Mid-term Evaluation of Regional Project Arab Youth for a Better Future

Report Cover Image
Evaluation Plan:
2015-2015, UNV
Evaluation Type:
Mid Term Project
Planned End Date:
06/2015
Completion Date:
06/2015
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
19,715

Share

Document Type Language Size Status Downloads
Download document AYV4BF MTE Report_June 2015.pdf report English 761.03 KB Posted 340
Title Mid-term Evaluation of Regional Project Arab Youth for a Better Future
Atlas Project Number:
Evaluation Plan: 2015-2015, UNV
Evaluation Type: Mid Term Project
Status: Completed
Completion Date: 06/2015
Planned End Date: 06/2015
Management Response: Yes
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
Evaluation Budget(US $): 19,715
Source of Funding:
Joint Programme: No
Mandatory Evaluation: No
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
GEF Evaluation: No
Key Stakeholders: UNDP, Governments
Location of Evaluation: Regional
Countries: EGYPTMOROCCOJORDANTUNISIAYEMEN
Lessons
Findings
Recommendations
1

Finalize on-going activities as relevant to the 4 outputs.

2

Verify the opportunity to implement a project second phase in the light of consolidation and sustainability.

3

Discuss with local partners/stakeholders, possibly in the context of the project board meeting, a project second phase and build a consensus.

4

Design a country based/multi-country project II phase with a participatory approach.

5

Conduct fundraising and secure funding for project second phase.

6

Reinforce management at field level, including one project manager and one project assistant referring directly to higher management level and relevant technique expertise from UNV HQs.

7

Reconsider the composition of national advisory committees (NAC) at country level to include fewer members and to operate as steering committees, thereby providing strategic guidance on the course of the project and allowing for relevant revisions, as opportune.

8

Explore regional collaboration with the provisions of MoU signed between UNV and the Arab Federation for Voluntary Activities (AFVA) under the patronage of the League of Arab States, and look at opportunities in relation to the establishment of the Arab Youth Observatory. 

1. Recommendation:

Finalize on-going activities as relevant to the 4 outputs.

Management Response: [Added: 2016/12/28]

This recommendation is accepted. Noting the considerable advances made towards the project results, finalizing the uncompleted activities is a priority. Strong partnerships have been established and nurtured through the project to promote volunteerism.  There is an overall drive to protect these gains.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
National and regional awareness activities - success stories and awards
[Added: 2016/12/28] [Last Updated: 2017/08/11]
AYVBF Project/Arab States PT-9 portfolio/Communications Section (CS) 2017/01 Completed The MBC Hope has decided to diversify its partnerships on their Annual Award; expanding it within and beyond the UN traditional. Accordingly, the AYVBF project has arranged to publish the Volunteers' success stories in a booklet and video. August 2017: The Arab Youth Project did not continue with a second phase. A similar project, Future Makers, is currently under implementation. A final report on project results is not available. However, the latest project progress available is that the awards ceremony was scheduled for January 2015 and the booklet was under development and scheduled to be completed in Q2 2015.
Re-consider the setting up of a web-based regional platform promoting networking, knowledge sharing and opportunities on volunteerism.
[Added: 2016/12/28]
Project / Arab states portfolio 2015/08 Completed A review of the current context and resources did not warrant the setting up of a regional platform. Current efforts focus on supporting existing platforms in Jordan and Egypt. This will strengthen national ownership and increase the likelihood of sustaining efforts.
Follow up with institutional/legal studies; conduct reports on policy gaps as feasible.
[Added: 2016/12/28] [Last Updated: 2017/08/11]
Project / Arab states portfolio 2016/03 No Longer Applicable [Justification: The Arab Youth Project was not continued for a second phase. A final report on the project is not available for follow up. ]
Policy gaps will be assessed in Egypt and Tunisia by Q1 2016. Tunisia’s national counterparts are engaged to ensure UNV’s work is part of upcoming legislative reforms on civil society. Follow up of previously completed assessments are ongoing in Morocco and Jordan
Publish the Training of Trainers manual and disseminate.
[Added: 2016/12/28] [Last Updated: 2017/08/11]
Project / Arab states portfolio, Communications Section (CS) 2015/12 No Longer Applicable [Justification: The Arab Youth Project was not continued for a second phase. A final report on the project is not available for follow up. ]
The review process is on-going at UNV Headquarters for clearance.
Promote national volunteers' scheme at CSOs level.
[Added: 2016/12/28] [Last Updated: 2017/08/11]
Project/Arab States Portfolio 2015/12 No Longer Applicable [Justification: The Arab Youth Project was not continued for a second phase. A final report on the project is not available for follow up. However, national volunteer promotion will feature significantly in the next UNV Strategic Framework. ]
As a pilot, a Moroccan UNV is working on volunteer management in a national CSO.
Equip project with adequate MIS and review indicators.
[Added: 2016/12/28]
Project/Arab States Portfolio 2015/09 Completed Output indicators were updated in the 2015 work plan to further substantiate results.
Conduct a final survey (i.e. web-based opinion poll)
[Added: 2016/12/28]
Project/Arab States Portfolio and Results Management Support Section (RMSS) 2016/06 Completed A final opinion survey was conducted as part of the project MTE in the 1st quarter of 2016. This led to the establishment of end-line data and gave insight to results.
Design and implement a resource mobilization strategy
[Added: 2016/12/28] [Last Updated: 2017/08/11]
Project/Arab States Portfolio in collaboration with Volunteer Resource and Recruitment Section (VRRS) 2015/12 Completed The resource mobilization strategy is drafted and now is being vetted. This task has been transferred to the PT9 due to the shortening of project lifetime and related activities. August 2017: The Arab Youth project was not continued for a second phase. However, the similar project, Future Makers is currently on-going. It is jointly funded by UNDP and UNV and implemented by UNDP. In addition, the UNV SF Evaluation makes recommendations related to development of resource mobilization strategies. Therefore, more overarching resource mobilization issues will be addressed through the implementation of that recommendation.
2. Recommendation:

