Fiji: Promoting Sustainability of Renewable Energy Technologies and Renewable Energy Sevice companies (Fiji)
Commissioning Unit: Fiji
Evaluation Plan: 2008-2012
Evaluation Type: Project
Completion Date: 10/2010
Unit Responsible for providing Management Response: Fiji
Documents Related to overall Management Response:
 
1. Recommendation: i. Evaluation Recommendation or Issue 1. Re-examine the Charter [and the draft RE Bill] in the context of the rural electrification policy, national energy policy, other current legislation and regulations to promote the use of renewable energy and, the proposed Fiji Sustainable Energy Bill.
Management Response: [Added: 2012/05/02] [Last Updated: 2012/05/02]

Project has ended. Key actions for Dept. of Energy, Fiji Govt. to take note of.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
3.1 Re-examine the modality of the RESCO Project Management Unit (Dept. of Energy, Fiji Govt)
[Added: 2012/05/02]
Dept. of Energy, Fiji Govt. No due date No deadline established Project has ended.
2. Recommendation: ii. Evaluation Recommendation or Issue 2: Further review the project documents including the draft outline of a RE Fund, the business model(s) for RESCOs, training programmes, among others so as to provide the basis for current proposed similar initiatives such as the Fiji Renewable Energy Power Project and the Sustainable Financing for Renewable Energy Project.
Management Response: [Added: 2012/05/02] [Last Updated: 2012/05/02]

Recommendation for Dept. of Energy to note

Key Actions:

Key Action Responsible DueDate Status Comments Documents
2.1. Further review the project documents including the draft outline of a RE Fund, the business model(s) for RESCOs, & training programmes;2.2. Ensure that the policy documents receives wider consultations to include women, community/traditional leaders(resource owners), academic institutions so that policy upstream can be realized.2.3 Ensure that governance mechanisms are in place to minimize risks of mismanagement of resources.
[Added: 2012/05/02]
Dept. of Energy, Fiji Govt. No due date No deadline established Project has ended
3. Recommendation: i. Evaluation Recommendation or Issue 3: Re-examine the modality of the RESCO Project Management Unit and consider an arrangement that would encourage and allow for a better participation of the private sector, including CSO?s in the implementation of similar energy initiatives.
Management Response: [Added: 2012/05/02] [Last Updated: 2012/05/02]

Project has ended. Key actions recommended are for Dept. of Energy, Fiji Govt.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
3.1 Re-examine the modality of the RESCO Project Management Unit
[Added: 2012/05/02]
Dept. of Energy, Fiji Govt. No due date No deadline established Project has ended