Strengthening Accountability Mechanisms in Public Finance (mid-term)
Share
Document | Type | Language | Size | Status | Downloads |
---|---|---|---|---|---|
![]() |
tor | English | 74.38 KB | Posted | 718 |
![]() |
report | English | 393.50 KB | Posted | 1176 |
Title | Strengthening Accountability Mechanisms in Public Finance (mid-term) | ||||||
---|---|---|---|---|---|---|---|
Atlas Project Number: | 00073006 | ||||||
Evaluation Plan: | 2011-2015, Serbia | ||||||
Evaluation Type: | Mid Term Project | ||||||
Status: | Completed | ||||||
Completion Date: | 10/2011 | ||||||
Planned End Date: | 10/2011 | ||||||
Management Response: | Yes | ||||||
Focus Area: |
|
||||||
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021) |
|
||||||
Evaluation Budget(US $): | 6,500 | ||||||
Source of Funding: | 00187 | ||||||
Joint Programme: | No | ||||||
Joint Evaluation: | No | ||||||
Evaluation Team members: |
|
||||||
GEF Evaluation: | No | ||||||
Key Stakeholders: | PPO, SAI | ||||||
Countries: | SERBIA |
Lessons | |
---|---|
Findings |
Recommendations | |
---|---|
1 | The projects management should improve systematic and documented monitoring of the project in the final phase of implementation |
2 | Reformulate activities in Outputs 2 and 3 Expert support provided for discussing Commissioner's /SAI reports and formulating recommendations in the Parliament by to suit the recent changes in the regulations affecting the relationship of the two institutions. |
Key Action Update History
Loading..
1. Recommendation: The projects management should improve systematic and documented monitoring of the project in the final phase of implementation
Management Response: [Added: 2011/12/23]
Use Atlas as monitoring tool
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Enter output targets in ATLAS and regularly updating the results against the targets
[Added: 2011/12/23] |
Project Manager | No due date | No deadline established | Throughout the project duration |
2. Recommendation: Reformulate activities in Outputs 2 and 3 Expert support provided for discussing Commissioner's /SAI reports and formulating recommendations in the Parliament by to suit the recent changes in the regulations affecting the relationship of the two institutions.
Management Response: [Added: 2011/12/23]
Budget/activities revision
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Budget revised and approved by the donor
[Added: 2011/12/23] |
Project Manager | 2011/12 | Completed | this recommendation has been already addressed |