Terminal Evaluation of Integrated Land and Ecosystem Management to Combat Land Degradation and Deforestation in Madhya Pradesh
Commissioning Unit: India
Evaluation Plan: 2013-2017
Evaluation Type: Project
Completion Date: 02/2016
Unit Responsible for providing Management Response: India
Documents Related to overall Management Response:
 
1. Recommendation:

Terminal Evaluation recommendation 1. State government should issue an appropriate notification to clarify the legality of the bamboo harvest rights model.

Management Response: [Added: 2016/12/26] [Last Updated: 2016/12/26]

Noted and initiated.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1.1 As per the JFM resolution existing in the state and under the National Forest Policy, the regional Forest Officers have involved the bamboo beneficiaries for harvesting, sale and distribution of profit
[Added: 2016/12/26] [Last Updated: 2019/02/01]
PMU and MP Forest Department. 2019/01 Completed The activity is completed and the project is closed History
1.2 Local poor families have been further involved in a planned manner through various existing schemes for working on new areas for RDBF in some Forest Divisions
[Added: 2016/12/26] [Last Updated: 2019/02/01]
MPFD/ State Bamboo Mission/ MGNREGA 2019/01 Completed The activity is completed and the project is closed. History
2. Recommendation:

Terminal Evaluation recommendation 2. A closing workshop should be held to summarize and publicize the achievements of the project and to identify and obtain commitments for future actions.

Management Response: [Added: 2016/12/26] [Last Updated: 2016/12/26]

Noted and addressed.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
2.1 District level workshops were organized by the respective regional officials
[Added: 2016/12/26]
MPFD 2019/01 Completed
2.2 The State bamboo Mission organized a buyer-seller meet which had active participation from the project districts
[Added: 2016/12/26]
MPFD 2019/01 Completed
3. Recommendation:

Terminal Evaluation recommendation 3.  The bamboo harvest rights model should be incorporated into other forest department programs on bamboo plantations and degraded land.

 

Management Response: [Added: 2016/12/26] [Last Updated: 2016/12/26]

Noted and initiated.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
3.1 In many of the Forest Divisions, the RDBF model has been considered for involving the local communities through various government schemes like MGNREGA, MPSRLM, IWMP etc.
[Added: 2016/12/26] [Last Updated: 2019/02/01]
MPFD, local governance models for state and centre sponsored schemes etc. 2019/01 Completed History
4. Recommendation:

Terminal Evaluation recommendation 4.  Discussions should take place immediately with the State Bamboo Mission and the National Bamboo Mission in order to widen the potential impact of project results.

 

Management Response: [Added: 2016/12/26] [Last Updated: 2016/12/26]

Noted and initiated

Key Actions:

Key Action Responsible DueDate Status Comments Documents
4.1 The State Bamboo Mission has recognized the project districts for their own mission objectives and coverage for bamboo based agroforestry plantations etc.
[Added: 2016/12/26] [Last Updated: 2019/02/01]
State Bamboo Mission and MPFD 2019/01 Completed History
5. Recommendation:

Terminal Evaluation recommendation 5.  Feed project results and experience into the current GEF/World Bank Biodiversity Conservation and Rural Livelihoods Improvement Project under implementation in the Satpura Landscape, and the forthcoming World Bank funded Ecosystem Services Improvement Project

 

Management Response: [Added: 2016/12/26] [Last Updated: 2016/12/26]

Noted and initiated

Key Actions:

Key Action Responsible DueDate Status Comments Documents
5.1 Under the World bank aided BCRLIP project, all the villages / areas of UNDP project has been considered for development initiatives. This has extended the involvement of the local communities/ stakeholders for furthering the agenda of addressing land degradation along with livelihood based issues.
[Added: 2016/12/26] [Last Updated: 2019/02/01]
MPFD/ World bank BCRLIP project unit in PCCF, W/L office 2019/01 Completed History