Support to National Efforts for the Promotion of Youth Employment and Management of Migration - MDG-F

Report Cover Image
Evaluation Plan:
2011-2015, Serbia
Evaluation Type:
Mid Term Project
Planned End Date:
04/2011
Completion Date:
04/2011
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
15,000

Share

Document Type Language Size Status Downloads
Download document YEM Mid term evaluation TOR.docx tor English 1500.97 KB Posted 624
Download document Mid-term evaluation report YEM 28Apr11.docx report English 199.41 KB Posted 1564
Title Support to National Efforts for the Promotion of Youth Employment and Management of Migration - MDG-F
Atlas Project Number: 0071027
Evaluation Plan: 2011-2015, Serbia
Evaluation Type: Mid Term Project
Status: Completed
Completion Date: 04/2011
Planned End Date: 04/2011
Management Response: Yes
Focus Area:
  • 1. Poverty and MDG
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021)
  • 1. Capacities of national and local institutions enhanced to scale up proven MDG acceleration interventions and to plan, monitor, report and evaluate the MDG progress in the context of related national development priorities
Evaluation Budget(US $): 15,000
Source of Funding: MDG-F Secretariat
Joint Programme: No
Joint Evaluation: Yes
  • Joint with IOM, UNDP, ILO and UNICEF
Evaluation Team members:
Name Title Nationality
Dietmar Aigner Team Leader
GEF Evaluation: No
Key Stakeholders: Ministry of Economy and Regional Development
Countries: SERBIA
Lessons
Findings
Recommendations
1 Extension of programme duration
2 Communication and Advocacy
3 Design of future joint programmes
1. Recommendation: Extension of programme duration
Management Response: [Added: 2011/08/30]

Prepare request for no-cost extension of 6 months

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Request for no-cost extension of 6 months processed
[Added: 2011/08/30]
JP Manager 2011/06 Completed
2. Recommendation: Communication and Advocacy
Management Response: [Added: 2011/08/30]

Prepare promotion event for the launch of the online campaign

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Prepare online campaign
[Added: 2011/08/30]
JP Manager 2011/07 Completed
3. Recommendation: Design of future joint programmes
Management Response: [Added: 2011/08/30] [Last Updated: 2011/08/30]

Extension of YEM

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Extension of YEM
[Added: 2011/08/30]
RC office and all partners No due date No deadline established An extension of the current YEM programme will allow sufficient time to explore improved joint working and coordination mechanisms in a potential YEM II joint programme