Commissioning Unit: | Maldives |
---|---|
Evaluation Plan: | 2011-2015 |
Evaluation Type: | Project |
Completion Date: | 05/2014 |
Unit Responsible for providing Management Response: | Maldives
|
Documents Related to overall Management Response: |
|
Key Action Update History
Management Response: [Added: 2014/05/08]
Agreed
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Prepare detailed written agreement about handover processes and procedures to include clear and specific detailed roles and responsibilities and timing, including aspects such as transfer of staff, transfer of capital assets, maintenance and operations support agreements, etc
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
UNOPS Project Team | 2014/05 | Completed | The handover period had been messy and protracted, however this was completed before the end of the project History |
Management Response: [Added: 2014/05/08]
Partially Agree: Agree that system handover and start-up phase is the most critical part of the project and the handover need to be supported. Do not agree with the reallocation of funds from Outputs 1.4, 3.2 and 3.3 as they are critical to the Project objectives. No cost savings from Outputs 1.1-1.3 are anticipated at this stage
Key Actions:
Management Response: [Added: 2014/05/08]
Agreed
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
FENAKA to approve the tariff structure sent by MEE in May 2013 and obtain approval from the regulatory body (EPA)
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
MEE/FENAKA | 2014/06 | Completed | MEE has shared the tariff structure developed by the project and is awaiting approval from FENAKA board. While a tariff structure was agreed at a policy level, it's implementation was difficult History |
Management Response: [Added: 2014/05/08]
Partially Agree ? Risk of not finishing the infrastructure component of the project by the PB agreed date of July 2014 is higher and needs UNOPS to address in detail the immediate risks. Overall project risks are reviewed every 6 months by the PMU, UNDP, UNOPS.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
UNOPS to send detailed risks and mitigation measures for project by the newly agreed handover date in September 2014.
The preparation of the handover agreement (Recommendation 1) will also have to address these risks.
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
UNOPS | 2014/03 | Completed | While risks and mitigation measures were developed the project faced many hurdles in completion History |
Management Response: [Added: 2014/05/08]
Agreed
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
MEE will communicate the information on planned construction and operations before construction begins.
-UNDP to lead and start the IWRM awareness campaign
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
UNDP | 2014/09 | Completed | Activity was not completed by due date but the awareness campaign was completed before project closure History |
Management Response: [Added: 2014/05/08]
Agreed
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
UNDP to prepare a new Quarterly Progress Report format that will further strengthen results-based reporting by including linkages between activities, expenditures and achievement of project indicator targets
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
UNDP | 2014/07 | Completed | New Quarterly Progress Report format was used History |
Management Response: [Added: 2014/05/08]
Agreed
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Key Action(s)
No action taken as the recommendation is beyond the project?s scope. No problems associated with the current project management have been identified by the MTE.
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
N/A | 2011/01 | No Longer Applicable |
[Justification: No action taken as the recommendation is beyond the projects scope. ] History |
Management Response: [Added: 2014/05/08] [Last Updated: 2014/05/08]
Partially Agree.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Project has already agreed that the staff trained for operation and maintenance of the system will be absorbed into FENAKA to ensure the sustainability of the plant operation. Training of trainers is beyond the scope and fund availability of the project. Staff handover time to be decided from the actions under Recommendation 1.
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
MEE | 2014/11 | Completed | Trainings were conducted to operators, however not all staff initially recruited continued History |
Management Response: [Added: 2014/05/08] [Last Updated: 2014/05/08]
Partially Agree. Households have limited capacity to store rainwater. The understanding is that households will store rainwater to their full capacity regardless of the tariff amount. Therefore the amount of rainwater that the community will contribute to the water supply system is already estimated based on this understanding
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
MEE will advocate with FENAKA on what needs to be done in order for such a rebate can be established within the tariff system and whether there is anything that can be done through the project to establish
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
MEE | 2014/06 | Completed | Tariffs was IWRM systems was established through a policy decision History |
Management Response: [Added: 2014/05/08]
Agreed
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
MEE will advocate with FENAKA on what needs to be done in order for such a rebate can be established within the tariff system and whether there is anything that can be done through the project to establish
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
MEE | 2014/06 | Completed | Initial dialogue has already been undertaken History |
Management Response: [Added: 2014/05/08]
Partially Agree. Project already has three staff stationed in the islands who are playing the role of communications and liaising with the community with the assistance of the PMU
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Knowledge products created through the project will be implemented via the existing staff stationed in the islands.
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
PMU/UNDP | 2015/10 | Completed | Throughout the lifespan of the project History |
Management Response: [Added: 2014/05/08]
DISAGREE. The groundwater management aspect of the project remains a crucial element of IWRM and therefore this project. The project aims to demonstrate a pilot mechanism for groundwater recharge in at least one island. There is sufficient funding and time to do this.
Key Actions:
Management Response: [Added: 2014/05/08]
Agreed
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Already addressed in Recommendation 4
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
N/A | 2011/01 | Completed | History |
Management Response: [Added: 2014/05/08]
Partially Agree. Agree that future revenue generating opportunities are necessary for the sustainability of the system. However, determining what these activities will be is outside the scope of this project. System was designed with the involvement of all stakeholders including utilities company and private sector
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
No action required as the recommendation is beyond the scope of the project.
[Added: 2014/05/08] |
2014/03 | Completed |
Management Response: [Added: 2014/05/08]
Agreed
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
UNOPS PMU taper the staff to ensure that the required technical support is available until project end in 2015. This includes engineering based technical support as well as project management support.
[Added: 2014/05/08] [Last Updated: 2018/09/16] |
UNOPS | 2014/06 | Completed | History |
Management Response: [Added: 2014/05/08]
Partially Agree. The project undertook a Willingness-to-pay study where a 10 year financial forecasting was undertaken. This information will be available for future donors and other projects to use in order to explore options
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
No action since the recommendation applies to future donor projects and is beyond the scope of this project
[Added: 2014/05/08] |
2014/05 | Completed |