MTR-Conservation, Sustainable Use of Biodiversity and the Maintenance of the Ecosystem Services in Protected Wetlands of International Importance
Commissioning Unit: El Salvador
Evaluation Plan: 2016-2020
Evaluation Type: Project
Completion Date: 06/2019
Unit Responsible for providing Management Response: El Salvador
Documents Related to overall Management Response:
 
1. Recommendation:

The project needs to have more impact on the benefits of declare NPA at the local level and to involve more local actors in the management of protected areas. The project must mobilize political influence to involve reticent partners, both private and institutional, relying on the MARN and UNDP. At the municipal level, the project must have a higher level of influence in the municipal governments to ensure budget support to achieve a reduction in the current contribution of solid waste.

Management Response: [Added: 2019/11/20]

MARN will mobilize its political influence in  local decision makers to enhance their commitment. Also It will strengthen the capacities of Local Ramsar Committees and Local Environmental Committees (COALES); and promote their involvement in the management of natural protected areas.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Promote the engagement of decision makers in the project´s area
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP 2019/12 Completed Se hizo una visita de campo conjunta MARN PNUD de alto nivel. Asistió la Alcaldesa de Jiquilisco y actores territoriales. También acompañó JICA History
Strengthen capacities of Local Ramsar Committees and COALES
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN 2020/12 Initiated Se fortalecieron las capacidades de los guarda (a representantes de las ANP del proyecto, 3) recursos de los comités Ramsar de la zona, en género y biodiversidad y en monitoreo ambiental. Pendiente programa de monitoreo comunitario (en 2020) History
2. Recommendation:

Under its influence, the project may extend the protected areas that are declared Ramsar sites, under the category of ‘protected landscapes’. The important mangrove of La Unión Bay should also be considered for inclusion in the SNAP. This declaration should be made in the framework of a dialogue with all the private and institutional actors to reach effective management agreements, concretizing the existing management plans, and obtaining budgetary allocations from the national and local governments.

Management Response: [Added: 2019/11/20]

The project will continue to make efforts to carry out actions to include the “protected landscapes” management category  in the SNAPs. Also It will shift from the declaration as SNAP the islands in the Fonseca Gulf to Include the mangrove forest of La Unión Bay as SNAP. 

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Adjust the project´s results framework
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP 2020/02 Overdue-Initiated Se hizo el ajuste al marco de resultado. Se programa Comité de Aprobación de Proyecto para aprobar la revisión sustantiva para el 2020. History
Request addendum of the project document
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP 2020/02 Overdue-Initiated Se está a la espera de la recomendación del Comité de Aprobación de Proyectos. History
3. Recommendation:

The project should contribute to establishing a monitoring system, in cooperation with other initiatives. This system must include emblematic species at the national level (crocodiles, marine turtles, etc.). In addition, the project should promote the development of a monitoring plan for the mangroves. The local Ramsar committees and the ROLA must be mobilized so that the monitoring serves as a forum for environmental participation and education. The MARN and UNDP must obtain the cooperation of CENDEPESCA for the better monitoring of artisanal fisheries.

Management Response: [Added: 2019/11/20]

Since 2018 the project has been working to develop the wetlands and NPAs monitoring system based on ecosystem health approach which includes the monitoring of emblematic species, and the mangrove forest as well. The project will include a community monitoring program and will strengthen capacities of Ramsar Local Committees and the Local Environmental Observers Network (ROLA, in Spanish). addition, once the monitoring systems is in place,  MARN will strengthen capacities of local actors including municipalities and technical staff of other government institutions in the territory. The monitoring of artisanal fisheries is full competency of CENDEPESCA. The efficiency of this activity is beyond the project’s scope.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Establish the wetland health monitoring system
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/Ramsar Local Committees 2019/08 Completed Sistema de monitoreo completado y en implementación en 3 humedales (Jocotal, Jiquilisco y Jaltepeque) History
Strengthen capacities of local actors
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/Ramsar Local Committees 2020/12 Initiated 77 guardas capacitados en género 15 en capacidad de carga de ANPs 28 en monitoreo ambiental de humedales y ANPs 20 guardarecursos voluntarios en Responsabilidades y funciones del Guardarrecusos History
Develop a wetlands community monitoring system
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/Ramsar Local Committees 2020/12 Initiated Se apoyó y fortaleció a las ROLA History
4. Recommendation:

The project should strive to facilitate the development of the administrative structures needed to better estimate the costs of the NPAs and the establishment of fee collection systems. The project can review the established budget gap reduction targets of the NPAs that were based on overly optimistic premises.

