Energy Efficiency Standards and Labeling in Jordan

Report Cover Image
Evaluation Plan:
2013-2017, Jordan
Evaluation Type:
Final Project
Planned End Date:
12/2014
Completion Date:
01/2015
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
6,970

Share

Document Type Language Size Status Downloads
Download document EESL_Jordan_TE_Report_30_Jan_2015.pdf report English 1815.68 KB Posted 2171
Download document GEF_Tracking_Tool_EESL_Jan_2015_Dinesh.xls related-document English 108.50 KB Posted 344
Download document EE FTE TOR - Final.docx tor English 93.28 KB Posted 384
Title Energy Efficiency Standards and Labeling in Jordan
Atlas Project Number:
Evaluation Plan: 2013-2017, Jordan
Evaluation Type: Final Project
Status: Completed
Completion Date: 01/2015
Planned End Date: 12/2014
Management Response: Yes
Focus Area:
  • 1. Others
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
  • 1. Output 1.5. Inclusive and sustainable solutions adopted to achieve increased energy efficiency and universal modern energy access (especially off-grid sources of renewable energy)
Evaluation Budget(US $): 6,970
Source of Funding: GEF
Joint Programme: No
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
Dinesh Consultant INDIA
GEF Evaluation: Yes
Evaluation Type:
Focal Area: Climate Change
Project Type: MSP
GEF Phase: GEF-4
PIMS Number: 3735
Key Stakeholders: Ministry of Environment
Countries: JORDAN
Lessons
Findings
Recommendations
1 to have more regular board meetings
2 Inability to capture and account for baseline situation
3 Developing business plan for the Labs
1. Recommendation: to have more regular board meetings
Management Response: [Added: 2015/02/16]

The reason behind this is the change of team at the project management unit level during implementation phase of the project, in addition to all difficulties faced at the beginning of the project that caused delays in all project aspects including board meetings

Key Actions:

2. Recommendation: Inability to capture and account for baseline situation
Management Response: [Added: 2015/02/16]

At the design stage of the project, it is important to forecast and capture externalities that needed to be accounted for, yet, many of such externalities can be in a form of uncertainty, this can be cumbersome to account for and can be confusing during the implementation phase

Key Actions:

3. Recommendation: Developing business plan for the Labs
Management Response: [Added: 2015/02/16]

As Labs are being developed through different donors, a coordination effort is needed to understand each position in terms of operational life for developed labs

Key Actions: