Evaluation of the EC Contribution to the Parliamentary Action for Renewable Energy (PARE) Project
Commissioning Unit: Bureau for Policy and Programme Support
Evaluation Plan: 2014-2017
Evaluation Type: Project
Completion Date: 12/2014
Unit Responsible for providing Management Response: Bureau for Policy and Programme Support
Documents Related to overall Management Response:
 
1. Recommendation:

Improved Documenting of the Core PARE Approach

Management Response: [Added: 2017/12/29] [Last Updated: 2017/12/29]

For the second phase of the PARE project (PARE II), a methodological roadmap and workplan will be drafted and agreed upon with the members of parliament at the outset of the project.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
An overall comprehensive country-level implementation plan is developed after the initial scoping work, in which the country will provide a realistic timescale and form the basis for the monthly discussion between UNDP and Climate Parliament to assess progress and discuss challenges arising and appropriate solutions.
[Added: 2017/12/29]
Project Manager / Implementing Partner 2015/12 Completed
UNDP country offices will be involved from the outset of the project, including through the organization of trainings for members of partner country parliaments and the meetings of stakeholders in country.
[Added: 2017/12/29]
Project Manager / UNDP Country Offices in PARE II implementing countries 2017/12 Completed
2. Recommendation:

Increased focus on Analysis and Lessons Learned in PARE Final Reporting

Management Response: [Added: 2017/12/29] [Last Updated: 2017/12/29]

In order to address these challenges, a tighter centralized management of all work streams will be established.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Reporting: A short weekly report from all implementing actors, using a pre-determined template that is results-focused will be established. A monthly teleconference will be set up and will include consolidation of previous weekly reports to allow a full assessment of real progress, identify shortcomings, challenges, successes and take remedial or alternative action.
[Added: 2017/12/29]
Project Manager, Implementing Partners 2015/12 Completed
The two hearings organized in the framework of the new (PARE II) project will ensure two face-to-face meetings between UNDP and Climate Parliament staff. Moreover, a new tracking system will be established where proof of meetings, official bulletin, pictures and all other documents will be regularly downloaded in a centralized system (Evernote) and updates discussed during the monthly progress review call
[Added: 2017/12/29]
Project Manager / Implementing Partner 2015/12 Completed