SUSTAINABLE FINANCING OF THE PROTECTED AREA SYSTEM IN MOZAMBIQUE MID-TERM REVIEW

Report Cover Image
Evaluation Plan:
2012-2016, Mozambique
Evaluation Type:
Mid Term Project
Planned End Date:
03/2015
Completion Date:
03/2015
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
19,900

Share

Document Type Language Size Status Downloads
Download document ToRs MTR Protected Areas.pdf tor English 1359.21 KB Posted 316
Download document MTR_3938_Moz_PA_Finance.pdf report English 1527.46 KB Posted 775
Download document Annex 3 _Progress towards Outputs at MTR.pdf related-document English 373.59 KB Posted 282
Title SUSTAINABLE FINANCING OF THE PROTECTED AREA SYSTEM IN MOZAMBIQUE MID-TERM REVIEW
Atlas Project Number: 65/62668
Evaluation Plan: 2012-2016, Mozambique
Evaluation Type: Mid Term Project
Status: Completed
Completion Date: 03/2015
Planned End Date: 03/2015
Management Response: Yes
Focus Area:
  • 1. Others
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
  • 1. Output 2.5. Legal and regulatory frameworks, policies and institutions enabled to ensure the conservation, sustainable use, and access and benefit sharing of natural resources, biodiversity and ecosystems, in line with international conventions and national
Evaluation Budget(US $): 19,900
Source of Funding: GEF
Evaluation Expenditure(US $): 20,000
Joint Programme: No
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
Brian J Huntley Independent Consultant
GEF Evaluation: Yes
GEF Project Title:
Evaluation Type:
Focal Area: Biodiversity
Project Type: EA
GEF Phase: GEF-1
GEF Project ID:
PIMS Number: 3839
Key Stakeholders: Ministry of Tourism, Carr Foundation, WWF
Countries: MOZAMBIQUE
Lessons
Findings
Recommendations
1 The Board must meet quarterly to ensure adequate project management and performance monitoring using the Project Results Framework as a guide.
2 The Project Management Unit must be restructured with strengthened leadership arrangements.
3 Training of the ANAC leadership and administration teams in financial management and project management must be focused and regular.
4 A facilitated workshop of key IPs and stakeholders must be convened to develop a shared understanding of the project objective and intended outputs, using the Logframe and Tracking Tools as integrative project management tools.
5 The extension of project by one year to compensate for the slow start is possible, but should be conditional on the restructuring of the PMU to ensure effective completion of component 1 activities and the integration of the three components into a whole greater than the sum of the parts.
6 The lack of a recognizable identity and the documentation and communication of the project?s achievements must be addressed.
1. Recommendation: The Board must meet quarterly to ensure adequate project management and performance monitoring using the Project Results Framework as a guide.
Management Response: [Added: 2015/12/14] [Last Updated: 2016/01/15]

Steering committees now being held in quarterly basis. Although there was disruption on the contract with the Senior Project Advisor, project results frameworks is being monitored by the technical team involving the 3 project components.

Key Actions:

2. Recommendation: The Project Management Unit must be restructured with strengthened leadership arrangements.
Management Response: [Added: 2015/12/14] [Last Updated: 2016/01/15]

In principle the setup fulfills the NIM approach. Additional capacity has been provided to the PMU on NIM procedures which are in line with Governments' procedures.

Key Actions:

3. Recommendation: Training of the ANAC leadership and administration teams in financial management and project management must be focused and regular.
Management Response: [Added: 2015/12/14] [Last Updated: 2016/01/15]

Training needs assessment was performed. Additional training content yet to be approved by ANAC Management before conducting capacity building activities.

Key Actions:

4. Recommendation: A facilitated workshop of key IPs and stakeholders must be convened to develop a shared understanding of the project objective and intended outputs, using the Logframe and Tracking Tools as integrative project management tools.
Management Response: [Added: 2015/12/14] [Last Updated: 2016/01/15]

The recommendation is accepted and will be implemented.

Key Actions:

5. Recommendation: The extension of project by one year to compensate for the slow start is possible, but should be conditional on the restructuring of the PMU to ensure effective completion of component 1 activities and the integration of the three components into a whole greater than the sum of the parts.
Management Response: [Added: 2015/12/14] [Last Updated: 2016/01/15]

The recommendation is accepted and will be implemented.

Key Actions:

6. Recommendation: The lack of a recognizable identity and the documentation and communication of the project?s achievements must be addressed.
Management Response: [Added: 2015/12/14] [Last Updated: 2016/01/15]

The recommendation will be addressed.

Key Actions: