Success message
error message
warn message
Fight Against Social and Economic Exclusion
Commissioning Unit: Gambia
Evaluation Plan: 2002-2006
Evaluation Type: Project
Completion Date: 09/2006
Unit Responsible for providing Management Response: Gambia
Documents Related to overall Management Response:
 
1. Recommendation: Sustain impact of project
Management Response: [Added: 2009/12/14]

Successor project addressing employment forumlated

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1.1 New project document entitle Gambia Priority Employment (GAMJOBS) was formulated
[Added: 2009/12/14]
2007/12 Completed
Resources Mobilization strategy incorporated as an output in the project document
[Added: 2009/12/14]
2008/12 Completed
2. Recommendation: Strengthen partnership
Management Response: [Added: 2009/12/14]

New project to seek partners

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Identify and strengthen partnership with national institutions
[Added: 2009/12/14]
2009/12 Completed
Identify and strengthen partnership with ILO and Spain
[Added: 2009/12/14]
2009/12 Completed
Complement and coordinate with world bank community driven development project (CDD)
[Added: 2009/12/14]
No due date No deadline established