Success message
error message
warn message
Vietnam Energy Efficiency Public Lighting (VEEPL) End of Project Evaluation
Commissioning Unit: Viet Nam
Evaluation Plan: 2006-2011
Evaluation Type: Project
Completion Date: 07/2011
Unit Responsible for providing Management Response: Viet Nam
Documents Related to overall Management Response:
 
1. Recommendation: Final impact report While the project´s outputs and deliverables have been extensively reported, what is missing for future reference is a ´Final report´ that integrates the results and impacts of the various components and outputs and presents it in one, easy-to-read, document.
Management Response: [Added: 2011/08/12]

Because the project is closed in June 2011, It cannot make the final impact report instead we will discuss and transfer to the Government to do this and note in UNDP/SDC.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1.1 Discussed at the next Project Steering Committee meeting on and the Transfer & Dissemination Workshop on 19 June 2011; 1.2 Transferred to Vietnam Academy of Science & Technology (VAST) related documents following the recommendation: 1) Project document; 2) Project terminal report; 3) Project terminal evaluation 4) Database and M&E tool. 1.3 Took notes in project monitoring and development of UNDP/SDC.
[Added: 2011/08/12]
PMU/SDC 2011/06 Completed
2. Recommendation: Options for future efforts on EEPL: The momentum generated by VEEPL must be maintained for a more widespread dissemination of EE PL.
Management Response: [Added: 2011/08/12]

This is discussed and transferred to the Government to follow-up options for future as well as noted in UNDP/SDC when closing project at the end of June 2011

Key Actions:

Key Action Responsible DueDate Status Comments Documents
2.1 Discussed at the next Project Steering Committee meeting and the Transfer & Dissemination Workshop on 19 June 2011; 2.2 Transferred to government agencies and relevant stakeholders project products: 1) Standardized designs of new and expanded EEPL system for streets; 2) Standardized Designs of new and expanded EEPL system for primary, secondary, and high schools; 3) Investment plan for the National Lighting Product Quality Certification; 4) Vision and 2011 ? 2020 investment plan for R&D research development of the Vietnam lighting industry; 5) A handbook "Guidelineon technical-economic tools for EEPL management" with the calculation software; 6) M&E tools; 7) Results of pilot rating program of EEL; 8) Appropriate lighting control center model for the cities of first and second level; and 9) Results of GHG emission factor calculation. 2.3 Handovered project websites with database and equipment to VAST to continue communication and dissemination on the project results as well as advocate for new policy, strategy, plan and guidelines. 2.4 Took notes in project monitoring and development of UNDP/SDC.
[Added: 2011/08/12]
PMU/SDC 2011/07 Completed
3. Recommendation: New project proposal on LEDs
Management Response: [Added: 2011/08/12]

The new project proposal on LED will be transferred to UNDP and VAST to develop in future.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
3.1 Discussed at the Project Steering Committee meeting and the Transfer & Dissemination Workshop on 19 June 2011; 3.2 Transferred to UNDP and MOST to develop. 3.3 Took notes in project monitoring and development of UNDP/SDC.
[Added: 2011/08/12]
PMU/SDC 2011/06 Completed

Latest Evaluations

Contact us

1 UN Plaza
DC1-20th Floor
New York, NY 10017
Tel. +1 646 781 4200
Fax. +1 646 781 4213
erc.support@undp.org