Management Response: [Added: 2013/09/02]
The PRF is updated since the last one prepared (last May 2012) and approved by the Project Steering Board in mid June 2013. All due parameters are updated in the PRF.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Update of the Project Result Framework
[Added: 2013/09/02] |
Project Manager | 2013/06 | Completed |
Management Response: [Added: 2013/09/02]
Calculations of emissions reduction due to project activities as well as actions taken by the City complementary to the scope of the project will be performed end of 2013/beginning of 2014, as to take into account ongoing and planned activities in the second half of 2013.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
City-wide survey amongst the active population on cycling
[Added: 2013/09/02] [Last Updated: 2016/11/18] |
Project manager | 2013/10 | Completed | History | |
Survey on the trips to schools by the primary pupils
[Added: 2013/09/02] [Last Updated: 2016/11/18] |
Project Manager | 2013/11 | Completed | History | |
Report on the eco-driving training
[Added: 2013/09/02] [Last Updated: 2016/11/18] |
Project Manager | 2013/12 | Completed | History | |
Calculation of emissions caused by transport and saving achieved by the project and the city partners
[Added: 2013/09/02] [Last Updated: 2016/11/18] |
Project Manager Project partners (City of Belgrade) | 2014/01 | Completed | History |
Management Response: [Added: 2013/09/02]
Recommendation accepted.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Implementation of Work Plan approved by Project Steering Board
[Added: 2013/09/02] [Last Updated: 2018/09/04] |
Project Manager, UNDP Project partners (City of Belgrade) | 2013/12 | Completed | History |
Management Response: [Added: 2013/09/02]
The UNDP CO will take the necessary steps to provide adequate follow-up and support the project team in project implementation as of September 2013.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Backstop project implementation, including engagement of external/additional expertise to support implementation, if and as required.
[Added: 2013/09/02] |
UNDP | 2013/09 | Completed |
Management Response: [Added: 2013/09/02]
The project will advocate for, and offer support to national partners to adopt the project-developed websites beyond the project lifetime. The project will continue in further dissemination of the project goals and activities through other networks and sites and invest additional efforts in improving the dissemination.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Provide recommendations and support to the City of Belgrade in adopting the cycling web-site at the end of the Project.
[Added: 2013/09/02] [Last Updated: 2016/11/18] |
Project Manager Project partners (City of Belgrade) | 2014/03 | Completed | History | |
Continue networking and disseminating with other partners/projects
[Added: 2013/09/02] [Last Updated: 2018/09/04] |
Project Manager | 2013/12 | Completed | History |
Management Response: [Added: 2013/09/02]
The project will continue to maintain an active dialogue with project partners and support the defining of priorities of the City relevant to the scope of the project for the following years. The project will continue to support the City to mobilize resources in addition to the EBRD-grant (EUR 400,000) already realized in support of the finalization of the Belgrade SUTP.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Provide support and advice to the City in defining priorities and RM opportunities, and the development of continuing programmes in support of sustainable transport and urban development.
[Added: 2013/09/02] [Last Updated: 2018/09/04] |
Project Manager Project partners (City of Belgrade) | 2013/12 | Completed | History |
Management Response: [Added: 2013/09/02]
The project will provide continue its support to the project partners in further dissemination of the project outcomes and sharing the lessons learned with other Serbian towns and municipalities. As part of the dissemination and replication process, the Project will prepare a project document for Novi Sad in order that the city will be able to pursue further the preparation of the SUTP. Novi Sad has been selected based on the fact that it is a second city in Serbia in terms of size of agglomeration and has expressed strong interest in following the path of sustainable urban and transport planning and development. The Project will continue maintaining a network of partners and sharing of results through local, regional and international channels.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Translation of SUTP guidelines into Serbian, and dissemination of all related documents/deliverables online (http://www.beoland.com/sutp2013/default_s.htm and http://www.biciklirajbeogradom.com/eng/post-international-conference-sutp2013/post-conference-organisers-address/)
[Added: 2013/09/02] |
Project Manager | 2013/07 | Completed | ||
Preparation of a project document on Sustainable Transport for Novi Sad
[Added: 2013/09/02] [Last Updated: 2016/11/18] |
Project Manager City of Novi Sad | 2013/11 | Completed | History | |
Organize 6 workshops in Belgrade on the subject of sustainable urban transport planning, as part of the first component (SUTP).
[Added: 2013/09/02] |
Project Manager Project partners (City of Belgrade) | 2013/05 | Completed | ||
Organize an international two-day conference on SUTP
[Added: 2013/09/02] |
Project Manager Project partners (City of Belgrade) | 2013/05 | Completed |
Management Response: [Added: 2013/09/02]
The cycling web-site will be upgraded and improved by also linking it to similar sites of other cities providing relevant and comparable information.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
The web-site on cycling will be upgraded and linked to other similar cites and sites.
