Mid-Term Review and Lessons on Implementing the National Emergency Response Mitigation and Adaptation Plan 2016-2022
Share
Document | Type | Language | Size | Status | Downloads |
---|---|---|---|---|---|
![]() |
report | English | 2195.41 KB | Posted | 1477 |
![]() |
tor | English | 849.00 KB | Posted | 1185 |
Title | Mid-Term Review and Lessons on Implementing the National Emergency Response Mitigation and Adaptation Plan 2016-2022 | ||||||
---|---|---|---|---|---|---|---|
Atlas Project Number: | 00095112 | ||||||
Evaluation Plan: | 2021-2025, Eswatini | ||||||
Evaluation Type: | Project | ||||||
Status: | Completed | ||||||
Completion Date: | 05/2017 | ||||||
Planned End Date: | 05/2017 | ||||||
Management Response: | Yes | ||||||
Focus Area: |
|
||||||
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021) |
|
||||||
Evaluation Budget(US $): | 30,000 | ||||||
Source of Funding: | |||||||
Evaluation Expenditure(US $): | 6,500 | ||||||
Joint Programme: | No | ||||||
Joint Evaluation: | No | ||||||
Evaluation Team members: |
|
||||||
GEF Evaluation: | No | ||||||
Key Stakeholders: | National Disaster Management Agency ; Deputy Prime Ministers Office | ||||||
Countries: | ESWATINI |
Lessons | |
---|---|
Findings |
Recommendations | |
---|---|
1 | Disaster Planning and Management Capacities: Technical weaknesses in the design of the NERMAP were observed in the form of lacking a Results Framework. Recommendations: Develop the M&E Framework for the NERMAP with indicators and timelines, and ensure future response plans have Results Framework. Follow-up Plan: Develop M&E Framework for the NERMAP. Focal Point: NDMA – Programme Manager. |
2 | Management of Disasters: The 2014/2016 El Nino had an impact on-set in 2015, however the country declared the Disaster in 16th February 2016. Recommendation: Increase capacity for Early Warning Systems to facilitate timely decision making on escalation of impacts of disasters. Follow-up Plan: Timely and consistent SADC FEWSNET and national weather and climate information dissemination. Focal Point: National Meteorological Services (MET) and the National Early Warning Unit (NEWU) at the Ministry of Agriculture. |
3 | Resource Mobilization: Sufficient funding is critical for the successful implementation of an emergency response. In the case of the NERMAP financial and human resources were not sufficient to carry out the interventions in the plan as determined by needs on the ground. Recommendation: Develop the Resource Mobilization Strategy and facilitate its operationalization. Fast-track the establishment of funding for disasters through the Disaster Management Fund. Follow-up Plan: Develop the Resource Mobilisation Strategy and Action Plan; Develop the costed Multi-Hazard Contingency Plan (MHCP) 2017/2018; Obtain approval for the establishment of the Disaster Management Fund. Focal Point: NDMA Operations Manager |
4 | Sustainability: The NERMAP does not have a Phase-out plan for short-term NERMAP activities and output, yet some of these activities have the potential to create dependency on food aid. Recommendation: A clear phase-out plan should be developed, indicating a systematic scaling down of interventions without upsetting communities and beneficiaries (safe-landing). Follow-up plan: Develop the Resilience Strategy and Action Plan to enable food security sustenance and improved water resources management. |
5 | Knowledge Management: The establishment of Information and Knowledge Management processes at the NDMA to facilitate decision-making. Recommendation: Develop and implement the Disaster Risk Management Communication Strategy and Action Plan; build knowledge management capacities; Conduct topical research to inform policy and capacity development. Follow-up Plan: Develop Communication Plan and implement. Focal point: NDMA Communication Manager |
Key Action Update History
Disaster Planning and Management Capacities: Technical weaknesses in the design of the NERMAP were observed in the form of lacking a Results Framework.
Recommendations: Develop the M&E Framework for the NERMAP with indicators and timelines, and ensure future response plans have Results Framework.
Follow-up Plan: Develop M&E Framework for the NERMAP.
Focal Point: NDMA – Programme Manager.
Management Response: [Added: 2017/12/18]
Progress: Draft NDMA Strategy Plan has provisions for development of M&E Framework for response plans
Key Actions:
Management of Disasters: The 2014/2016 El Nino had an impact on-set in 2015, however the country declared the Disaster in 16th February 2016.
Recommendation: Increase capacity for Early Warning Systems to facilitate timely decision making on escalation of impacts of disasters.
Follow-up Plan: Timely and consistent SADC FEWSNET and national weather and climate information dissemination.
Focal Point: National Meteorological Services (MET) and the National Early Warning Unit (NEWU) at the Ministry of Agriculture.
Management Response: [Added: 2017/12/18]
Progress:
· Weather and climate information disseminated by FEWSNET and SADC Climate Change Unit.
MET and NEWU weather and climate information disseminated national-wide and key stakeholders.
Key Actions:
Resource Mobilization: Sufficient funding is critical for the successful implementation of an emergency response. In the case of the NERMAP financial and human resources were not sufficient to carry out the interventions in the plan as determined by needs on the ground.
Recommendation: Develop the Resource Mobilization Strategy and facilitate its operationalization. Fast-track the establishment of funding for disasters through the Disaster Management Fund.
Follow-up Plan: Develop the Resource Mobilisation Strategy and Action Plan; Develop the costed Multi-Hazard Contingency Plan (MHCP) 2017/2018; Obtain approval for the establishment of the Disaster Management Fund.
Focal Point: NDMA Operations Manager
Management Response: [Added: 2017/12/18]
Progress:
- Draft MCHP 2017/18 in place
- Resource Mobilisation Strategy under development by NDMA
Key Actions:
Sustainability: The NERMAP does not have a Phase-out plan for short-term NERMAP activities and output, yet some of these activities have the potential to create dependency on food aid.
Recommendation: A clear phase-out plan should be developed, indicating a systematic scaling down of interventions without upsetting communities and beneficiaries (safe-landing).
Follow-up plan: Develop the Resilience Strategy and Action Plan to enable food security sustenance and improved water resources management.
Management Response: [Added: 2017/12/18]
Progress:
Resilience Strategy and Action Plan 2017-2030 produced with support from UNDP
Key Actions:
Knowledge Management: The establishment of Information and Knowledge Management processes at the NDMA to facilitate decision-making.
Recommendation: Develop and implement the Disaster Risk Management Communication Strategy and Action Plan; build knowledge management capacities; Conduct topical research to inform policy and capacity development.
Follow-up Plan: Develop Communication Plan and implement.
Focal point: NDMA Communication Manager
Management Response: [Added: 2017/12/18]
Progress:
Disaster Communication and Advocacy Plan developed.
Key Actions: