Mid-term Evaluation; Strengthening Protected Areas Finance & Mngt System
Commissioning Unit: Egypt
Evaluation Plan: 2018-2022
Evaluation Type: Project
Completion Date: 11/2020
Unit Responsible for providing Management Response: Egypt
Documents Related to overall Management Response:
 
1. Recommendation:

Legislation to declare NCS as an autonomous general authority

Management Response: [Added: 2020/12/02]

continuous follow up with EEAA

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Follow up with EEAA through other ongoing biodiversity projects
[Added: 2020/12/02] [Last Updated: 2021/11/17]
NCS, EEAA 2022/09 Initiated But it seems it will not be completed in the near future. A decree was issued and presented to the parliament. However, it is not approved yet. History
2. Recommendation:

Financing strategy work need updating

Management Response: [Added: 2020/12/02]

More work is needed to update the national financing PA strategy

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Matching financial needs to the updated NBSAP
[Added: 2020/12/02] [Last Updated: 2021/11/17]
NCS EEAA 2021/10 Completed Financial needs were discussed and the NBSAP was updated. History
Recording al success stories related to implementation permit system
[Added: 2020/12/02] [Last Updated: 2021/11/17]
NCS EEAA 2021/10 Completed Permit system is in place for the Parks. Success stories related to the implementation is reflected in progress reports of the project. History
Matching the new global biodiversity targets
[Added: 2020/12/02] [Last Updated: 2021/11/17]
NCS 2021/10 Completed Reporting on the global biodiversity targets in reflected in the 6th National Report for Biodiversity. History
3. Recommendation:

Success and non success stories recorded

Management Response: [Added: 2020/12/02]

lesson learned documentation

Key Actions:

Key Action Responsible DueDate Status Comments Documents
projects to support sustainability and needed time for the bridging work for this work
[Added: 2020/12/02] [Last Updated: 2021/11/17]
NCS with Project managers for the two projects 2023/10 Not Initiated Delay due to COVID-19 pandemic History