Success message
error message
warn message
Modernization of Public Administration
Commissioning Unit:Kosovo
Evaluation Plan:2016-2020
Evaluation Type: Project
Completion Date:08/2017
Unit Responsible for providing Management Response: Kosovo
1. Recommendation:

Continue to contribute to institutional development by focusing on enhancing the institutional legitimacy

Management Response: [Added: 2017/09/15]

Management takes note of the recommendation. The project was developed within the existing wider CDF concept thus institutional development was integrated into project activities

Key Actions:

Key Action Responsible DueDate Status Comments Documents
This recommendation will be taken into consideration when designing the follow-up project or other projects contributing to the same outcome
[Added: 2017/09/15]
Programme Team 2020/12 Not Initiated
2. Recommendation:

Continue support to improving civil service training and career development system

Management Response: [Added: 2017/09/15]

Management takes note of the recommendation. UNDP will coordinate efforts, in support of KIPA, with other partners/donors who are active in this field

Key Actions:

Key Action Responsible DueDate Status Comments Documents
This recommendation will be taken into consideration when implementing a potential new project or other projects contributing to the same outcome
[Added: 2017/09/15]
Project Staff 2020/12 Initiated
3. Recommendation:

Continue with providing on-the-job and on-demand technical assistance and mentoring – and strengthen performance criteria

Management Response: [Added: 2017/09/15]

Management takes note of the recommendation. The project was developed within the broader concept of CDF thus this activity was an integral part of the project

Key Actions:

Key Action Responsible DueDate Status Comments Documents
This recommendation will be implemented when designing the follow-up project or other projects contributing to the same outcome
[Added: 2017/09/15]
Programme Team 2020/12 Not Initiated
4. Recommendation:

Trainings and follow-up actions

Management Response: [Added: 2017/09/15] [Last Updated: 2017/09/15]

Management takes note of the recommendation never the less, it does not foresee this as a possibility for new/follow-up projects related to PAR/SAA

Key Actions:

5. Recommendation:

Focus on local governance

Management Response: [Added: 2017/09/15]

Management takes note of the recommendation. UNDP’s forward-looking plans include the expansion at the municipal level

Key Actions:

Key Action Responsible DueDate Status Comments Documents
This recommendation will be implemented when designing the follow-up project or other projects contributing to the same outcome
[Added: 2017/09/15]
Programme Team 2020/12 Not Initiated
6. Recommendation:

Introduce small motivational grants

Management Response: [Added: 2017/09/15]

Management takes note of the recommendation never the less, it does not foresee this as a possibility for new/follow-up projects related to PAR/SAA

Key Actions:

Latest Evaluations

Contact us

220 East 42nd Street
20th Floor
New York, NY 10017
Tel. +1 646 781 4200
Fax. +1 646 781 4213
erc.support@undp.org