Management Response: [Added: 2019/11/20]

The project is currently working to develop and implement the business plans for the NPAS as mean to generate incomes. These aim to reduce the current financial gap. However, the goals and the indicators that are established in the project results framework for the reduction of the budgetary gap are going to be reviewed.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Develop and implement the business plans for NPAs.
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/Ramsar Local Committees 2019/10 Completed Se realizaron 7 planes para 7 áreas naturales protegidas. History
Strengthen the institutional capacities to improve the cost estimation of the NPAs, and the establishment of fees charge systems.
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/Ramsar Local Committees 2020/12 Initiated 77 guardas capacitados en género 15 en capacidad de carga de ANPs 28 en monitoreo ambiental de humedales y ANPs 20 guardarecursos voluntarios en Responsabilidades y funciones del Guardarrecusos History
5. Recommendation:

The project must advocate at the municipal corporation level for institutionalizing the diploma that it developed in order to ensure the maintenance of individual capacities for the management of wetlands.

Management Response: [Added: 2019/11/20]

The project will continue to carry out actions to strengthen the institutional and individual capacities for the sustainable management of wetlands through the creation of training modules and materials, which will be available for all interested public through the MARN´s website, Environmental Education Unit and the Wetlands Unit (MARN).

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Develop training modules and materials
[Added: 2019/11/20] [Last Updated: 2019/12/23]
MARN, Municipalities 2019/12 Completed Se desarrollaron los módulos. Están en etapa de diagramación. History
Training of the MARN staff in the use and application of the modules
[Added: 2019/11/20]
MARN, Municipalities 2020/05 Not Initiated
6. Recommendation:

In order to maximize the scarce project funds, the project must make an impact on the use of grasslands on wetland banks and flooded pastures, or the use of irrigation watercourses, and not invest in the development of an environmental seal for livestock products. In addition, the Wetlands Unit of the MARN should improve coordination with the JICA project to avoid duplication and forge synergies.

With the support of UNDP, the project should call on the sugar associations and mills rather than on individual producers to allow access of ‘sustainable’ sugar to differentiated markets. Here, UNDP’s experience in social and environmental certification of agricultural products (commodities) at the regional level can be capitalized on

Management Response: [Added: 2019/11/20]

The project will continue to promote good environmental practices, in both, cattle raising and in the sugarcane production. At this moment is not expected to include a certification process due to the time and cost that it would imply. The project will develop educational materials about good environmental practices to be implemented in productive process in the buffer zones of wetlands. This will help to train  in training producers as well as the MARN technical staff.

UNDP will support and facilitate the experiences exchange to define a roadmap for social and environmental certification of agricultural products.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Develop educational materials about good environmental practices to be implemented in productive processes in wetlands buffer zones
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2019/12 Completed Se ha elaborado un manual de buenas prácticas ambientales para actividades ganaderas en las áreas de amortiguamiento de los humedales y además se acompaña con un calendario History
Train staff and producers about good environmental practices for livestock and sugarcane production in wetlands buffer zones
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2020/12 Initiated Se han capacitado 20 productores de ganado History
Develop an action plan to work with sugarcane associations, sugar mills and JICA project in the promotion of good environmental practices.
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2019/12 Completed Ya se tiene un plan de trabajo a ser implementado en conjunto con Fundazucar History
7. Recommendation:

The clean-up campaigns planned by the project make sense within the framework of dialogue and learning processes that involve institutional and private actors, with the aim of quantifying waste and developing solutions to reduce its discharge into rivers and coasts.

Management Response: [Added: 2019/11/20]

The program for the control, reduction and prevention of solid waste pollution in  wetlands will be adjusted to give greater emphasis to the development of campaigns for the removal of the accumulated waste in the wetlands. An emphasis will be put on environmental education.  Also, to reduce the solid waste pollution in rivers and coasts, it will be implemented bio-bars or similar structures. The project has plans to implement an itinerant  museum about wetlands that will serve as a tool for raising awareness among communities.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Adjust the program for the control, reduction and prevention of solid waste pollution in wetlands
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2020/12 Initiated Se hicieron 3 campañas de limpieza, se colocaron 2 río bardas. History
Prepare an action plan to promote the involvement of institutional and private actors
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2020/06 Not Initiated History
Carry out campaigns for the removal of the solid waste accumulated in the wetland
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2019/12 Completed Se hicieron 3 campañas de limpieza, se colocaron 2 río bardas History
Develop an environmental education program about the threats to wetlands due to the inadequate disposal of solid waste
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2020/06 Initiated Se está apoyando la Unidad de Educacion Ambiental del MARN para la implementación de las escuelas ambientales municipales en los municipios del área de influencia del proyecto y se desarrollarán los materiales en temas específicos de interés del proyecto History
Develop drafts of agreements to be signed between MARN and municipalities for the maintenance of retention structures and removal of solid waste accumulated
[Added: 2019/11/20] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2019/12 Completed Los borradores ya están elaborados falta que se lleve a cabo el proceso de negociación entre las partes History
8. Recommendation:

The project should abandon the strategies suggested in the project document for the elimination of Eichhornia crassipes, because they are ecologically and economically unsustainable.

