Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Management is addressing the matter by ensuring that before the end of 2014, the appropriate structure and legislative frameworks are in place to ensure sustainability.
Key Actions:
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Management takes note of the observations. The Project logframe cannot be revised at this stage. The project main indicators will be evaluated at the end of the project.
Key Actions:
Management Response: [Added: 2013/09/10]
Management takes note of the delayed MTR and this has been explained in the PIR under Adjustments. The late start of the project in 2009 as opposed to 2007 as was initially planned was the delayed approval of the financial clearance of the project by the GEF given this project was funded under the remains of GEF III allocations. With the extension of the closing date this will not have any significant impact on project implementation. The recommendations of the MTR will be taken on board between now and end of the project.
Key Actions:
Management Response: [Added: 2013/09/10] [Last Updated: 2014/01/14]
Management takes note of the recommendation and agrees with the first part of the recommendation which is to further develop the capacity of the PAHS at the Seychelles Agricultural Agency. However, management does not necessarily agree with the second part of the observation that PAHS is not the best institution to have the overall responsibility for biosecurity in Seychelles. Given the context of scare human resource and the institutional setup, the PAHS is the best institution to drive the project and to ensure sustainability after the end of the project. Appropriate capacity development and strengthening of the institution will be maintained during the remainder of the project, with the Biosecurity Advisor working closely with the SAA and PAHS personnel. The project continues to work closely with agencies responsible for Customs, Public Health, Trade and Environment to strengthen Biosecurity functions.)
Key Actions:
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
The Request for Extension has already been completed and granted. No further action
Key Actions:
Management Response: [Added: 2013/09/10] [Last Updated: 2014/01/14]
The work plan prepared for 2013 and 2014 has captured the essence of the monitoring required for the remainder of the project. The OVIs however will not be amended at this stage, but the workplan will ensure that the targets set in the original logframe are met at the end of the project. The new workplan for the new PM as well as for the extension of the Biosecurity Advisor has taken into account the MTR recommendations.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Revise work-plan for 2013 and 2014 to integrate recommendations of the MTR.
Update the Risk Log in ATLAS for 2013/14
[Added: 2013/09/10] [Last Updated: 2014/01/14] |
Project Manager Biosecurity Advisor | 2013/04 | Completed | New work-plan completed for 2013 and 2014 and approved. New Risk Log prepared and updated in ATLAS as well as management responses. |
Management Response: [Added: 2013/09/10] [Last Updated: 2014/01/14]
Noted. The PCU will ensure that co-financing is captured on a yearly basis from co-financiers and reflected in the PIRs and the Evaluation Reports. This has been institutionalized as a requirement within the revised agreement between Government and the PCU to ensure that Government reports its own co-financing accurately and supports other institutional co-financiers to do the same. The SC meeting chaired by the MEE will request and review the updated co-financing at least once a year before the preparation of the PIRs. All project co-financier are fully aware of the concept and no further explanation is required.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Co-financing will feature as an item on the SC meetings. Yearly returns from project co-financers will be requested by the SC Chairman and reports prepared by the PM for the Project SC and for the annual PIR on co-financing expenditure.
[Added: 2013/09/10] [Last Updated: 2014/01/14] |
Project Manager Programme Coordination Unit | No due date | No deadline established | This is an ongoing process which will be completed when project ends. |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Noted. The Management does not agree with the observation as all data and records are provided to the PCU as well as to the auditors during the NIM audits. This project has been audited twice already during its lifetime. The issue of recording against the wrong account code has been noted as it was highlighted in previous audit reports, which explains the obesetrvation of over expenditure on project management budgets. Management will undertake necessary actions to ensure proper recording on budget lines are maintained.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
The follow up action plan of the last audit has already taken care of this observation. The 2013 and 2014 work-plan has correctly budgetd the cost of the Biosecurity Advisor across the outcomes instead of under Project Management Cost as was previously the case with the Financial Reporting from the Project Coordination Unit.
[Added: 2013/09/10] |
Project Manager- Programme Coordination Unit | 2013/05 | Completed | New work-plan has already taken care of this recommendation |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Management takes note of the recommendations. If funds available this can be undertaken as GEF project provides only for terminal evaluation and not ex-post evaluations
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
No further action required at this stage from project management.
[Added: 2013/09/10] |
GEF | No due date | No deadline established | This can only be acted upon if GEF decides on ex-post evaluation for projects |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
The project objectives are in line with SSDS but needs to pay attention to the recommendations and ensure a coordinated approach for prevention and control of IAS. The necessary institutional and legislative frameworks being developed under the project will all be aligned to the objective of the SSDS.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Strengthen Biosecurity Strategy
Improve M &E framework
Develop Emergency and Rapid Response Protocols by end of Project. The revision of the Biosecurity Bill can only take place after it is reviewed by the Attormey General?s Office and Cabinet of Ministers.
[Added: 2013/09/10] [Last Updated: 2014/12/15] |
Project Management Unit- Ministry of Environment Biosecurity Advisor PCU | 2014/09 | Completed | Biosecurity Project Completed and recommendation now taken on board in New Biosecurity Bill |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Noted. The remainder of the project is addressing this recommendation for the revision of the Strategy as well as establishment of the appropriate M & E Framework.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
The project will define the institutional and management framework for the agencies involved in IAS and how the Biosecurity Strategy will be implemented. The appropriate M & E Framework is being developed.
