Bhutan Recovery and Reconstruction Project
Commissioning Unit: Bhutan
Evaluation Plan: 2008-2013
Evaluation Type: Project
Completion Date: 01/2012
Unit Responsible for providing Management Response: Bhutan
Documents Related to overall Management Response:
 
1. Recommendation: Project planning
Management Response: [Added: 2012/03/06]

For future recovery and reconstruction and/or disaster risk management projects, recommendations of the terminal evaluation are: - Increasing provisions for public education and awareness on disaster response and management; - Consideration of multi-hazard planning that integrates DRR and climate change adaptation measures in all sectors - Adopting a multi-sector approach involving relevant sectors such as the DoC, MoE, MoH, MoAF and MoWHS, to improve project implementation;. - ?Build Back Better? schemes should look beyond infrastructure; - Provision of adequate resources to improve response coordination through establishment and operationalization of Emergency Operation Centre?s (EOCs) in all districts - Community development plans should align their mandates with the current institutional environment. - Establish appropriate institutions and legal mechanisms, including identification of relevant actors, especially at the local level, in order to enable the implementation of the DM Act (when enacted); - Develop technical and managerial capacity of the Department of Disaster Management. - Strengthening of insurance companies to deal with rapid assessments and disaster compensation, as well as development of insurance models and livestock and crop insurance

Key Actions:

Key Action Responsible DueDate Status Comments Documents
UNDP and DDM will discuss and develop a work plan to address the need for immediate recovery support following the 2011 earthquake. This will be discussed in cooperation with MoWHS-DES and MoHCA-DoC and focus on capacity development of artisans and engineers
[Added: 2012/03/06]
UNDP and DDM 2012/03 Completed
UNDP and DDM and key stakeholders will discuss and consider how to address the above recommendations as part of the design of a new disaster risk management project/programme, including the need for longer term institutional strengthening of DDM in view of the expected enactment of the DM bill by mid/end 2012.
[Added: 2012/03/06] [Last Updated: 2012/12/27]
UNDP 2012/12 Completed The CO submitted a detail proposal to UNDP/BCPR on a Comprehensive DRM programme for Bhutan addressing the above issues, but despite submission to 2 subsequent Bureau PACs, the proposal was not considered due to lack of resources and other priorities of BCPR.