Commissioning Unit: | Belarus |
---|---|
Evaluation Plan: | 2006-2010 |
Evaluation Type: | Project |
Completion Date: | 08/2009 |
Unit Responsible for providing Management Response: | Belarus
|
Documents Related to overall Management Response: |
|
Key Action Update History
Management Response: [Added: 2010/11/09]
Fully agree. Currently, the main tool used for planning is annual detailed work plan prepared for each project year, and approved by the national executing agency, Ministry of Environment, and UNDP. Development of an overall project work-plan for the full duration of the project appears to be a useful tool to ensure focused strategic planning. Develop. The plan is to be approved by UNDP Belarus and the national executing agency.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
An overall project work-plan for the full duration of the project will be developed
[Added: 2010/11/09] [Last Updated: 2011/04/15] |
PMU | 2009/12 | Completed | ||
The overall plan will be approved by UNDP Belarus and the Ministry of Environment of Belarus.
[Added: 2010/11/09] [Last Updated: 2011/04/15] |
PMU, UNDP, MoEnv | 2009/12 | Completed |
Management Response: [Added: 2010/11/09]
There were some delays during the first half of the project implementation which caused the project to fall behind the schedule with some activities implementation, particularly in case of demonstration of viability of alternative use of polders, and development of eco-tourism on the natural reserves territories. Project extension would allow achieving fully the project outputs, along with monitoring/verification of the effectiveness and sustainability of the project results. However, even no cost project extension means administrative additional expenses (project staff salaries, communication, etc). Currently, the project finish date is April 2011. An extension until end of 2011 can be considered. The decision of project extension (or not extension) should be based on evaluation of the results of project implementation in 2009- 2010, taking into account availability of funds to cover additional administrative expenses. It appears that the best time for extension consideration is end of 2010; and the extension should be endorsed by the Project Steering Committee (PSC).
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Close monitoring of project implementation with focus on project outputs.
[Added: 2010/11/09] [Last Updated: 2011/04/15] |
PMU, UNDP | 2010/12 | Completed | Monitoring of project implementation will continue through 2011 | |
Evaluation of project implementation and consideration of project extension at the end of 2010. In case of request for extension, it should be endorsed by the PSC
[Added: 2010/11/09] [Last Updated: 2011/04/15] |
PMU, UNDP, MoEnv and PSC | 2010/12 | Completed | Project has been extended till 31 Dec 2011 |