Documents Related to overall Management Response:
 
1. Recommendation: Project budgets should be re-visited to ensure adequacy for financing project activities if there a significant time lag between project design and project implementation.
Management Response: [Added: 2015/01/15] [Last Updated: 2015/01/15]

Will work with Government in this regard as appropriate.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Engagement of all relevant stakeholders early in the project formulation stage as well as reviewing activities if there is a lag between design and implementation
[Added: 2015/01/15] [Last Updated: 2018/11/26]
Line Ministries as appropriate 2015/01 No Longer Applicable [Justification: UNDP is not responsible for this key action. ]
Stake holder engagement done by Government officials History
2. Recommendation: Continue the public awareness programme emphasising the benefits of a comprehensive and integrated approach to island resource management as a prerequisite for sustainable economic development, and build this into the work programme of an appropriate government agency.
Management Response: [Added: 2015/01/15]

Will work with Government in this regard as appropriate, as well as work through Small Grants Programme

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Support the efforts of community groups in Antigua and Barbuda to formally register and seek small grants to continue and expand project activities.
[Added: 2015/01/15] [Last Updated: 2018/11/26]
Line Ministries as appropriate 2015/01 No Longer Applicable [Justification: UNDP is not responsible for this key action.]
Government has increased liaison with SGP and NGOs. History
3. Recommendation: Aggressively support the establishment and operationalization of the Antigua and Barbuda Sustainable Island Resource Framework (SIRF) Fund, and support the activities identified to be supported under the Fund
Management Response: [Added: 2015/01/15]

Continued support to be given to government

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Continue to advocate for the necessary changes in institutional arrangements required to effectively operationalize SIRF to be identified and implemented.
[Added: 2015/01/15] [Last Updated: 2018/11/26]
Line Ministry 2015/01 Completed SIRF operationalised in 2016. History
Aggressively support the establishment and operationalization of the Antigua and Barbuda Sustainable Island Resource Framework (SIRF) Fund, and support the activities identified to be supported under the Fund.
[Added: 2015/01/15] [Last Updated: 2018/11/26]
Line Ministry 2015/01 Completed The SIRF was operationalised in 2016. History