Final Tuvalu Ridge to Reef Evaluations

Report Cover Image
Evaluation Plan:
2018-2022, Fiji
Evaluation Type:
Final Project
Planned End Date:
08/2021
Completion Date:
09/2021
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
30,000

Share

Document Type Language Size Status Downloads
Download document UNDPGEF-TE TORTuvalu R2R .doc tor English 335.00 KB Posted 820
Download document Final-Tuvalu-R2R-Terminal Evaluation UNDP-GEF.pdf report English 2988.07 KB Posted 887
Download document GEF BD Tracking Tool LS_130421.xls related-document English 582.00 KB Posted 800
Download document GEF IW Tracking Tool_LS130421.xls related-document English 473.00 KB Posted 819
Download document GEF LD Tracking Tool_LS130421 (2).xls related-document English 172.00 KB Posted 807
Download document TV R2R TE Clearance slip.docx.pdf related-document English 444.08 KB Posted 789
Title Final Tuvalu Ridge to Reef Evaluations
Atlas Project Number: 00086015
Evaluation Plan: 2018-2022, Fiji
Evaluation Type: Final Project
Status: Completed
Completion Date: 09/2021
Planned End Date: 08/2021
Management Response: Yes
Focus Area:
  • 1. Others
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021)
  • 1. Output 1.4.1 Solutions scaled up for sustainable management of natural resources, including sustainable commodities and green and inclusive value chains
Evaluation Budget(US $): 30,000
Source of Funding: GEF Trust Fund
Evaluation Expenditure(US $): 30,000
Joint Programme: No
Joint Evaluation: No
Evaluation Team members:
Name Title Nationality
Dima Reda Team Leader
GEF Evaluation: Yes
GEF Project Title: R2R Implementing a Ridge to Reef Approach to Protect Biodiversity and Ecosystem Functions in Tuvalu
Evaluation Type: Terminal Evaluation
Focal Area: Multifocal Areas
Project Type: FSP
GEF Phase: GEF-5
GEF Project ID: 5550
PIMS Number: 5220
Key Stakeholders: Departmnet of Environment, Ministry of Foreign Affiars, Trades, Tourism, Environment and Labour
Countries: FIJI
Lessons
Findings
Recommendations
1

Ensure that all technical reports produced by the project be available to the public after the end of the project

2

Expand the exit strategy to include annual costs for activities to be taken over by the government.

3

Organize a final workshop focusing on achievements of the project and the way forward

4
  1. A next phase project should focus on providing additional funding at the community level  
1. Recommendation:

Ensure that all technical reports produced by the project be available to the public after the end of the project

Management Response: [Added: 2021/12/12]

In Agreement

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Project Implementation Unit to ensure that copies of reports are saved and stored with the Department of Environment so that they are available to public
[Added: 2021/12/12] [Last Updated: 2022/03/06]
Project Management Unit/UNDP 2022/02 Completed completed History
2. Recommendation:

Expand the exit strategy to include annual costs for activities to be taken over by the government.

Management Response: [Added: 2021/12/12]

Agreement

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Revision of exit strategy and implementation
[Added: 2021/12/12] [Last Updated: 2022/03/06]
Department of Environment/UNDP 2022/02 Completed completed History
3. Recommendation:

Organize a final workshop focusing on achievements of the project and the way forward

Management Response: [Added: 2021/12/12]

agreement

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Finalization of agenda and facilitation workshop
[Added: 2021/12/12] [Last Updated: 2022/03/06]
Department of Environment 2022/02 Completed completed History
4. Recommendation:
  1. A next phase project should focus on providing additional funding at the community level  
Management Response: [Added: 2021/12/12]

Partially Agreement.  Accessing additional funding through another project can take between 2 -4 years. Therefore, suggesting that other projects in country should include providing additional funding for community level

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Indetify collaboration with existing iniatives/projects as well as exploring new funding avenues
[Added: 2021/12/12]
Department of Environment 2022/12 Not Initiated

Latest Evaluations

Contact us

1 UN Plaza
DC1-20th Floor
New York, NY 10017
Tel. +1 646 781 4200
Fax. +1 646 781 4213
erc.support@undp.org