Mainstreaming Marine Biodiversity Conservation into Coastal Zone Management in the Aqaba Special Economic Zone

Report Cover Image
Evaluation Plan:
2013-2017, Jordan
Evaluation Type:
Final Project
Planned End Date:
05/2015
Completion Date:
07/2015
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
8,500

Share

Document Type Language Size Status Downloads
Download document marine biodiversity evaluation report.docx report English 1237.70 KB Posted 713
Download document FTE_TOR_marine project.docx tor English 122.80 KB Posted 392
Download document 4002_GEFID 2251_Terminal SO2 TT_Jordan marine_final.xlsx related-document English 32.91 KB Posted 578
Title Mainstreaming Marine Biodiversity Conservation into Coastal Zone Management in the Aqaba Special Economic Zone
Atlas Project Number: 00078516
Evaluation Plan: 2013-2017, Jordan
Evaluation Type: Final Project
Status: Completed
Completion Date: 07/2015
Planned End Date: 05/2015
Management Response: Yes
Focus Area:
  • 1. Others
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
  • 1. Output 1.1. National and sub-national systems and institutions enabled to achieve structural transformation of productive capacities that are sustainable and employment - and livelihoods- intensive
  • 2. Output 2.1. Parliaments, constitution making bodies and electoral institutions enabled to perform core functions for improved accountability, participation and representation, including for peaceful transitions
Evaluation Budget(US $): 8,500
Source of Funding: GEF
Joint Programme: No
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
Francis Hurst Consultant
GEF Evaluation: Yes
Evaluation Type:
Focal Area: Biodiversity
Project Type: EA
GEF Phase: GEF-2
PIMS Number: 4002
Key Stakeholders: ASEZA
Countries: JORDAN
Lessons
Findings
Recommendations
1 Financial Planning within the AMP: Develop a Financial Plan and Strategy for the AMP Management Plan
2 Development of a substantive scenario planning exercise for ASEZA
1. Recommendation: Financial Planning within the AMP: Develop a Financial Plan and Strategy for the AMP Management Plan
Management Response: [Added: 2015/08/02]

Establishing a mechanism that would secure a sustainable and efficient financial resources for AMP

Key Actions:

2. Recommendation: Development of a substantive scenario planning exercise for ASEZA
Management Response: [Added: 2015/08/02]

Improvement of the planning system at ASEZA so as to be able to integrate environmental issues

Key Actions: