Commissioning Unit: | Albania |
---|---|
Evaluation Plan: | 2022-2026 |
Evaluation Type: | Project |
Completion Date: | 06/2022 |
Unit Responsible for providing Management Response: | Albania
|
Documents Related to overall Management Response: |
Key Action Update History
Efforts should be made to complete all the activities envisaged by the ProDoc and disburse all the funds provided by the GEF grant. The PMU should closely monitor implementation of the activities.
Management Response: [Added: 2022/06/22]
Accept
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
The project is proceeding as per annual working plan. Almost all GEF funds are committed. Procedures are ongoing to commit the rest of GEF funds.
[Added: 2022/06/22] |
PMU/ UNDP and implementing partner | 2022/08 | Initiated | On track |
While the project’s exit strategy was finalised and discussed with partners and stakeholders, efforts should be made to achieve a smooth transition towards a post-project period in order to maintain the momentum and secure the sustainability of project’s results.
Management Response: [Added: 2022/06/22]
Accept
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Project implementation team is following the issue in close cooperation with the Exit Strategy consultant
[Added: 2022/06/22] |
PMU/ UNDP and Exit Strategy consultant | 2022/08 | Initiated | History |
Complete the Biodiversity Tracking Tool before the closure of the project. The last revision of the Tracking Tool was prepared on 15 December 2021, but one has to be prepared before the project will be closed.
Management Response: [Added: 2022/06/22]
Accept
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
PMU is working to complete the Biodiversity Tracking Tool.
[Added: 2022/06/22] |
PMU/ UNDP | 2022/07 | Overdue-Initiated | on Track |
In order to facilitate access to the knowledge base generated during the course of the Project, upload all technical documents produced with project support onto the project’s portal.
Management Response: [Added: 2022/06/22]
Accept
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
The technical documents and studies are being uploaded in the UNDP portal https://www.undp.org/albania/projects/enhancing-financial-sustainability-protected-areas-system-albania
[Added: 2022/06/22] |
PMU/ UNDP | 2022/08 | Initiated | On track |