Final evaluation of the Support to Tajikistan Mine Action Programme
Commissioning Unit: Tajikistan
Evaluation Plan: 2016-2020
Evaluation Type: Project
Completion Date: 12/2019
Unit Responsible for providing Management Response: Tajikistan
Documents Related to overall Management Response:
 
1. Recommendation:

For UNDP CO

Recommendation 1. Meet with Tajikistan National Mine Action Centre (TNMAC, the government body in charge of mine action coordination) staff and partners to explain why STMAP has ended, what it achieved and how UNDP intends to support TNMAC and the mine action sector in future. This meeting should be arranged as soon as possible.

Management Response: [Added: 2020/01/11] [Last Updated: 2020/11/08]

The meeting will be arranged with TNMAC and counterparts in January-February 2019.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1. Request the TNMAC to facilitate the organization of the meeting, and conduct the meeting on UNDP’s support to TNMAC beyond 2019.
[Added: 2020/01/11] [Last Updated: 2020/10/08]
Nargizakhon Usmanova 2020/02 No Longer Applicable [Justification: the project ended and UNDP didn't receive any request for support from TNMAC]
History
2. Recommendation:

For UNDP CO

Recommendation 2. Advocate for funding for TNMAC and mine action. Promote Tajikistan as potentially mine free by 2025.

Management Response: [Added: 2020/01/11] [Last Updated: 2020/11/08]

Once/if the request from Tajikistan National Mine Action Centre (TNMAC, the government body in charge of mine action coordination) with concrete areas of technical support required from UNDP is received, UNDP will develop several concept notes to mobilize funding to provide the required support to TNMAC.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1. UNDP will develop several concept notes to mobilize funding to provide the required support to TNMAC.
[Added: 2020/01/11] [Last Updated: 2020/10/08]
Nargizakhon Usmanova 2020/06 No Longer Applicable [Justification: Since UNDP didn’t receive any formal request from TNMAC, the government body in charge of mine action coordination with concrete areas of technical support required from UNDP - UNDP didn’t proceed with the development of concept notes for additional resource mobilization beyond the end of the Programme]
History
3. Recommendation:

For UNDP CO

Recommendation 3. Publicize the mine action successes in Tajikistan.

Management Response: [Added: 2020/01/11] [Last Updated: 2020/11/08]

The mine action successes in Tajikistan are being publicized globally.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1. Contribute into UNDP Global Report on Mine Action (2018-19)
[Added: 2020/01/11] [Last Updated: 2020/10/08]
Nargizakhon Usmanova 2020/01 Completed the action completed History
2. Provide inputs into SG’s report on Mine Action
[Added: 2020/01/11] [Last Updated: 2020/10/08]
Nargizakhon Usmanova 2020/01 Completed the action completed History
4. Recommendation:

For UNDP CO

Recommendation 4. Using a participatory approach, facilitate the development of the 2021-2025 national mine action strategy.

Management Response: [Added: 2020/01/11] [Last Updated: 2020/11/08]

The development of 2021-2025 national mine action strategy will be supported, once/if the request for such technical support is received by UNDP from Tajikistan National Mine Action Centre (the government body in charge of mine action coordination).

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1. The development of 2021-2025 national mine action strategy will be supported through existing advisory and policy support capacities within UNDP.
[Added: 2020/01/11] [Last Updated: 2020/10/08]
Olaf Juergensen, Regional Development and Mine Action Specialist, HQ/Crisis Bureau 2020/12 Not Initiated the project ended History
5. Recommendation:

For UNDP CO

Recommendaiton 5. Provide ongoing technical support for TNMAC for at least the next two years to support capacity building, institutional development and help to maintain and improve operational standards.

Management Response: [Added: 2020/01/11] [Last Updated: 2020/11/08]

The implementation of this recommendation requires mobilization of funding for mine action work by UNDP Tajikistan, and will be implemented once/if funding is mobilized, and UNDP is approached by the Government of Tajikistan with specific request on technical support in mine action.

Key Actions:

6. Recommendation:

For UNDP CO

Recommendation 6. Support the development of strategies to promote sustainability and ensure capacity for residual clearance and initiatives to use Tajikistan’s mine action capacity post 2025.

Management Response: [Added: 2020/01/11] [Last Updated: 2020/11/08]

The implementation of this recommendation requires mobilization of funding for mine action by UNDP Tajikistan, and will be implemented once/if funding is mobilized, and UNDP is approached by the Government of Tajikistan with specific request on technical support in mine action.

Key Actions:

7. Recommendation:

For UNDP CO

Recommendation 7. Promote the success of STMAP to the UNDP Regional Hub and New York, request technical and financial support and support in drawing attention to mine action needs in Tajikistan.

Management Response: [Added: 2020/01/11] [Last Updated: 2020/11/08]

UNDP Country Office will provide inputs and contributions to corporate level reporting on mine action, as required.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1. Contribute into UNDP Global Report on Mine Action (2018-19)
[Added: 2020/01/11] [Last Updated: 2020/10/08]
Nargizakhon Usmanova 2020/01 Completed the action completed History
2. Provide inputs into SG’s report on Mine Action
[Added: 2020/01/11] [Last Updated: 2020/10/08]
Nargizakhon Usmanova 2020/01 Completed the action completed History
8. Recommendation:

For UNDP CO

Recommendation 8. Approach UNOPS to facilitate recruitment of mine action expertise through its roster of consultants

Management Response: [Added: 2020/11/03] [Last Updated: 2020/11/08]

Key Actions:

9. Recommendation:

For TNMAC

Recommendations 9-17 

 • Promote Tajikistan as potentially mine free by 2025 to support resource mobilization

• In consultation with stakeholders develop the 2021-2025 national mine action strategy, resource mobilization strategy, communications strategy.

• Develop a strategy to maintain capacity to deal with residual contamination and identify how surplus mine action capacity can contribute to other initiatives post-2025.

• Focus on coordination and quality assurance and avoid implementation to ensure that there is no conflict of interests.

• Ensure that TNMAC has appropriate oversight for all MRE activities.

• Delegate responsibilities for MRE and VA to other partners and focus on coordination and quality assurance for these mine action pillars

• Hold meetings for victim assistance in a place that is accessible to persons with disabilities.

• Work actively with partners including UNDP to mobilize resources and coordinate efforts to approach donors.

• Provide leadership and oversight for the implementation of the gender and diversity strategy. 

Management Response: [Added: 2020/11/03] [Last Updated: 2020/11/08]

Key Actions:

10. Recommendation:

For the Tajikistan Mine Action Sector

Recommendations 18-27:

• Continue to work closely together and share resources.

• Participate in the development of the next national mine action strategy and other strategies for resource mobilization, communications etc.

• Continue to improve land release methodologies.

• Continue to liaise closely with GICHD, OSCE and UNDP and seek their support for resource mobilization, capacity building and technical support.

• Maintain clear roles and responsibilities and transparent financial and administrative procedures.

• Ensure that quality assurance is maintained. Consider requesting regular reviews from an external party.

• Examine the feasibility of physically clearing all remaining contamination. If some areas are determined to be impossible to clear using existing methods and technology, agree a strategy for marking as well as ways to communicate effectively the necessity of marking to the relevant international regulatory bodies.

• Individual organizations that have commissioned studies into the different aspect of mine action should consider sharing them with all mine action stakeholders to maximize effective use of resources and avoid duplication of efforts. Use existing strategies and assessments - many of them contain useful recommendations and advice that is still relevant.

• Mainstream gender and diversity through the next national mine action strategy and implementation of mine action activities as articulated in the 2017 gender and diversity strategy.

Management Response: [Added: 2020/11/03] [Last Updated: 2020/11/08]

Key Actions:

Latest Evaluations