Fight Against Social and Economic Exclusion
Commissioning Unit: Gambia
Evaluation Plan: 2002-2006
Evaluation Type: Project
Completion Date: 02/2003
Unit Responsible for providing Management Response: Gambia
Documents Related to overall Management Response:
 
1. Recommendation: sustain impact of the project
Management Response: [Added: 2009/12/14]

Successor project addressing employment formulated

Key Actions:

Key Action Responsible DueDate Status Comments Documents
New Project document entitle GAMJOBS forulated
[Added: 2009/12/14]
2007/01 Completed
Resources mobilisation strategy incorporated as an output in the project document
[Added: 2009/12/14]
2007/01 Completed
2. Recommendation: strengthen partnership
Management Response: [Added: 2009/12/14]

new project to seek parnters

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Identify and strengthen partnerships with national institutions
[Added: 2009/12/14]
2007/01 Completed
identify strengthen partenships with ILO and spain
[Added: 2009/12/14]
2007/01 Completed