Success message
error message
warn message
Improvement of DDT-based Production of Dicofol and Introduction of Alternative Technologies Including IPM for Leaf Mites Control in China project Final Evaluation
Commissioning Unit: China
Evaluation Plan: 2011-2015
Evaluation Type: Project
Completion Date: 12/2013
Unit Responsible for providing Management Response: China
Documents Related to overall Management Response:
 
1. Recommendation:

Recommendation 1: Full utilization of the institutional infrastructure established and the strengthened technical and management capacity in the National Replication Program. The National Replication Program should take full advantage of the skill and experience that will benefit the replication plan.

Management Response: [Added: 2014/05/19] [Last Updated: 2017/06/29]

Experience and knowledge gained, the infrastructure established will be used as much as possible as valuable resources to implement and promote the National IPM Replication Program

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Project experience and knowledge gained etc. will be shared and used by the National Replication Program
[Added: 2014/05/19] [Last Updated: 2017/06/29]
Ministry of Agriculture (MOA), assisted by Ministry of Environmental Protection (MEP) as required 2019/12 Completed History
2. Recommendation: Recommendation 2: Experience gained and the effective working mechanism in the successful implementation of the demonstration activities that contributed to efficient management and coordination efforts yielding excellent project results should be captured and properly documented. The experience and work mechanism can serve as good model for other projects in China, in particular in the process of project design and implementation.
Management Response: [Added: 2014/05/19]

Manuals, technical reports, promotional materials etc. produced by the project have been well documented and shared. Project management experience has also been documented and shared among FECO to serve as good model for the project formulation, design and implementation of multilateral and bilateral environmental projects

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Experience and knowledge sharing through training, technical exchange workshops
[Added: 2014/05/19] [Last Updated: 2017/06/29]
Local Project Management Offices (PMOs), FECO and key stakeholders 2019/12 Completed History
3. Recommendation: Recommendation 3: Identify effective mechanism to promote acceptance of IPM technology by farmers and related personnel. To attract wider acceptance for the National Replication Program, it is recommended to make special efforts to identify effective advocacy and public awareness programme to promote the benefits of IPM applications.
Management Response: [Added: 2014/05/19]

Ministry of Agriculture will implement the IPM National Replication Program and will take into the experience of the demonstration activities to implement awareness activities to generate wider acceptance of IPM technologies

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Awareness activities formulated and implemented to promote wider acceptance of IPM technologies
[Added: 2014/05/19] [Last Updated: 2017/06/29]
MOA and key stakeholders 2019/12 Completed History

Latest Evaluations

Contact us

1 UN Plaza
DC1-20th Floor
New York, NY 10017
Tel. +1 646 781 4200
Fax. +1 646 781 4213
erc.support@undp.org