Watershed services terminal evaluation

Report Cover Image
Evaluation Plan:
2016-2021, Tanzania
Evaluation Type:
Final Project
Planned End Date:
12/2020
Completion Date:
03/2021
Status:
Completed
Management Response:
No
Evaluation Budget(US $):
50,000

Share

Title Watershed services terminal evaluation
Atlas Project Number: 00086631
Evaluation Plan: 2016-2021, Tanzania
Evaluation Type: Final Project
Status: Completed
Completion Date: 03/2021
Planned End Date: 12/2020
Management Response: Yes
Focus Area:
  • 1. Environment & Sustainable Development
  • 2. Others
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
  • 1. Output 2.5. Legal and regulatory frameworks, policies and institutions enabled to ensure the conservation, sustainable use, and access and benefit sharing of natural resources, biodiversity and ecosystems, in line with international conventions and national
SDG Goal
  • Goal 15. Protect, restore and promote sustainable use of terrestrial ecosystems, sustainably manage forests, combat desertification, and halt and reverse land degradation and halt biodiversity loss
SDG Target
  • 15.2 By 2020, promote the implementation of sustainable management of all types of forests, halt deforestation, restore degraded forests and substantially increase afforestation and reforestation globally
Evaluation Budget(US $): 50,000
Source of Funding: GEF, UNDP
Evaluation Expenditure(US $): 50,000
Joint Programme: No
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
Nelson Gapare Mr gaparen@greensoftgmc.com
John Kessy Prof jfkessy2012@gmail.com
GEF Evaluation: Yes
GEF Project Title: Securing watershed services through SLM in the Ruvu and Zigi catchments (Eastern Arc Region).
Evaluation Type: Terminal Evaluation
Focal Area: Biodiversity
Project Type: FSP
GEF Phase: GEF-6
GEF Project ID: 5463
PIMS Number: 5077
Key Stakeholders: Ministry of Water, Vice President's Office, Local Government Authorities
Countries: TANZANIA (UNITED REPUBLIC OF )
Lessons
Findings
Recommendations
1

While it is noted that all projects are now required to prepare theories of change at the design phase, the TE team further recommends that both risks and assumptions are explicitly stated and validated with stakeholders.  During the project design, inadequate funding was identified as a key barrier to successful SLM, but no further analysis was undertaken to validate other underlying assumptions such as policy and statutory limitations. Further questions should have been raised at that point to critically assess the underlying causes of inadequate funding and if any lessons could be learnt from previous attempts under REDD+.  While it is noted that all projects are now required to prepare theories of change at the design phase, the TE team further recommends that both risks and assumptions are explicitly stated and validated with stakeholders.  During the project design, inadequate funding was identified as a key barrier to successful SLM, but no further analysis was undertaken to validate other underlying assumptions such as policy and statutory limitations. Further questions should have been raised at that point to critically assess the underlying causes of inadequate funding and if any lessons could be learnt from previous attempts under REDD+.  

2

Projects are encouraged to adequately use tools such as theories of change, problem tree analysis, or SWOT analysis to validate at the design phase and ensure adequate due diligence on significant output proposals that require high level intervention and or political support

Latest Evaluations

Contact us

1 UN Plaza
DC1-20th Floor
New York, NY 10017
Tel. +1 646 781 4200
Fax. +1 646 781 4213
erc.support@undp.org