Success message
error message
warn message
Terminal Evaluation; Strengthening Protected Areas Finance & Mngt System
Commissioning Unit: Egypt
Evaluation Plan: 2018-2022
Evaluation Type: Project
Completion Date: 11/2020
Unit Responsible for providing Management Response: Egypt
Documents Related to overall Management Response:
 
1. Recommendation:

Legislation to declare NCS as an autonomous general authority

Management Response: [Added: 2020/12/02]

continuous follow up with EEAA

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Follow up with EEAA through other ongoing biodiversity projects
[Added: 2020/12/02]
NCS, EEAA 2021/10 Initiated
2. Recommendation:

Financing strategy work need updating

Management Response: [Added: 2020/12/02]

More work is needed to update the national financing PA strategy

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Matching financial needs to the updated NBSAP
[Added: 2020/12/02]
NCS EEAA 2021/10 Not Initiated
Recording al success stories related to implementation permit system
[Added: 2020/12/02]
NCS EEAA 2021/10 Not Initiated
Matching the new global biodiversity targets
[Added: 2020/12/02]
NCS 2021/10 Not Initiated
3. Recommendation:

Success and non success stories recorded

Management Response: [Added: 2020/12/02]

lesson learned documentation

Key Actions:

Key Action Responsible DueDate Status Comments Documents
projects to support sustainability and needed time for the bridging work for this work
[Added: 2020/12/02]
NCS with Project managers for the two projects 2021/10 Not Initiated

Latest Evaluations

Contact us

1 UN Plaza
DC1-20th Floor
New York, NY 10017
Tel. +1 646 781 4200
Fax. +1 646 781 4213
erc.support@undp.org