- Evaluation Plan:
- 2006-2010, China
- Evaluation Type:
- Outcome
- Planned End Date:
- 12/2008
- Completion Date:
- 12/2008
- Status:
- Completed
- Management Response:
- Yes
- Evaluation Budget(US $):
- 30,000
Energy (CPO-06)
Share
Document | Type | Language | Size | Status | Downloads |
---|---|---|---|---|---|
![]() |
tor | Posted | 862 | ||
![]() |
report | English | Posted | 1309 | |
![]() |
summary | Posted | 506 |
Title | Energy (CPO-06) | ||||||
---|---|---|---|---|---|---|---|
Atlas Project Number: | |||||||
Evaluation Plan: | 2006-2010, China | ||||||
Evaluation Type: | Outcome | ||||||
Status: | Completed | ||||||
Completion Date: | 12/2008 | ||||||
Planned End Date: | 12/2008 | ||||||
Management Response: | Yes | ||||||
Focus Area: |
|
||||||
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021) |
|
||||||
Evaluation Budget(US $): | 30,000 | ||||||
Source of Funding: | |||||||
Joint Programme: | No | ||||||
Joint Evaluation: | No | ||||||
Evaluation Team members: |
|
||||||
GEF Evaluation: | No | ||||||
Key Stakeholders: | |||||||
Countries: | CHINA, PEOPLE'S REPUBLIC | ||||||
Comments: | Partners will include NDRC, SEPA, MOST, CICETE, ect. |
Lessons | |
---|---|
Findings |
Recommendations | |
---|---|
1 | Evaluation Recommendation or Issue 1: Continue the development of local capacities and encouraging continuing commitment by supporting relevant institutions sustain the training and capacity building |
2 | Evaluation Recommendation or Issue 2: Continue further work to support updating and refinements of policy, planning, and strategy. |
3 | Evaluation Recommendation or Issue 3: Continue technology development and modernization the RE technology to bring down further the cost of acquisition and operation |
Key Action Update History
Loading..
1. Recommendation: Evaluation Recommendation or Issue 1: Continue the development of local capacities and encouraging continuing commitment by supporting relevant institutions sustain the training and capacity building
Management Response: [Added: 2008/12/26]
UNDP China agrees to the evaluation recommendation and will take follow-up actions.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
1. Trainings, workshops .and seminars will be held, training materials will be published and disseminated.
[Added: 2008/12/26] |
E & E Team/CO | No due date | No deadline established | The annual workplan (AWP) is being developed and discussed with the counterparts. | |
2. Initiate a training gap analysis and manpower requirement assessment vis-à-vis the long term energy goals and targets.
[Added: 2008/12/26] |
E & E Team/CO | No due date | No deadline established | The annual workplan (AWP) is being developed and discussed with the counterparts. |
2. Recommendation: Evaluation Recommendation or Issue 2: Continue further work to support updating and refinements of policy, planning, and strategy.
Management Response: [Added: 2008/12/26]
UNDP China agrees to the evaluation recommendation and will take follow-up actions.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
1. National strategy on rural energy development will be drafted and workshops will be held.
[Added: 2008/12/26] |
E & E Team/CO | No due date | No deadline established | The annual workplan (AWP) is being developed and discussed with the counterparts. | |
2. Roundtables on technology transfer, financing mechanism, etc will be held.
[Added: 2008/12/26] |
E & E Team/CO | No due date | No deadline established | The annual workplan (AWP) is being developed and discussed with the counterparts. |
3. Recommendation: Evaluation Recommendation or Issue 3: Continue technology development and modernization the RE technology to bring down further the cost of acquisition and operation
Management Response: [Added: 2008/12/26]
UNDP China agrees to the evaluation recommendation and will take follow-up actions.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
1. A feasibility study on biomass pellet system will be conducted and two biomass pellet system demonstration projects will be initiated.
[Added: 2008/12/26] |
E & E Team/CO | No due date | No deadline established | The annual workplan (AWP) is being developed and discussed with the counterparts. | |
2. Workshops on advanced RE technology will be held.
[Added: 2008/12/26] |
E & E Team/CO | No due date | No deadline established | The annual workplan (AWP) is being developed and discussed with the counterparts. |