Disaster Resilience for Pacific SIDS (RESPAC) Terminal Evaluation
Commissioning Unit: Fiji
Evaluation Plan: 2018-2022
Evaluation Type: Project
Completion Date: 04/2021
Unit Responsible for providing Management Response: Fiji
Documents Related to overall Management Response:  
1. Recommendation:

Recommendation 1: In relation to future Project design to address some of the design issues encountered in the project, the TE recommends that UNDP consider the following in future project design:

 • Include a coherent overall design concept that links activities and targets with high level goals and aspirations that set the scene for project activities

• Include explicit provisions to address inclusion of women, youth and vulnerable people in project activities and outcomes, as well as reporting

• Include appropriate M&E provisions, including realistic indictors and targets that support clear reporting that, taken together, can be used to assist project management

• Incorporate flexibility and clear opportunities for stakeholder (i.e. participating country and territory) input into project management decisions

Management Response: [Added: 2021/05/17]

Agree. The listed recommendations to enhance project design will be taken into account for future project designs of development projects

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1.1 Future project documents will undergo rigorous PREPAC reviews and comments
[Added: 2021/05/17]
UNDP, IRMU 2021/12 Initiated
2. Recommendation:

Recommendation 2: In relation to future Project implementation Where procurement is a significant component of the project design, the TE recommends that specific expertise (or resources) be assigned to this aspect of the project to ensure quality [fitness for purpose] and timeliness in the procurement of goods and services

Management Response: [Added: 2021/05/17]

Agree. The above recommendation on specific expertise be assigned to specific scale of projects to support effective implementation of the project will be taken into account for future projects.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
2.1 For future projects on similar scale, procurement plan will be established as part of the project design phase before project is submitted for LPAC
[Added: 2021/05/17]
UNDP PAO, Procurement Unit 2021/12 Not Initiated
3. Recommendation:

Recommendation 3: On sustainability recognizing that there will be an ongoing need for support in the sectors targeted by this project, the TE recommends that UNDP work with donors to develop a follow-up project that continues and/or scales up the work, in line with relevant regional strategies and plans

Management Response: [Added: 2021/05/17]

Agree. This will be further informed through the final board meeting discussion for this project

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Sustainable Plan will be devised to determine key way forward
[Added: 2021/05/17]
PMU/UNDP/Govt counterparts 2021/12 Not Initiated