[Added: 2013/09/02] [Last Updated: 2016/11/18] |
Project Manager Project Assistant | 2013/10 | Completed | History |
Management Response: [Added: 2013/09/30]
Through the SRS campaign the project will continue emphasizing the benefits of walking for the youngest. As part of the SRS campaign, a gaming approach to provide incentives are foreseen, considering the MTE given examples and using a tailor-made approach for the context of Belgrade, in cooperation with teachers, parents and psychologists.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Implement games/competition in the framework of the SRS-Pedibus campaign during school year 2013/14
[Added: 2013/09/30] [Last Updated: 2016/11/18] |
Project Manager Primary schools Project partners (City of Belgrade) | 2014/04 | Completed | History | |
Workshop for pupils and parents on the health aspects of alternative transport modes
[Added: 2013/09/30] [Last Updated: 2016/11/18] |
Project Manager Primary schools Project partners (City of Belgrade) | 2013/10 | Completed | History |
Management Response: [Added: 2013/09/30]
The implementation of the eco-driving component is planned to start mid June 2013, with expected first results by end of 2013. The State Agency on Road Safety will take part in the eco-driving trainings and be awarded one certificate/license in eco-driving. A one-day workshop will be held at the end of the eco-driving trainings to disseminate the results and effects of this new approach to the wider audience of stakeholders and beneficiaries.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Provide recommendations to the authorities in charge of driving schools to include ?eco-driving?
[Added: 2013/09/30] [Last Updated: 2016/11/18] |
Project Manager Partners/Direct beneficiaries of the eco-driving Project partners (City of Belgrade) | 2014/01 | Completed | History |
Management Response: [Added: 2013/09/30]
During the process of preparation of the first SUTP phase, comparisons to French and English cities have been done and a conclusion was drawn by all parties that in the case of Belgrade a tailor-made approach is needed due to its complexity in terms of urban set-up and sprawl, topographic configuration and location on the cross-road of two pan- European corridors. The Land Development Agency (LDA), as direct beneficiary of this project, has considered this MTE recommendation and considers it not beneficial or relevant given the context of Belgrade; as stated in their written statement (see Annex 1). The project will continue an active dialogue with the project partners, to support them in the further development of the SUTP, in line with the scope of the project and drawing on adequate, comparable case studies, as appropriate
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Continue the dialogue and partnership with the Land Development Agency of Belgrade on the topics of sustainable urban transport development and planning, drawing on adequate, comparable expertise
[Added: 2013/09/30] [Last Updated: 2018/09/04] |
Project Manager Project partners | 2013/12 | Completed | History |
Management Response: [Added: 2013/09/30]
The project will increase dissemination of good practice from comparable cities through established networks of cycling associations, groups and institutions, as well as promote activities undertaken by third-party actors at city, national level or regional level.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Invite speakers from the European Cycling Federation and the German Cycling Associations to attend a workshop in September in Belgrade on promotion of cycling within the European Mobility Week
[Added: 2013/09/30] |
Project Manager | 2013/09 | Completed | ||
Further networking and liaising with the cycling associations and other relevant actors in Belgrade
[Added: 2013/09/30] [Last Updated: 2018/09/04] |
Project Manager | 2013/12 | Completed | History |
Management Response: [Added: 2013/09/30]
In the process of preparing projects on Safe Routes to Schools (SRS) to other four schools, the project will give a recommendation to the project partners on better implementation of traffic calming measures and coordination of actions taken by the City and the Project.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Preparation of a study on SRS for four primary schools in Belgrade, which inter alia takes into account traffic calming measures
[Added: 2013/09/30] [Last Updated: 2016/11/18] |
Project Manager Project partners (City of Belgrade) | 2014/01 | Completed | History | |
In the framework of the final report, provide recommendations to the City on further traffic calming measures
[Added: 2013/09/30] [Last Updated: 2016/11/18] |
Project Manager Project partners (City of Belgrade) | 2014/04 | Completed | History |
Management Response: [Added: 2013/09/30]
The project will increase information dissemination and involvement of a wide stakeholder group in forthcoming project activities, within the project scope and as adequate.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Increase dialogue with local and national partners on project relevant topics, aimed at ensuring increased stakeholder participation and ownership
[Added: 2013/09/30] [Last Updated: 2018/09/04] |
Project Manager Project partners (City of Belgrade) National authorities | 2013/12 | Completed | The Project already cooperates with all relevant City partners and authorities but also at national level with all relevant Ministries by also maintaining liaisons with the donors? community active in the area of transport, environment and climate change. As one of the merits to the project deep involvement and lobbying, the national authorities have increased the scope of the programming cycles 2014-17 by introducing support to the urban transport as one of the three key priorities in the transport sector. Further, the national authorities are considering revising the transport policy by embracing urban transport and creating a favorable legal framework for the establishment of the SUTPs. History |
Management Response: [Added: 2013/09/30]
The project will provide recommendation to the City authorities to actively participate in relevant city networks, and continues supporting the City authorities in awareness raising and capacity strengthening in the related domains.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Communicate experience from the project through several EU related sites (ELTIS, Transport and Research, Civitas, ICLEI).
[Added: 2013/09/30] [Last Updated: 2018/09/04] |
Project Manager | 2013/12 | Completed | History | |
Disseminate knowledge and experience of the project through / with the Standing Conference of Towns and Municipalities (SCTM) and related networks
[Added: 2013/09/30] [Last Updated: 2018/09/04] |
Project Manager City of Novi Sad SCTM | 2013/12 | Completed | History | |
Through component 4, develop a full-fledged project document on SUTP for Novi Sad
[Added: 2013/09/30] [Last Updated: 2016/11/18] |
Project Manager City of Novi Sad | 2013/11 | Completed | History |