Terminal evaluation of NAMA Compost project
Commissioning Unit: Ethiopia
Evaluation Plan: 2021-2025
Evaluation Type: Project
Completion Date: 11/2021
Unit Responsible for providing Management Response: Ethiopia
Documents Related to overall Management Response:
 
1. Recommendation:

Evaluation recommendation 1.  There need to support SMEs by looking for ready markets for their products for social-economic sustainability to be achieved.

Management Response: [Added: 2021/11/17]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1.1. Promote compost to the nearby farmers
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU, MUDI, Cities 2021/12 Completed Action completed History
1.2. Create linkage with urban agriculture
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU, MUDI, Cities, UNDP 2021/12 Completed Action completed. History
1.3. Promote more utilization of organic fertilizers in collaboration with relevant organization and research institutions to create demand for compost which is directly linked with agricultural investment, and increased income
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU, Cities, UNDP 2021/12 Completed Action completed History
2. Recommendation:

Evaluation recommendation 2. The establishment of recreational centers with different facilities such as sports can help generate income and create more jobs for financial sustainability.

Management Response: [Added: 2021/11/17] [Last Updated: 2021/11/17]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
2.1.Establish neighbourhood parks and open public spaces by fulfilling all necessary facilities
[Added: 2021/11/17] [Last Updated: 2022/04/15]
PMU, Cities 2022/08 Initiated History
2.2. Diversify income-generating activities from recreational centers
[Added: 2021/11/17] [Last Updated: 2022/04/15]
PMU, Cities 2022/07 Initiated History
3. Recommendation:

Evaluation recommendation 3.  Law enforcement to protect the rehabilitated areas and sites from illegal land grabbing and encroachments into the project sites in collaboration with key stakeholders

Management Response: [Added: 2021/11/17]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
3.1 Insure all rehabilitated sites are secured title deed
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU, Cities, MUDI 2021/12 Completed Action completed History
3.2. Encourage community participation in afforestation/reforestation site management
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU, Cities 2021/12 Completed Action completed History
3.3. Develop bylaws and sign MoU with participating MSEs
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU, MUDI, Cities 2021/12 Completed Action completed History
4. Recommendation:

Evaluation recommendation 4.   Consider support afforestation and reforestation of 1,270ha of lands in five project cities.

Management Response: [Added: 2021/11/17]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
4.1. Planting tree seedlings on 1,270ha of land in and around project cities
[Added: 2021/11/17] [Last Updated: 2022/04/15]
PMU, Cities, MUDI 2022/07 Initiated History
4.2. Support and follow up
[Added: 2021/11/17] [Last Updated: 2022/04/15]
PMU, Cities 2022/07 Initiated History
4.3. Ensure Community Participation in planting and management of trees
[Added: 2021/11/17] [Last Updated: 2022/04/15]
PMU, MUDI, Cities 2022/07 Initiated History
5. Recommendation:

Evaluation recommendation 5.   Determining the survival rates of planted seedlings per annum starting from 2021.

Management Response: [Added: 2021/11/17]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
5.1. Coordinate and support estimation of survival rates of planted trees
[Added: 2021/11/17] [Last Updated: 2022/04/15]
PMU, Cities, MUDI 2022/07 Initiated History
5.2. Conduct refreshment training on standardized methods of planted tree survival rate estimation
[Added: 2021/11/17] [Last Updated: 2022/04/15]
PMU, Cities 2022/07 Initiated History
6. Recommendation:

Evaluation recommendation 6. Finalize procurement, distribution and installation of balling machine in the five cities. 

Management Response: [Added: 2021/11/17]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
6.1. Follow up and finalize procurement process of balling machine
[Added: 2021/11/17] [Last Updated: 2022/04/15]
PMU, Cities 2022/08 Initiated History
6.2 Distribute and install the balling machine in five project cities
[Added: 2021/11/17] [Last Updated: 2022/04/15]
PMU, Cities 2022/08 Initiated History
7. Recommendation:

Evaluation recommendation 7. Consider granting no-cost extension for the purpose of completing the remaining project activities by the PMU

Management Response: [Added: 2021/11/17]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
7.1. Consider granting a no-cost extension for the purpose of completing the remaining project activities by the PMU
[Added: 2021/11/17] [Last Updated: 2022/04/15]
UNDP, PMU 2022/09 Initiated History