Emergency Mine Action Final Evaluation
Commissioning Unit: Yemen
Evaluation Plan: 2019-2022
Evaluation Type: Project
Completion Date: 07/2021
Unit Responsible for providing Management Response: Yemen
Documents Related to overall Management Response:
 
1. Recommendation:

Capacity development is a key component of mine action development assistance. UNDP should continue to support the national institutions YMACC and YEMAC in developing national capacity to address the long-term humanitarian and development challenges caused by the threat of ERW. This will be realized through the continuation of provision of technical advisors to undertake all aspects of operational management to address the long-term humanitarian and development challenges posed by the presence of ERW, with other United Nations actors and international partners. 

Management Response: [Added: 2021/11/02]

UNDP recognizes the need to further strengthen the capacity of the national institutions. To this end the new intervention (EMP – Phase II) will focus on this matter as one of its priorities.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Conduct a capacity development assessment analysis to map the current capacity baselines of the YMACC and YEMAC and formulate a joint capacity development strategy
[Added: 2021/11/02] [Last Updated: 2022/02/14]
Project Team 2022/02 Completed The Project has developed and implemented the ‘Mine Action Capability Maturity Self-Assessment Tool – Yemen’ and the corresponding ‘C-IED Maturity Self-Assessment Tool’. These tools help measure the progress and maturity of the Mine Action and C-IED programmes in Yemen. History
Continue to enhance its support to national institutions via the new interventions
[Added: 2021/11/02]
Project Team 2023/06 Not Initiated
2. Recommendation:

UNDP responses should continue to enhance support to national institutions and authorities by building on lessons from the two different areas under IRG/DFA control with different speeds in project progress and achievements. This segmentation should be considered for a sustainable national ownership and utilizing closer engagement with national and international partners.

Management Response: [Added: 2021/11/02]

UNDP will support the strengthened links among its interventions as per the recommendation. It will also step up its efforts in the areas of C-IED and training national counterparts’ staff on how to manage new threats, among other maritime contamination

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Focus efforts on YMACC responsibilities regarding policy, through the monitoring and coordination of mine action that bring about change management and foster sustainable long-term challenges
[Added: 2021/11/08]
Project/Programme team 2023/12 Not Initiated
Enhance the link between Mine action, Peacebuilding and Rule of Law and inclusive sustainable recovery and development.
[Added: 2021/11/08]
project/programme team 2023/12 Not Initiated
Pursue dialogue with mine action partners to take necessary corrective and adaptative measures, and to reinforce synergies and coherence of interventions within and between portfolios and to consolidate achievements with a focus on C-IED and even maritime threat interventions
[Added: 2021/11/08]
project/programme team 2023/12 Not Initiated
3. Recommendation:

UNDP must multiply efforts into exploring partnerships and fostering cooperation among the UN system actors and agencies such as UNICEF, to leverage comparative advantages as opposed to setting up parallel systems, in the particular domain of mine risk education (MRE), explosive ordnance risk education (EORE) and improvised explosive device education as well as victim assistance (VA) for women and children

Management Response: [Added: 2021/11/02]

UNICEF and UNDP have been the two UN organization that have continuously supported their national counterparts with risk awareness efforts. The cooperation will continue and increase.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Continue to support the development of national mine action frameworks and monitor protection needs using the indicator of number of civilians killed or injured by ERW as planned in the HRP 2021
[Added: 2021/11/08]
project/programme team 2023/12 Not Initiated
Reinforce the coordination and learning of YMACC and effectiveness of YEMAC
[Added: 2021/11/08]
project/programme team 2023/12 Not Initiated
4. Recommendation:

UNDP Mine Action should reinforce its mechanism for planning, field monitoring and evaluation (M&E), risk management and results achieved or ongoing. This should feed into an updated theory of change (ToC) and their use in results management.

Management Response: [Added: 2021/11/02]

The Monitoring and evaluation (M&E) mechanism will focus on improving the communication on results, further showing local improvement in living conditions and community resilience including GEWE aspects. UNDP will provide additional support to the project through the advisors of its Country Office.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Reinforce its mechanisms for planning and monitoring and evaluation so that it can provide information based on concrete data and analysis on the outcome and impact
[Added: 2021/11/08] [Last Updated: 2022/02/14]
project/programme team M&E Analyst 2022/02 Completed the Project has included in its new Phase a revised set of indicators (attached file containing the revised Results Framework) which should improve the monitoring of the achievements in the field. In addition, the project has strengthened its team with an information management specialist with the support of Sweden’s MSB and has re-instated the post of Planning and Monitoring Specialist. These actions will respond to the matter raised during the terminal evaluation of the Project. History
Greater emphasis on communicating the positive changes resulting from Mine action supported interventions will be considered with a dedicated action plan.
[Added: 2021/11/08]
project/programme team Comms Unit 2023/12 Not Initiated
5. Recommendation:

UNDP should maintain and reinforce its efforts to strengthen the gender and diversity dimensions - for example persons with disabilities (PWD), the aged, marginalized tribes etc - of its mine action project and further support the structuration and capacities on women’s empowerment.

Management Response: [Added: 2021/11/08]

acknowledged

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Pursue the gender and diversity dimension, continuing to advocate for and facilitate women’s and other marginalized groups’ participation in Mine action and seek to increase the percentage of women in all activities
[Added: 2021/11/08]
project/programme team Gender Analyst 2023/12 Not Initiated
Aim at training of trainers for risk awareness sessions are gender balanced and work on introducing female quality assurance/quality control officers.
[Added: 2021/11/08]
project/programme team Gender Analyst 2023/12 Not Initiated
Raise the awareness of the targeted communities on gender to enhance their local acceptance of women to work in this field.
[Added: 2021/11/08]
project/programme team Gender Analyst 2023/12 Not Initiated