Management Response: [Added: 2019/12/10]

The project accepts the recommendation,  and will adjust the related goals and indicators in the project´s results framework. Instead, the project will implement an environmental education program to raise awareness about invasive species and its threats to wetlands.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Develop an environmental education program about invasive species and its threats to wetlands
[Added: 2019/12/10] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2020/02 Overdue-Initiated Modulos ya elaborados, falta la diagramación History
Implement the environmental education program
[Added: 2019/12/10]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2020/12 Not Initiated
Develop an action plan to promote the participation of institutional and private actors in the solution of the problem
[Added: 2019/12/10] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2020/06 Initiated Se han llevado a cabo reuniones de coordinación con actores como: UCA, UES, FISDL, FIAES, CEL para el tema de manejo del jacinto acuático History
Develop drafts of agreements to be signed between MARN and municipalities
[Added: 2019/12/10] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/MAG/Municipalities 2020/02 Overdue-Not Initiated History
9. Recommendation:

In the case of the Phalacrocorax brasilianus control program already started in the Cerrón Grande reservoir, and in the absence of the conservation unit's own resources, the project could consider extending its support for one or two additional control campaigns.

Management Response: [Added: 2019/12/10]

Considering that the project has provide solutions to the problem with this specie and is not considered a threat, it will adjust the goals and indicators in the project´s results framework. Instead, the project will implement an environmental education program to raise awareness about invasive species and its threats to wetlands.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Develop an environmental education program about invasive species
[Added: 2019/12/10] [Last Updated: 2019/12/23]
Project´s Unit/MARN/Municipalities 2019/12 Completed Modulos ya elaborados, falta la diagramación History
Implement the environmental education program
[Added: 2019/12/10] [Last Updated: 2019/12/23]
Project´s Unit/MARN/Municipalities 2020/12 Not Initiated History
10. Recommendation:

The project must abandon the specific goal of the number of holdings managed by women in favour of monitoring socio-economic effects of the practices promoted in a differentiated manner, including impacts on child feeding and youth education.

Management Response: [Added: 2019/12/10]

The project accepts the recommendation and will adjust the goals and indicators in the project´s results framework. The monitoring will shift to focus on impacts in the producers livelihoods.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Adjust the project´s results framework
[Added: 2019/12/11] [Last Updated: 2019/12/23]
Project´s Unit/MARN 2020/02 Overdue-Initiated Se eliminará un indicador. Ya hubo Junta de Proyecto, falta PAC History
Request addendum to the project document
[Added: 2019/12/11] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP 2020/02 Overdue-Initiated Ya se solicitó, estamos esperando la carta de GEF/PNUD. History
11. Recommendation:

The change of the government administration in June 2019, requires an extension of the project up to the end of 2020 or until April 2021.

Management Response: [Added: 2019/12/10]

The Project accepts the recommendations and will proceed with the extension solicitation as per the corresponding procedures.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Adjust the project´s results framework
[Added: 2019/12/10] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP 2020/02 Overdue-Initiated Se eliminará un indicador. Ya hubo Junta de Proyecto, falta PAC History
Request addendum of the project document
[Added: 2019/12/10] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP 2020/02 Overdue-Initiated Ya se solicitó, estamos esperando la carta de GEF/PNUD. History
12. Recommendation:

The project must include enough budget for trips in the next work plan or introduce modifications in the current one to facilitate the access of its specialists to the terrain. In addition, the project may consider hiring local coordinators and /or a facilitator for negotiations on the expansion of the SNAP.

Management Response: [Added: 2019/12/10]

The Project accepts the recommendations and the corresponding adjustments will be made in the annual work plan.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Adjust the 2019 annual work plan and request approval of the Executive Board
[Added: 2019/12/10] [Last Updated: 2019/12/23]
Project´s Unit/MARN/UNDP/GEF 2019/07 Completed El Plan fue ajustado y aprobado en Junta Ejecutiva. History