Final Evaluations for Kashgar Tarim Basin Energy Forest Project

Report Cover Image
Evaluation Plan:
2016-2020, China
Evaluation Type:
Project
Planned End Date:
08/2017
Completion Date:
12/2016
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
10,000

Share

Document Type Language Size Status Downloads
Download document Terminal Evaluation report (final for submission) _20161223_V2.doc report English 580.00 KB Posted 293
Title Final Evaluations for Kashgar Tarim Basin Energy Forest Project
Atlas Project Number: 76089
Evaluation Plan: 2016-2020, China
Evaluation Type: Project
Status: Completed
Completion Date: 12/2016
Planned End Date: 08/2017
Management Response: Yes
Focus Area:
  • 1. Environment & Sustainable Development
  • 2. Others
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
  • 1. Output 1.3. Solutions developed at national and sub-national levels for sustainable management of natural resources, ecosystem services, chemicals and waste
Evaluation Budget(US $): 10,000
Source of Funding: Project budget
Evaluation Expenditure(US $): 10,000
Joint Programme: No
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
Yuan Dr Zhenhong
Zhang Dr Xuemei
Li Dr Yanfeng
GEF Evaluation: No
Key Stakeholders: Ministry of Environment
Countries: CHINA, PEOPLE'S REPUBLIC
Lessons
Findings
Recommendations
1

Conduct study on low cost desalination technology of brackish water, and the effects of drought and heat stress on the plant growth, and resolve the problem of moisture conservation for sand soil;

2

Select and breed species such as salt tolerance crops, forage grass and high value added plants which are suitable for the project;

3

integrate experimental research, ecological management demonstration and development of sand industry, which can be the inner power for the sustainable development of the project;

4

Conduct research on breeding and grafting technique of Xanthoceras Sorbifolia, including composition analysis and utilization of natural products. With continuing development of bio-fuel industry, attention should also be paid to the research & development of bio-chemical and bio-medical products; a base which combines the agriculture, forestry and animal husbandry would be built during the 13th Five-Year Plan period, with the ecological benefits from the project, the local environment can be improved. The establishment of this scientific and reasonable whole industry chain would do an evidently contribution to the local social and economic development.

5

Carry out scientific assessment of the underground water balance and ecological environmental risks of the project. Study the carbon sink process and ecological threshold during the cultivation of ecological forest and utilization of underground water. With the development project the technical specifications and standards of sand industry would be established, and the technical service team and the scientific achievements transformation platform would be formatted.

1. Recommendation:

Conduct study on low cost desalination technology of brackish water, and the effects of drought and heat stress on the plant growth, and resolve the problem of moisture conservation for sand soil;

Management Response: [Added: 2016/12/30]

The proposed studies could be considered as follow up activities should there be a Phase-II or related new project(s).

Key Actions:

2. Recommendation:

Select and breed species such as salt tolerance crops, forage grass and high value added plants which are suitable for the project;

Management Response: [Added: 2016/12/30]

The proposed selection of species, such as salt tolerance crops, forage grass and high value added plants, could be considered as follow up activities should there be a Phase-II or related new project(s).

Key Actions:

3. Recommendation:

integrate experimental research, ecological management demonstration and development of sand industry, which can be the inner power for the sustainable development of the project;

Management Response: [Added: 2016/12/30]

In implementation of the Kashgar project, establishment of Shiny leaf Yellow Horn plantations has been well integrated with academic research by The Minzhu Univeristy of Dalian and mixed plantation of different cash crops, which are elements of sand industry development for the region. More efforts could be made should there be a Phase-II or related new project(s).

Key Actions:

4. Recommendation:

Conduct research on breeding and grafting technique of Xanthoceras Sorbifolia, including composition analysis and utilization of natural products. With continuing development of bio-fuel industry, attention should also be paid to the research & development of bio-chemical and bio-medical products; a base which combines the agriculture, forestry and animal husbandry would be built during the 13th Five-Year Plan period, with the ecological benefits from the project, the local environment can be improved. The establishment of this scientific and reasonable whole industry chain would do an evidently contribution to the local social and economic development.

Management Response: [Added: 2016/12/30]

The recommendation could be considered should there be a Phase-II or related new project(s).  as key elements in the entire supply chain of bio-fuel industry in Xinjiang, the proposed breeding/grafting research for the targeted species should be given priority in a Phase-II or related new projects.

Key Actions:

5. Recommendation:

Carry out scientific assessment of the underground water balance and ecological environmental risks of the project. Study the carbon sink process and ecological threshold during the cultivation of ecological forest and utilization of underground water. With the development project the technical specifications and standards of sand industry would be established, and the technical service team and the scientific achievements transformation platform would be formatted.

Management Response: [Added: 2016/12/30]

The proposed assessment of underground water resources and environmental risks, as well as formation of technical service team and transformation platform, could be considered as key components as follow up activities should there be a Phase-II or related new project(s).

Key Actions: