Terminal Evaluation: Namibia Energy Efficiency Programme in buildings (NEEP) Project
Commissioning Unit: Namibia
Evaluation Plan: 2014-2018
Evaluation Type: Project
Completion Date: 05/2014
Unit Responsible for providing Management Response: Namibia
Documents Related to overall Management Response:
 
1. Recommendation: Mandatory energy audits in public buildings
Management Response: [Added: 2014/12/05]

NEI to foster a partnership between MME and MWT for energy audits across the portfolio of government buildings

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1.1 Extrapolate the potential benefits of the audit findings across the portfolio of government buildings. 1.2 Seek support from MWT for retrofits of the portfolio of government occupied buildings (approximately 9,500 buildings).
[Added: 2014/12/05] [Last Updated: 2018/08/09]
NEI, MME, NEEP trained Energy 2015/12 Completed History
2. Recommendation: Showcasing of demonstration buildings
Management Response: [Added: 2014/12/05]

NEI, with support from MME, to verify EE principles in the demonstrations buildings and retrofit where necessary and then popularize the results from the NEEP project among all key stakeholders. Efforts will be made to gain interest from the commercial building sector as a potential catalyst.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
2.1 Utilize six demonstration facilities (EE House, Convenience Centre, FNB Green Star rated building and planned Erongo RED and MME buildings) to show case the results, technologies and benefits of EE to government, local authorities, NHE and the construction and engineering private sector. 2.2. Sharing and communicate the technical/ design brochure developed for Erongo RED with other regional energy distributors, local authorities, NHE and the construction and engineering private sector.
[Added: 2014/12/05] [Last Updated: 2018/08/09]
NEI, UNDP, MME 2015/12 Completed History
3. Recommendation: Resolve high-level ownership of the building codes
Management Response: [Added: 2014/12/05]

NEI to solicit support from Ministry of Regional and Local Government, Housing and Rural Development, MWT and other key partners in the construction sector to foster ownership for the review and revision of building codes

Key Actions:

Key Action Responsible DueDate Status Comments Documents
3.1 Package and widely share the benefits of building codes that enable and advocate for energy efficiency in buildings. 3.2 The information in 3.1 must be packaged appropriately and shared with the minister, deputy minister, PS, relevant Under Secretary and directors of MME, MWT, MET and MoHSS. This will facilitate building knowledge and understanding about the rationale and social and economic benefits of energy efficient buildings. E.g. ? projecting potential energy costs to govt. at present vs. cost of energy for e-efficient buildings ? and demonstrate potential health and safety hazards if codes are not revised. 3.3 Following the above, arrange a high level dialogue between the MME and MWT, including other key partners in the construction sector in view of reaching agreement to review and revise current building codes. Such a meeting can start with a brief presentation about benefits of energy efficient buildings, a tentative process outline for reviewing/ revising the codes, and what a desired outcome could be.
[Added: 2014/12/05] [Last Updated: 2018/08/09]
NEI 2015/03 Completed History
4. Recommendation: Administrative support to Green Building Council of Namibia (GBCNA)
Management Response: [Added: 2014/12/05]

NEI management to discuss support to the GBCNA and formally relay a decision to the Council

Key Actions:

Key Action Responsible DueDate Status Comments Documents
4.1 NEI management to meet and discuss support to GBCNA and formally relay the outcome of the meeting to the Council, with copy to UNDP
[Added: 2014/12/05]
NEI 2014/09 Completed
5. Recommendation: Showcase the UN?s commitment to climate change mitigation
Management Response: [Added: 2014/12/05]

NEI, through MME, to meet with the UN Resident Representative for commitment to carry out an energy audit of the UN House. UNDP to commit TO IMPLEMENTING Energy Audit Recommendations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
5.1 Secure commitment from the UN Resident Representative for the implementation of the energy audit recommendations of the UN House.
[Added: 2014/12/05]
NEI, MME 2014/09 Completed
6. Recommendation: Energy Efficiency (EE) in the Namibia Energy Institute (NEI).
Management Response: [Added: 2014/12/05]

NEI and its stakeholders to convene a Development Dialogue Forum (DDF) session to discuss and agree on strengthening the position of EE in the Institute

Key Actions:

Key Action Responsible DueDate Status Comments Documents
6.1 NEI concept paper of EE in the NEI. 6.2 Share concept paper with stakeholders in view of a consultation on the subject. 6.3 Facilitate a stakeholder meeting to present the concept paper on ?The role of EE in the NEI and its activities? and to reach a decision.
[Added: 2014/12/05] [Last Updated: 2018/08/09]
NEI, MME 2015/02 Completed History