Verify the opportunity to implement a project second phase in the light of consolidation and sustainability.

Management Response: [Added: 2016/12/28]

This recommendation is accepted. The results of the evaluation of this pilot project warrants an in-depth ex-ante evaluation to determine the future of the project.   Reflecting positive discussions between UNV SMT and UNDP CIS SMT during the conception of the MTE, a consultancy was designed to explore the possibility of expanding the current project in other countries/regions.

Key Actions:

3. Recommendation:

Discuss with local partners/stakeholders, possibly in the context of the project board meeting, a project second phase and build a consensus.

Management Response: [Added: 2016/12/28] [Last Updated: 2016/12/28]

This recommendation is accepted.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Exploratory missions with UNDP COs in Egypt and Turkey
[Added: 2016/12/28]
Project/Arab States Portfolio and UNV Strategic Management Team (SMT) 2015/12 Completed The project board meeting focused considerably on discussing opportunities for future programming in the identified countries (ECIS/RBAS Egypt).
4. Recommendation:

Design a country based/multi-country project II phase with a participatory approach.

Management Response: [Added: 2016/12/28]

This recomendation is accepted. This has been considered in the design of the new cross-regional youth volunteering and innovation pilot (UNDP/UNV-RBAS/RBEC).

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Consultancy mission for project proposal.
[Added: 2016/12/28]
Peace Programming Section (PPS)/Development Programming Section (DPS) / Programme Coordination Section (PCS)/ Office of the Executive Coordinator (OEC) 2015/09 Completed A consultancy based on the outcome and recommendations of the current Mid Term Evaluation - as a key reference- led to the drafting of the project proposal as the key outcome of this process.
Consultancy team mission and meetings at UNV HW
[Added: 2016/12/28]
Peace Programming Section (PCS)/ Development Programming Section (DPS)/ Programme Coordination Section (PCS) and Office of the Executive Coordinator (OEC) 2015/09 Completed
Concept note and proposal to be developed and submitted to UNV Project Approval Committee (PAC)
[Added: 2016/12/28]
Peace Programming Section (PPS)/ Development Programming Section (DPS)/ Programme Coordination Section (PCS) and Office of the Executive Coordinator (OEC) 2015/12 Completed
5. Recommendation:

Conduct fundraising and secure funding for project second phase.

Management Response: [Added: 2016/12/28]

This recommendation is accepted and will be featured in the new project proposal.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Once the concept note/proposal is endorsed by PAC, resource mobilization will begin.
[Added: 2016/12/28] [Last Updated: 2017/08/10]
PPS/DPS/PCS/Partnership Unit(PU) 2016/01 Completed A second phase of this project was not implemented. A similar project, Future Makers has been implemented without additional donors. It is funded by UNV and UNDP only.
6. Recommendation:

Reinforce management at field level, including one project manager and one project assistant referring directly to higher management level and relevant technique expertise from UNV HQs.

Management Response: [Added: 2016/12/28]

This recommendation is conditionally accepted. The feasibility will be determined as part of the new project structure/ arrangement.

Key Actions:

7. Recommendation:

Reconsider the composition of national advisory committees (NAC) at country level to include fewer members and to operate as steering committees, thereby providing strategic guidance on the course of the project and allowing for relevant revisions, as opportune.

Management Response: [Added: 2016/12/28]

This recommendation is accepted. Participating FUs have been advised accordingly

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Follow-up by the portfolio manager and POs in FUs
[Added: 2016/12/28] [Last Updated: 2017/08/10]
PPS/DPS Portfolios 2015/12 Completed The Regional Project Arab Youth for a Better Future has not been continued. However, a inter-regional project called Future Makers, implemented by UNDP, has been developed. National Advisory Committees are not part of the project.
8. Recommendation:

Explore regional collaboration with the provisions of MoU signed between UNV and the Arab Federation for Voluntary Activities (AFVA) under the patronage of the League of Arab States, and look at opportunities in relation to the establishment of the Arab Youth Observatory. 

Management Response: [Added: 2016/12/28]

This recommendation is accepted. Field Units have been advised and connected with representatives of the AFVA in the participating countries

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Closely engage and communicate with AFVA members at regional conferences, meetings
[Added: 2016/12/28]
AYVBF Field Units and Arab States Portfolio 2015/09 Completed The representatives of the AVFA have been involved in the partnership forum in China, in youth volunteer awards in Dubai, Arab volunteer day in Bahrain where the AYVBF lessons learnt were shared and discussed. The UNV-AFVA MOU has been extended through December 2017.