Success message
error message
warn message
HIV Programme Evaluation
Commissioning Unit: Viet Nam
Evaluation Plan: 2006-2011
Evaluation Type: Others
Completion Date: 05/2009
Unit Responsible for providing Management Response: Viet Nam
Documents Related to overall Management Response:
 
1. Recommendation: Delay in starting implementing project activities in provinces due to lack of human resources
Management Response: [Added: 2009/10/16]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Project personnel had been employed and kept project running well
[Added: 2009/10/16]
Project Management Unit 2009/06 Completed Projects have been successfully completed, set good models for replication.
2. Recommendation: Lack of clear guidelines for project implementation from beginning
Management Response: [Added: 2009/10/16]

Partly agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
NEX manual and training had been provided to project staff at the start up of the project and NEX training was provided to any new project staff recruited during the lifetime of the projects. In addition, UNDP staff had also been regularly providing assistance and instructions to project staff.
[Added: 2009/10/16]
UNDP 2009/06 Completed Projects have been successfully completed, set good models for replication.