Commissioning Unit: | South Africa |
---|---|
Evaluation Plan: | 2013-2020 |
Evaluation Type: | Project |
Completion Date: | 05/2015 |
Unit Responsible for providing Management Response: | South Africa
|
Documents Related to overall Management Response: |
|
Key Action Update History
Management Response: [Added: 2015/08/05]
UNDP, SABS and DoE have agreed on the content of the draft Memorandum of Agreement. DoE is working on securing the Director-General?s signature before SABS signs off.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Securing the Director-General?s signature before SABS signs off.
[Added: 2015/08/05] |
DoE and SABS | 2015/06 | Completed |
Management Response: [Added: 2015/08/05]
This recommendation will be discussed with the Chief Director and DDG for consideration.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Organising a discussion with the Chief Director and DDG for consideration
[Added: 2015/08/05] |
DoE | 2015/06 | Completed |
Management Response: [Added: 2015/08/05]
This recommendation will be discussed with the Chief Director & DDG for consideration. Recommendation accepted. The arrangement for a temporal appointment of the administrative assistant for a 6 month period is an expedient measure pending the results of the MTR process. However, the extension of the contract period will be subject to the Project Assistant?s performance during the first six month.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Discussion with the Chief Director & DDG for consideration
[Added: 2015/08/05] |
DoE | 2015/06 | Completed | ||
Extension of the contract based on the Project Assistant?s performance during the first six month
[Added: 2015/08/05] [Last Updated: 2017/12/13] |
UNDP | 2015/11 | Completed | History |
Management Response: [Added: 2015/08/05]
Recommendation accepted. UNDP has committed to write a letter to UNDP-GEF unit justifying the extension of the project to September 2017 (dependent upon signing of the DoE-SABS MoA.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Write a letter to UNDP-GEF unit justifying the extension of the project to September 2017
[Added: 2015/08/05] [Last Updated: 2017/12/13] |
UNDP | 2015/10 | Completed | History |
Management Response: [Added: 2015/08/05]
Recommendation accepted. The Work Plan will be drafted and presented in the next PSC meeting. However, this extended Work Plan is subject to approval of the extension period by UNDP/GEF.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Work Plan will be drafted and presented in the next PSC meeting
[Added: 2015/08/05] [Last Updated: 2017/12/13] |
DoE/PMU | 2015/11 | Completed | The extended Work Plan is subject to approval of the extension period by UNDP/GEF. History |