- Evaluation Plan:
- 2008-2012, Malaysia
- Evaluation Type:
- Final Project
- Planned End Date:
- 07/2011
- Completion Date:
- 07/2011
- Status:
- Completed
- Management Response:
- Yes
- Evaluation Budget(US $):
- 30,000
Biomass Power Generation and Co-generation in Palm Oil Mills
Share
Document | Type | Language | Size | Status | Downloads |
---|---|---|---|---|---|
![]() |
report | English | 540.62 KB | Posted | 9792 |
![]() |
tor | English | 77.00 KB | Posted | 736 |
Title | Biomass Power Generation and Co-generation in Palm Oil Mills | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Atlas Project Number: | 00013487 | ||||||||||||||
Evaluation Plan: | 2008-2012, Malaysia | ||||||||||||||
Evaluation Type: | Final Project | ||||||||||||||
Status: | Completed | ||||||||||||||
Completion Date: | 07/2011 | ||||||||||||||
Planned End Date: | 07/2011 | ||||||||||||||
Management Response: | Yes | ||||||||||||||
Focus Area: |
|
||||||||||||||
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021) |
|
||||||||||||||
Evaluation Budget(US $): | 30,000 | ||||||||||||||
Source of Funding: | GEF | ||||||||||||||
Joint Programme: | No | ||||||||||||||
Joint Evaluation: | No | ||||||||||||||
Evaluation Team members: |
|
||||||||||||||
GEF Evaluation: | Yes
|
||||||||||||||
Key Stakeholders: | MEGTW, EPU | ||||||||||||||
Countries: | MALAYSIA | ||||||||||||||
Comments: | Environmental and energy sustainability objectives integrated in macroeconomic and sector policies. This is the Terminal Evaluation |
Lessons | |
---|---|
Findings |
Recommendations | |
---|---|
1 | While the other components (policy, awareness and financing) have been completed, the completion of the 2 Full scale model (biomass and biogas) projects is crucial in determining the success of the this project. |
Key Action Update History
Loading..
1. Recommendation: While the other components (policy, awareness and financing) have been completed, the completion of the 2 Full scale model (biomass and biogas) projects is crucial in determining the success of the this project.
Management Response: [Added: 2011/12/22]
UNDP CO will discuss further with MEGTW in resolving this concern.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Completion of the 2 FSMs
[Added: 2011/12/22] |
MEGTW | 2011/12 | Completed | the 2 projects have been fully commissioned. as both are under the new RE Act, they will be subjected to the conditions under FiT. |