00068398 Strategic Planning and Action to Climate Resilience (SPARC) GEF Terminal Evaluation
Commissioning Unit: Indonesia
Evaluation Plan: 2016-2020
Evaluation Type: Project
Completion Date: 06/2019
Unit Responsible for providing Management Response: Indonesia
Documents Related to overall Management Response:  
1. Recommendation:

Project activities ensuring scaling up should be clearly articulated at project design and with actions included in annual plans intended
to ensure the success of scaling up project outcomes/outputs.

Management Response: [Added: 2019/06/20]

Development of scale-up strategy for a pipeline climate smart agriculture (CSA) intervention in NTT Province that emphasize on increasing the effectiveness and coverage of agricultural
support services.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Inclusion of scale-up strategy in the pipeline CSA programme interventions in NTT Province
[Added: 2019/06/20] [Last Updated: 2020/02/10]
UNDP CO Indonesia 2020/01 Completed The scale up strategy in the pipeline CSA programme interventions In NTT province has been included. It has been reference for the development of new pipeline. History
2. Recommendation:

Incorporate participatory monitoring and evaluation in project design, whereby beneficiaries choose targets and indicators relevant to them, beneficiaries monitor and report of indicators, and identify adaptive strategies to adjust/modify CCA or AIG actions

Management Response: [Added: 2019/06/20]

Development of public, private and civil society partnerships strategy for the implementation and monitoring of CSA input for selected crops in NTT Province. The interventions will be
executed through strengthening the capacity of Farmer Producer Organizations (FPOs) to promote more institutionalized and effective farming activities.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Inclusion of PPP strategy in the pipeline CSA programme interventions in NTT Province
[Added: 2019/06/20] [Last Updated: 2020/02/10]
UNDP CO Indonesia 2020/01 Completed The action was implemented in 2019. History
3. Recommendation:

Supporting existing or new income generating activities should be accompanied by appropriate market chain analysis

Management Response: [Added: 2019/06/20]

Conduct value chain analysis ranging from the stage of production, postharvest, distribution (including market) and consumption for specific agricultural commodities in NTT province. The VCA
is used to identify gaps in all stages and its specific interventions

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Finalization of Feasibility study on 6 agriculture commodities in NTT.
[Added: 2019/06/20] [Last Updated: 2020/02/10]
UNDP CO Indonesia 2020/01 Completed Finalization of feasibility study was conducted and has being reference to similar interventions History