Kontum project

Report Cover Image
Evaluation Plan:
2006-2011, Viet Nam
Evaluation Type:
Mid Term Project
Planned End Date:
06/2010
Completion Date:
06/2010
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
15,000
See attached

Share

Document Type Language Size Status Downloads
Download document 00056164-_JP_Kon_Tum_Mid-term_review_-_TOR.doc tor Posted 1268
Download document 00056164- JP Kon Tum Mid-term review - Eval Report.doc report English 1422.50 KB Posted 2741
Download document 00056164- JP Kon Tum Mid-term review -Sum&LessonLearnt.doc summary English 896.00 KB Posted 751
Title Kontum project
Atlas Project Number: 00056164
Evaluation Plan: 2006-2011, Viet Nam
Evaluation Type: Mid Term Project
Status: Completed
Completion Date: 06/2010
Planned End Date: 06/2010
Management Response: Yes
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021)
Evaluation Budget(US $): 15,000
Source of Funding: JP
Joint Programme: No
Joint Evaluation: Yes
  • Joint with UNDP, UNICEF, UNFPA
Evaluation Team members:
Name Title Nationality
Frank Noij and Nguyen Thi Thanh Hang Team Leader
GEF Evaluation: No
Key Stakeholders:
Countries: VIET NAM
Lessons
Findings
Recommendations
1 Extend the implementation of the Joint KonTum project into the second part of the project period and to reinforce the requirements for the project to reach its outcomes and goals
2 Support the project to move towards increasingly addressing organisational issues and issues of the enabling environment as part of the wider capacity development process, including the institutionalisation of the local level planning process within the province and legal aspects concerned on provincial and/or national level.
3 Play an active role in the strategy development of the project in the second phase of the project,
4 Urgently fill the technical support gap that results from the resignation of the Project coordinator, in order to enhance the technical capacity of the PMB on a sustained basis.
5 Further enhance the capacity of the PMB
6 Enhance the project capacity in M&E through dedicated M&E support
7 Develop capacity development strategies for the remainder of the project period
8 Pro-active management of the change process in each of the outcome areas concerned
9 Systematic documentation of relevant aspects of implemented models so far, including work done in development of community based networks for child protection, which in effect could serve as an example of how documenting of pilot activities can be undertaken and inform project implementation
10 Enhance the likeliness of learnings from training to be used by trainees
11 Further harmonize the financial and administrative requirements and procedures
12 Mainstream project activities into the main work of the participating entities
1. Recommendation: Extend the implementation of the Joint KonTum project into the second part of the project period and to reinforce the requirements for the project to reach its outcomes and goals
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
- Enhancing the project management board with on-going high level technical support to the management board, enabling the board to actively manage for obtaining outcome level changes - Putting in place a result-based monitoring system in each of the outcome areas of the project that can provide project management with information on the attainment of results in addition to outputs and activities - Developing an adapted and enhanced project results framework with indicators on the level of the outcomes of the various outcome areas
[Added: 2010/12/28] [Last Updated: 2011/12/26]
Project Steering Committee 2011/12 Completed Updated Dec2011
2. Recommendation: Support the project to move towards increasingly addressing organisational issues and issues of the enabling environment as part of the wider capacity development process, including the institutionalisation of the local level planning process within the province and legal aspects concerned on provincial and/or national level.
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
- Enhancing the support and involvement of the project steering committee to the project?s activities. Actively working with the province and the province?s leaders on a concrete plan to move forward the application and institutionalization of the new planning method.
[Added: 2010/12/28] [Last Updated: 2011/12/26]
PSC 2011/12 Completed Updated Dec2011
3. Recommendation: Play an active role in the strategy development of the project in the second phase of the project,
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
- Redefining the role of piloting within the project - Developing models and enhancing horizontal exchanges and learning within the project and thus to create synergy amongst the various outcome areas concerned
[Added: 2010/12/28] [Last Updated: 2011/12/26]
Project Steering Committee 2011/12 Completed Updated Dec2011
4. Recommendation: Urgently fill the technical support gap that results from the resignation of the Project coordinator, in order to enhance the technical capacity of the PMB on a sustained basis.
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
- Hire a techical support staff - In the short run this could be done by hiring a consultant while actions are undertaken for a longer term solution.
[Added: 2010/12/28]
Project Mgt Board 2010/12 Completed
5. Recommendation: Further enhance the capacity of the PMB
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
- Arrange/organize required training for the PMB members on project cycle management, coordination amongst stakeholders, implementing partners and project components, progress monitoring, implementation of the Harmonised Program and Project Management Guidelines and English language ability
[Added: 2010/12/28]
PMB 2010/12 Completed
6. Recommendation: Enhance the project capacity in M&E through dedicated M&E support
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
- Making explicit the responsibilities for M&E at the various levels within the project - Building capacities of implementing partners of the various project components based on existing levels of capacity Supporting data gathering processes with the development of a central project data base using simple database software
[Added: 2010/12/28] [Last Updated: 2011/12/26]
PMB 2011/12 Completed Updated Dec2011
7. Recommendation: Develop capacity development strategies for the remainder of the project period
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
- Making a better balance amongst individual, organisational and enabling environment levels of capacity development in each outcome area - Making use of capacity assessments of key organizations to inform what issues to address. These assessments can in turn be used as reference for monitoring and evaluation.
[Added: 2010/12/28] [Last Updated: 2011/12/26]
PMB 2011/12 Completed Updated Dec2011
8. Recommendation: Pro-active management of the change process in each of the outcome areas concerned
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Monitoring output and outcome level data, informing management decision-making with monitoring information in order to heighten the likeliness that outcome level changes are being achieved through the project.
[Added: 2010/12/28] [Last Updated: 2011/12/26]
UN Agencies and Implementing partners 2011/12 Completed Updated Dec2011
9. Recommendation: Systematic documentation of relevant aspects of implemented models so far, including work done in development of community based networks for child protection, which in effect could serve as an example of how documenting of pilot activities can be undertaken and inform project implementation
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Strengthening the project?s documentation system at the project office and through the project?s activities
[Added: 2010/12/28] [Last Updated: 2011/12/26]
UN Agencies and Implementing partners, PMU 2011/12 Completed Updated Dec2011
10. Recommendation: Enhance the likeliness of learnings from training to be used by trainees
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
- Enhance the likeliness of learnings from training to be used by trainees through: (i) inclusion of trainee responsibility for dissemination of learning to colleagues as part of the training process (ii) include the development of trainee action plans (how the trainee plans to use learning in the workplace) as part of the training and include this in the TOR for the trainer (iii) ensure the availability of budget for implementation of learnings from training (iv) monitor and address constraints concerned, provide follow-up training when needed
[Added: 2010/12/28] [Last Updated: 2011/12/26]
PMU, UN Agencies and Implementing partners 2011/12 Completed Updated Dec2011
11. Recommendation: Further harmonize the financial and administrative requirements and procedures
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents

[Added: 2010/12/28]
UN agencies 2010/12 Completed
12. Recommendation: Mainstream project activities into the main work of the participating entities
Management Response: [Added: 2010/12/28]

Agree with the recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
- Incorporate project activities within their mainstream work planning rather than treating them as stand-alone activities. Relate the identification of outcome level indicators with M&E that is on-going already
[Added: 2010/12/28] [Last Updated: 2011/12/26]
Implementing partners 2011/12 Completed