Commissioning Unit: | Malaysia |
---|---|
Evaluation Plan: | 2013-2015 |
Evaluation Type: | Project |
Completion Date: | 02/2014 |
Unit Responsible for providing Management Response: | Malaysia
|
Documents Related to overall Management Response: |
|
Key Action Update History
Management Response: [Added: 2014/12/23]
All the 10 recommendations have been discussed in the NSC meeting. The necessary actions have been proposed and taken up. In summary: Recommendation 1: Revision of the Planning Matrix and Budgeting - This is an ongoing activity where the project team has proposed some concrete measures. However, it needs to be further verified by the independent consultant and finally approved by RTA. This is planned to be completed by Mar 2015. Recommendation 2: Refocus the key Component 1 outputs - The project team has adopted the recommendation. The C1 shall now include monitoring as one of the focus. Recommendation 3: Put the emphasis of Component 3 EE Financial Mechanism Capacity Improvements on the ESCO business model - ESCO and energy performance contracting have been incorporated in the recent activities. For instance, the project team has conducted trainings and capacity buildings for a certified Perfomance contracting module. Recommendation 4: Revised Component 5 budget to include purchase of monitoring systems and inclusion of best practices in energy management. - The project team has proposed a set of measures. This recommendation has linked with Recommendation no1 and will be finalized during the PPM review. Recommendation 5: Extend the network of implementation partners - The necessary actions have been taken up. Recommendation 6: Filling up the vacant positions - All positions now have been filled in. Recommendation 7: Recruitment of the Chief Technical Advisor (CTA) - CTA has been engaged. Recommendation 8: Project Duration Extension - Extension has been proposed and agreed by NSC and the Government of Malaysia. Recommendation 9: Improvement to Progress and Planning Reports - Action has been taken up and resolved. Recommendation 10: Timely scheduling of the NSC and PRC Meetings - Timely scheduling for NSC/PRC meetings have been organized accordingly.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Revision to the Planning Matrix and Budgeting
[Added: 2017/04/09] |
Project Team | 2015/03 | Completed | Completed as planned | |
Refocusing key Component 1 outputs to place priority on development and rollout of the integrated monitoring system (IMS) that is the National Energy Consumption Monitoring System and Data Analysis.
[Added: 2017/04/09] |
Project Team | 2015/03 | Completed | Adopted recommendation as planned. | |
Incorporating the ESCO business model and EPC modality in Component 3.5 output (EE Financial Mechanism Capacity Improvements)
[Added: 2017/04/09] |
Project Team | 2015/03 | Completed | ||
Revised Component 5 budget to include purchase of monitoring systems and inclusion of best practices in energy management.
[Added: 2017/04/09] |
Project Team | 2015/03 | Completed | Measures proposed and finalised during PPM review | |
Extending the network of implementation partners
[Added: 2017/04/09] |
Project team | 2015/06 | Completed | Potential partners have been identified and included within the network | |
Vacant positions in the project to be filled
[Added: 2017/04/09] |
Project team | 2015/12 | Completed | All positions have now been filled. | |
Recruitment of Chief Technical Advisor
[Added: 2017/04/09] |
Project Team | 2015/06 | Completed | Position has been filled. | |
Extending the Project Duration
[Added: 2017/04/10] |
Project Team and UNDP | 2015/12 | Completed | Project Extension agreed by NSC and Government of Malaysia | |
Improving the project management namely progress reporting and project meetings
[Added: 2017/04/10] |
Project team | 2015/09 | Completed | Measures have been introduced to improve the quality of the progress and planning reports, as well as the planning of the NSC and PRC meetings. |