Mid Term Evaluation - Solar Water Heater (Global Prog)
Commissioning Unit: India
Evaluation Plan: 2013-2017
Evaluation Type: Project
Completion Date: 01/2013
Unit Responsible for providing Management Response: India
Documents Related to overall Management Response:
 
1. Recommendation: Establish Independently Verifiable Baseline and Progress Indicators
Management Response: [Added: 2013/07/31] [Last Updated: 2013/07/31]

Appointing a consultant to review the LFA was discussed at the 32nd PEC held in Pune. It was decided that a team comprising of MNRE & UNDP would finalise the need for further action.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
A suitable independent consultant be retained to undertake an independent study of the applicable project baseline and of the indicators of project inputs and results so that a useful final project evaluation can be undertaken.
[Added: 2013/07/31]
2013/01 Completed
2. Recommendation: Focus Remaining Project Funds on Residential SWH Market
Management Response: [Added: 2013/07/31] [Last Updated: 2013/07/31]

The project is making significant efforts to address the residential sector. The same needs to be highlighted. Further funding allocation would not be possible as already balance of the project funds is already committed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
A number of key residential sector SWH focused activities are apparently not yet started or remain unfinished.
[Added: 2013/07/31] [Last Updated: 2017/06/23]
UNDP 2013/12 Completed Activities in the residential sector were taken up and completed such as low cost solar water heater model developed and tested. History
If necessary the project end date should also be extended to enable these and other recommendations to be fully implemented
[Added: 2013/07/31] [Last Updated: 2017/06/23]
UNDP 2013/12 Completed Activities completed as per scheduled History
3. Recommendation: Consolidate and Learn from Completed SWH Studies
Management Response: [Added: 2013/07/31] [Last Updated: 2013/07/31]

A national workshop was conducted during August 2012 where the studies and manuals produced under the project was released and exhibited. The consulting firms are also advised to sell the reports. In fact, PMC will also buy them as and when required.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Consultants with expertise in capturing and synthesizing lessons learned from the studies and providing a way forward to future needs should be recruited for the task
[Added: 2013/07/31]
2013/01 Completed
4. Recommendation: Expedite MNRE Subsidy Payments to SWH Manufacturers
Management Response: [Added: 2013/07/31] [Last Updated: 2013/07/31]

Actions are underway by MNRE. It is suggesting that the manufacturer provide online information which further expedites the payments. During the MASMA [Maharashtra Solar Manufacturers Association] meeting on 4th June this was highlighted by MNRE with MASMA.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
MNRE must urgently address this issue of the timely reimbursement of SWH subsidies to approved SWH manufacturers, for a target maximum reimbursement period on receipt of paperwork by SWH manufacturers of say 2 - 6 weeks. The MNRE SWH subsidies are the main part of the India GSWH project co-funding, and delays in the MNRE subsidy?s disbursement (as was reported to the MTR reviewers) would undo much of the benefit of the SWH growth support provided by the India GSWH project.
[Added: 2013/07/31] [Last Updated: 2017/06/23]
MNRE 2013/12 Completed History
5. Recommendation: Start Planning for Eventual MNRE SWH Subsidy Phase Out
Management Response: [Added: 2013/07/31] [Last Updated: 2013/07/31]

MNRE officials felt time is not yet appropriate for SWH subsidy phase out.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
The project fund considerations and criteria for an exit strategy for the current SWH subsidy scheme, as no subsidy lasts forever
[Added: 2013/07/31] [Last Updated: 2017/06/23]
MNRE 2015/12 Completed Subsidy phase-out was considered in 2013 and actually phased-out in 2015 History
6. Recommendation: Urgently Start Work on BIS Technology-Neutral SWH Standards
Management Response: [Added: 2013/07/31] [Last Updated: 2013/07/31]

PEC members took note of this as important outcome. It was decided to pursue this even beyond UNDP-GEF project period.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
A key project priority be the urgent development of whole-system, performance oriented and technology neutral BIS standards
[Added: 2013/07/31] [Last Updated: 2017/06/23]
MNRE 2013/12 Completed BIS considered whole solar water heating system. However, they have prepared norms for different components as per their standard operating procedures History
7. Recommendation: Project / MNRE Literature to Better Describe SWH Tech Options
Management Response: [Added: 2013/07/31]

PEC suggested this recommendation be looked into and appropriate actions taken to put up relevant material on website www.solarwaterheater.gov.in 1. All the reports are converted to short summaries. 2. Closure report is underway 3. All the above will be uploaded on project and UNDP website.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
The India SWH project literature be urgently updated to describe the full range of the four main SWH technology systems options available, and low/high pressure configurations, and their applications in different sectors
[Added: 2013/07/31] [Last Updated: 2017/06/23]
MNRE 2014/01 Completed The updated literature is available at the MNRE website: http://mnre.gov.in/file-manager/UserFiles/brief_swhs.pdf History