Jamaica Violence Prevention, Peace and Sustainable Development Programme

Report Cover Image
Evaluation Plan:
2007-2011, Jamaica
Evaluation Type:
Final Project
Planned End Date:
06/2010
Completion Date:
12/2011
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
16,000

Share

Document Type Language Size Status Downloads
Download document UNDP Final JVPPSDP Evaluation Report_SUBMITTED.pdf report English 2143.86 KB Posted 965
Download document ToR Evaluator-JVPPSD.pdf tor English 105.26 KB Posted 472
Title Jamaica Violence Prevention, Peace and Sustainable Development Programme
Atlas Project Number:
Evaluation Plan: 2007-2011, Jamaica
Evaluation Type: Final Project
Status: Completed
Completion Date: 12/2011
Planned End Date: 06/2010
Management Response: Yes
Focus Area:
  • 1. Democratic Governance
  • 2. Environment & Sustainable Development
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
  • 1. Effective, responsive, accessible and fair justice systems promote the rule of law, including both formal and informal processes, with due consideration on the rights of the poor, women and vulnerable groups
Evaluation Budget(US $): 16,000
Source of Funding: BCPR
Joint Programme: No
Joint Evaluation: Yes
  • Joint with BCPR, UNDP
Evaluation Team members:
Name Title Email Nationality
Team Leader
GEF Evaluation: No
Key Stakeholders: BCPR, Ministry of National Security, Ministry of Justice, Social Development Commission
Countries: JAMAICA
Lessons
Findings
Recommendations
1 Evaluation recommendation 1. Ensure project implementation matches project design Flexibility should only be allowed where there is a demonstrable improvement to the programme if a different implementation strategy were taken.
2 Evaluation recommendation 2. Train implementing and responsible partners in reporting format The quality of submitted reports exhibited deficiencies, which led to delays in approval of further advances to project partners
3 Evaluation recommendation 3. Ensure gender mainstreaming is effectively incorporated into the design and execution of the projects. The project design did not have specific gender mainstreaming plans or targets
4 Evaluation recommendation 4. Ensure active buy-in from state counterparts on national implementation The project began without this arrangement being cemented
1. Recommendation: Evaluation recommendation 1. Ensure project implementation matches project design Flexibility should only be allowed where there is a demonstrable improvement to the programme if a different implementation strategy were taken.
Management Response: [Added: 2011/12/28] [Last Updated: 2011/12/28]

Supported. Will be done for future projects

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Engage competent project management
[Added: 2011/12/28]
Programme team No due date No deadline established
Ensure deviations from project as designed, only take place on approval from Project Board
[Added: 2011/12/28]
Programme team No due date No deadline established
Ensure exception reports/ justifications are always provided in writing when project implementation deviates from design
[Added: 2011/12/28]
Programme team No due date No deadline established
2. Recommendation: Evaluation recommendation 2. Train implementing and responsible partners in reporting format The quality of submitted reports exhibited deficiencies, which led to delays in approval of further advances to project partners
Management Response: [Added: 2011/12/28] [Last Updated: 2011/12/28]

supported. Will be done for future projects

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Engage competent project management
[Added: 2011/12/28]
Programme team No due date No deadline established
Conduct training on a project-by-project basis for project managers and support
[Added: 2011/12/28]
Programme team No due date No deadline established
3. Recommendation: Evaluation recommendation 3. Ensure gender mainstreaming is effectively incorporated into the design and execution of the projects. The project design did not have specific gender mainstreaming plans or targets
Management Response: [Added: 2011/12/28] [Last Updated: 2011/12/28]

Supported. Will be done for future projects

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Gender mainstreaming plans with tangible targets and actions to be incorporated in the design of the project
[Added: 2011/12/28]
Programme team No due date No deadline established
4. Recommendation: Evaluation recommendation 4. Ensure active buy-in from state counterparts on national implementation The project began without this arrangement being cemented
Management Response: [Added: 2011/12/28] [Last Updated: 2011/12/28]

Supported. Will be done for future projects.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Programmes and projects are designed in consultation with the national counterparts. LPAC held for all projects
[Added: 2011/12/28]
Programme team No due date No deadline established