[Added: 2013/09/10] [Last Updated: 2014/12/15] |
Biosecurity Advisor Project Manager PCU | 2014/09 | Completed | The further requirements for development of strategic interventions for biosecurity noted in the SSDS are also taken up within the 2014 revision of the NBSAP. |
Management Response: [Added: 2013/09/10] [Last Updated: 2014/01/14]
The project focussed more on building awareness rather than on a communication plan however this recommendation has been taken on board and targeted awareness campaigns will be created as part of the overall awareness programme for all GEF projects that's being developed by the PCU and implemented early on in 2014.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
A short film that will be featured on local channels as well as on board flights will be developed.
Banners, leaflets and Website to be used to disseminate information. The PCU has recruited a Communications Officer since January December 2012 and awareness of all projects is being undertaken by the PR Officer. The project will work on specific awareness and educational programmes to be implemented till the end of the project.
[Added: 2013/09/10] [Last Updated: 2014/12/15] |
Communication Officer/Biosecurity Advisor Project Manager-PCU UNDP Country Office | 2014/09 | Completed | Film produced and now being shows on incoming air Seychelles flight |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Noted. This recommendations has been addressed in the recommendations above
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Actions will follow as outlined in #10 above
[Added: 2013/09/10] [Last Updated: 2014/12/15] |
Same as #10 above | 2014/06 | Completed | The ERP has been developed |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Noted. The PS of MENR is now the Chair of the NIASMC with the PS of MEE and the Commissioner of Public Health are also on the committee. The appropriate sub-committee will be established
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Committee has been revived and at the last SC held in August 2013, the proposal was tabled for establishment of the appropriate subcommittees.
[Added: 2013/09/10] |
MEE Project Manager Biosecurity Advisor | 2013/12 | Completed | Action completed for the main Committee and pending for the subcommittees. The subcommiteees will be established by Dec 2013 |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Management has taken note of the detailed recommendations. Overall this is a repeat of recommendation #11
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
No further action. Addressed at #11 above
[Added: 2013/09/10] |
Same as #11 above | No due date | No deadline established | Same as #11 above |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Management takes note of the recommendation and will ensure additional training is carried out by the Biosecurity Advisor up to the end of the project to build capacity of the PAHs. Appropriate booklet and guide will be further updated and use during the training
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
The PM and the Biosecurity Advisor have prepared a Training Plan for PAHS and SAA for up to end of the project. Training is organized at regular (weekly)intervals both formal training and on-site training.
All training materials developed will be part of the project and will be used as future reference by the PAHS and staff of the Biosecurity Agency.
[Added: 2013/09/10] [Last Updated: 2014/01/14] |
Project Manager Biosecurity Advisor PCU | 2013/12 | Completed | Training Plan Prepared and Various Training activities carried out throughout 2013 by the Biosecurity Advisor and the new PM. The Training will also continue through 2014. |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Recommendation noted and will be implemented during remainder of the project
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
PM will ensure that PAHS database is updated and maintained.
[Added: 2013/09/10] [Last Updated: 2014/12/15] |
Project Manager PCU Biosecurity Advisor | 2014/11 | Completed | This has been initiated and will be completed with the completion of the Project in Nune 2014 |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Recommendations noted and will be implemented as part of the remainder of the project.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Border Control mechanisms will incorporate the risk of IAS to Seychelles. Rating of risk will be provided to the border control agents. The functioning of the Biosecurity Service will be implemented even if not formal structure or institution will be established. The function of the service will be distributed among existing agencies with appropriate protocols and guidelines and processes established and well defined to ensure functioning inter-agency coordination
[Added: 2013/09/10] [Last Updated: 2014/12/15] |
Project Manager PCU Biosecurity Advisor | 2014/11 | Completed | Current risk analysis procedures require adequate assesment of the risks to the environment/biodiversity and there are mechanisms to ensure these are done by adequately qualifed officers. Specific procedures will developed to with import of biological control agents and beneficial organisms |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Noted. Will be part of the ongoing activities of the project up to EOP
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
The Biosecurity Advisor and the PCU will discuss the matter with the SAA and the PAHS and appropriate measures will be implemented on site.
[Added: 2013/09/10] [Last Updated: 2014/01/14] |
Project Manager/ Biosecurity Advisor- PCU, SAA, PAHS | No due date | No deadline established | Ongoing process. Garbage disposal remains a concern because of the number of parties involved. The project team with work the ED, SAA and the other parties involved to ensure biosecurity risks associated with aircraft and sea vessels are adequately addressed. |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Recommendation noted and addressed under 11 above
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Project Manager and Biosecurity Advisor will establish the appropriate structure as part of the broader institutional framework.
[Added: 2013/09/11] |
PM/Biosecurity Advisor, PCU | No due date | No deadline established |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/11]
Recommendation Noted.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Project Manager and Biosecurity Advisor will raise this issue with the
National Biosecurity Committee in Q3 or early Q4 2013. The National IAS Committee (a sub-committee of the NBC) will be tasked to establish this network, supported by the project.The National IAS Committee has been established as a sub-committee of the NBC.
[Added: 2013/09/11] [Last Updated: 2014/12/15] |
PM/Biosecurity Advisor, PCU | No due date | No deadline established | A framework for a IAS knowledge and learning network will be established in Q4 2013.The National IAS Committee has been establised as a sub-committee of the NBC but has not met in 2013. The issue will be discussed at the next NBC/IAS Committee meeting in Q1 of 2014. |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/11]
Noted. Awareness has been captured under Recc # 12 above
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Same actions as in #12
[Added: 2013/09/11] |
No due date | No deadline established |
Management Response: [Added: 2013/09/10] [Last Updated: 2013/09/10]
Management has taken note of the recommendation and this is being addressed during the remainder of the project. the contract of the Biosecurity Advisor has been extended and terms of reference amended to ensure that this recommendation is clearly addressed. The remaining task of the Biosecurity Advisor is to complete the establishment of the IAS management tools and further awareness-raising activities at national level