Promotion of Energy Efficiency Room Air Conditioners Midterm evaluation
Commissioning Unit: China
Evaluation Plan: 2011-2015
Evaluation Type: Project
Completion Date: 08/2013
Unit Responsible for providing Management Response: China
Documents Related to overall Management Response:
 
1. Recommendation:

Placing additional emphasis on retaining an international technical specialist to assist in the tasks normally performed by a Chief Technical Advisor (CTA).

Management Response: [Added: 2017/06/30]

PMO takes this feedback positively and will mainstream it into project implementation.

Key Actions:

2. Recommendation:

Looking for means of extending training and technical assistance and AMIS efforts after PEERAC ends

Management Response: [Added: 2017/06/30]

PMO takes this recommendation positively and will mainstream it into project implementation.

Key Actions:

3. Recommendation:

Stressing the importance of ‘market pull’ efforts to project participants.  The technology push components are very popular, but there seems to be much less interest in ‘market pull’ activities.  Such efforts will nevertheless become necessary if the industry is to accomplish a market-driven transformation.

Management Response: [Added: 2017/06/30]

PMO takes this recommendation positively and will mainstream it into project implementation.

Key Actions:

4. Recommendation:

Undertake a review of the project’s approach for determining goals and objectives, and try to develop a more realistic measure of the project’s contribution to energy savings and emissions reductions.

Management Response: [Added: 2017/06/30]

PMO takes it positively and will mainstream it into project implementation.

Key Actions:

5. Recommendation:

Examine the data and assumptions employed in the original calculations of these parameters, and determine whether they are accurate and remain suitable.

Management Response: [Added: 2017/06/30]

PMO takes the feedback positively and will mainstream it into project implementation.

Key Actions:

6. Recommendation:

Continue to use other indicators as guides for project management and evaluation, and continue to use quantitative measures to the extent possible.

Management Response: [Added: 2017/06/30]

PMO takes the feedback postively and will mainstream it into project implementation.

Key Actions:

7. Recommendation:

Incorporate data about alternative refrigerants (e.g., energy efficiency, GWP, environmental impacts, etc.) in all of its technical training and assistance programs.

Management Response: [Added: 2017/06/30]

PMO takes it positively and wil mainstream it into project implementation.

Key Actions:

8. Recommendation:

Coordinate project efforts with other UNDP and MEP programs addressing refrigerants to the fullest extent possible.

Management Response: [Added: 2017/06/30]

PMO takes the feedback postively and will mainstream it into project implementation.

Key Actions: