Success message
error message
warn message
Final project evaluation of UNDP/GEF Promoting Technology Transfer and Market Development for Small Hydropower in Tajikistan
Commissioning Unit:Tajikistan
Evaluation Plan:2016-2020
Evaluation Type: Project
Completion Date:02/2018
Unit Responsible for providing Management Response: Tajikistan
1. Recommendation:

1. Install meters of electricity supplied from the SHP plants

Management Response: [Added: 2018/06/06]

Considering that the project has ended the official owners of the SHPPs are informed that the SHP plants need to be equipped with electricity meters.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Make agreement with the SHPP owners to supply the SHPPs with electricity meters
[Added: 2018/06/06]
PM 2018/06 Completed Whenever SHPP is operational, the owners are informed and agreement is reached
Purchasing and installation of the electricity meters in all 4 SHPPs
[Added: 2018/06/06] [Last Updated: 2018/11/22]
SHPP owners 2018/11 Completed Electric meters are installed in 3 out of 4 SHPPs
After the installation of the meters, the SHPPs operators need to control and fix the amount of transmitted electricity for proper financial planning
[Added: 2018/06/06] [Last Updated: 2018/11/22]
SHPP owners 2019/03 Initiated The amounts of electricity supply to the community residents are recorded by operators where SHPPs are operating; for now only Safedob SHPP in Shamsiddin Shohin district is operating / supplying electricity to users
2. Recommendation:

  2. Elimination of soil erosion at SHP in Pinyon

Management Response: [Added: 2018/06/06]

The recommendation is relevant and has been addressed accordingly.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Conduct financial assessment of the additional works to be performed to comply with the recommendation
[Added: 2018/06/06]
PM; Contractor; UNDP CO engineer 2018/03 Completed List of additional works identified and submitted;
Eliminating the soil erosion in Pinyon SHPP and perform additional works preventing the erosion in the future according to the findings of the assessment
[Added: 2018/06/06] [Last Updated: 2018/11/22]
PM; Contractor; UNPD CO Engineer 2018/09 Completed The water channels zones with high risk of flush flooding and soil erosion are covered with concrete plates, and additional works are completed;
Submit full report on completed works, including evidence
[Added: 2018/06/06] [Last Updated: 2018/11/22]
Contractor 2019/03 Initiated After completion of commissioning of SHPP Jilikul, Komperg LTD will provide full and final report on works completion
3. Recommendation:

3. Publish project information and documents on-line

Management Response: [Added: 2018/06/06]

The recommendation is relevant and to be adhered to

Key Actions:

Key Action Responsible DueDate Status Comments Documents
The project team compiles all the materials (photos and videos) and publications developed within the project framework and publishes them on the UNDP and its partners’ websites.
[Added: 2018/06/06] [Last Updated: 2018/11/22]
PM, UNDP Communications Analyst 2018/12 Completed All materials and publications developed in the framework of the project have been spread out
4. Recommendation:

4. Continuity in RE support

Management Response: [Added: 2018/06/06]

Continuity in RE support is provided by the continued cooperation and coordination with the MEWR to support the implementation of the national targets on RE development. This also included the development and submission of a project proposal to GEF for funding the Green Energy SMEs Development project

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Coordinate with the stakeholders and national partners the measures to ensure continuity in RE support
[Added: 2018/06/06]
PM, UNDP Portfolio Manager 2018/03 Completed While this recommendation was provided during the TE period in 2017, the project team had already held consultations with partners and national stakeholders to define the areas of supporting the RE support.
Based on the findings from the consultations, develop decent project proposal and aim towards raising funds for the continuity in RE support
[Added: 2018/06/06]
PM; UNDP Portfolio Manager; IRH 2018/04 Completed The project developed and approved by the donor – GEF
Support the development of new legislations and assist in implementation of the existing laws and sub-laws. Special stress needs to be put to establishing the National Trust Fund for RE and EE, which is fixed in the law on “EE and ES”.
[Added: 2018/06/06]
PM; UNDP CO 2020/06 Initiated Development and upgrading of new RES/ EE laws and by-laws, as well as promoting RES/ EE through Trust Fund mechanism are envisaged under new UNDP-GEF Green Energy and SME Development Project

Latest Evaluations

Contact us

220 East 42nd Street
20th Floor
New York, NY 10017
Tel. +1 646 781 4200
Fax. +1 646 781 4213
erc.support@undp.org