Management Response: [Added: 2014/12/19]
SAJI needs more funding to bring these current achievements into their fully matured phases that can make sure their sustainability and functionality to benefit the people on the ground
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Resource mobilizations
[Added: 2014/12/19] [Last Updated: 2018/11/07] |
DGPRU | 2014/12 | Completed | History |
Management Response: [Added: 2014/12/19]
For resource mobilization strategy, SAJI public relation materials for donors are to be developed, the government agencies (BAPPENAS, Ministry of Law and Human Rights, Ombudsman, pilot Provinces) endorsement that demands continued project supports is to be pronounced. In the fields, SAJI activities are being tailored with substantial resource sharing from the government partners.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
- Production of the printed material of a video on the SAJI?s results for donors audience;
- Exhibition of the project results for the donors
- Project board meeting (with the government partners) that discussed the current project?s need for more resource mobilization.
- Technical assistances and monitoring to the government partners agencies on the shared budget allocation for the project activities implementation, resulted in More government partners agencies that allocate their own budget to support implementation of the project activities; for example on the legal aid, BPHN has allocated IDR 50 billion, on PCM, the Bener Meriah government allocated IDR 100 million, for informal justice strengthening, Aceh government allocated IDR 1 billion.
[Added: 2014/12/19] |
DGPRU | 2014/12 | Completed | Done |
Management Response: [Added: 2014/12/19]
This recommendation has been shared with BAPPENAS on which they agree to make the role of the Secretariat more effective and sustainable. In order to enhance its function, the Strategic Coordination Team on Access to Justice comprising BAPPENAS, Ministry of Law and Human Rights, the Cabinet Secretariat and the Ministry of Interior has just been established through the BAPPENAS minister?s decree. the decree also prescribed clearer functions of the Secretariat. Furthermore, in order to enhance government ownership and attract more supports from development partners to functioning of the A2J secretariat, the Project will gradually detach the Secretariat from being managed under the SAJI team and will be placed back under full auspice of BAPPENAS and operated by the government hired staffs. As a transitional measure, SAJI will build a separate team to continue serve the secretariat and will directly report to and work under the close guidance of the BAPPENAS. For the legal cover of NSA2J, the SAJI team has been in process of revising the current NSA2J document as to make it adhered to the government format for the presidential regulation.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
- Support for issuance of the BAPPENAS? minister?s decree that clarifies mandate and function and coordination team of the A2J secretariat
- Support for an establishment of the A2J team separated from SAJI team.
- Revision of NSA2J document to make it adhere to the presidential regulation document.
[Added: 2014/12/19] [Last Updated: 2018/11/07] |
PMU SAJI | 2015/07 | Completed | History |
Management Response: [Added: 2014/12/19]
In response, SAJI has allocated substantial resources to implement awareness rising and socialization activities on the legal aid, PCMs, and informal justice mechanisms.
Key Actions:
Management Response: [Added: 2014/12/19]
If substantial additional funding is obtained, portion of activities supports for the two provinces of Maluku and North Maluku will be made increased.
Key Actions:
Management Response: [Added: 2014/12/19]
Small provincial field team is to be established with the arrival of new additional funding.