quarterly review and update. Regular monitoring of the project financial status will be undertaken, and budget revisions will be conducted as appropriate.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Carry out an additional analysis of delivery pace per budget lines, project components and objectives
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Tatiana Novikova, Project Field Coordinator on Knowledge Management; • Vladimir Lekarkin, Project Administrative Assistant; • Dilovarsho Dustov, Project Finance Assistant 2021/08 Initiated
Develop project delivery strategy (Procurement Action Plan), and then update it on a monthly basis along with the review of risks and assumptions
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Dilovarsho Dustov, Project Finance Assistant; • Vladimir Lekarkin, Project Administrative Assistant 2021/08 Initiated
Regularly monitor the financial status of the project and conduct budget revision when necessary
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Dilovarsho Dustov, Project Finance Assistant; • Vladimir Lekarkin, Project Administrative Assistant 2021/08 Initiated
11. Recommendation:

It is recommended to review co-financing commitments and request yearly estimates from Partners of the project.

Management Response: [Added: 2020/05/15]

Recommendation accepted. The project will develop a co-financing confirmation template and provide to partners in order to collect annual reports on the co-finance provided in accordance with the commitments in the Project Document.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Prepare a project co-financing confirmation template and provide to partners in order to collect annual reports on the co-finance provided and to take into account relevant sectorial expenses of Tajikistan in accordance with statistical reporting of the Ministry of Finance and the Ministry of Economy
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Dilovarsho Dustov, Project Finance Assistant; • Vladimir Lekarkin, Project Administrative Assistant 2020/10 Overdue-Initiated
Conduct a review of co-financing from the partners in accordance with the commitments in the Project Document
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Dilovarsho Dustov, Project Finance Assistant; • Vladimir Lekarkin, Project Administrative Assistant 2021/08 Initiated
12. Recommendation:

It is recommended to increase coordination between snow leopard projects in Kyrgyzstan, Uzbekistan, Kazakhstan and Tajikistan to exchange best practices and lessons learned.

Management Response: [Added: 2020/05/15]

Recommendation accepted. The project will undertake online consultations on monitoring and transboundary cooperation with other projects implemented in Central Asia and participate in relevant meetings and programs implemented between the countries of the snow leopard range.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Undertake online consultations on monitoring and transboundary cooperation with other projects in Central Asia, including on experience exchange.
[Added: 2020/05/15] [Last Updated: 2020/10/08]
• Neimatullo Safarov, Project Manager; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Tatiana Novikova, Project Field Coordinator on Knowledge Management; • Vladimir Lekarkin, Project Administrative Assistant; • Dilovarsho Dustov, Project Finance Assistant 2021/05 Initiated History
Participate in meetings and programs implemented between the countries of the snow leopard range, and present the knowledge products, as well as lessons learnt from the project implemented in Tajikistan.
[Added: 2020/05/15]
• Neimatullo Safarov, Project Manager; • Khisravshokh Shermatov, Project Field Coordinator on Protected Areas; • Tatiana Novikova, Project Field Coordinator on Knowledge Management; • Vladimir Lekarkin, Project Administrative Assistant; • Dilovarsho Dustov, Project Finance Assistant 2021/08 Initiated