EMPRETEC Terminal Evaluation
Commissioning Unit: Gambia
Evaluation Plan: 2017-2021
Evaluation Type: Project
Completion Date: 08/2017
Unit Responsible for providing Management Response: Gambia
Documents Related to overall Management Response:
 
1. Recommendation:

Define and establish a Transition Program for the EMPRETEC Centre

Management Response: [Added: 2017/10/04]

In the light of recommendations for a one-year Transition Program, it is furthermore recommended that the UNDP continues funding the project for a further one year commencing October 2017. In this period a transition plan is to be articulated.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Develop a transition plan
[Added: 2017/10/04]
Abdou Touray 2019/10 Not Initiated
2. Recommendation:

Determine the appropriate Institutional Model for the Centre

Management Response: [Added: 2017/10/04]

There is a need to agree on and establish the Legal Status of the EMPRETEC Centre; define the Governance Structures for the Centre and develop  the Accountability Instruments (Organizational Processes) of the center.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Facilitate decision on institutional model of centre and support the legal establishment based on agreed model.
[Added: 2017/10/04]
AbdouTouray 2018/10 Overdue-Not Initiated
3. Recommendation:

Develop or strengthen collaborative partnerships and strategic alliances with similar initiatives

Management Response: [Added: 2017/10/04]

Empretec Centre to concluding MOUs with relevant institutions to ensure synergetic relations

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Initiate MoU
[Added: 2017/10/04]
Abdou Touray 2018/10 Overdue-Not Initiated
4. Recommendation:

Localize the EMPRETEC model to local Gambian context

Management Response: [Added: 2017/10/04]

The project takes note of the need to define local perceptions, mindsets and business organizational culture in order to design relevant modules.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Assess key factors influencing local business culture and integrate within curriculum
[Added: 2017/10/04]
Abdou Touray 2018/10 Overdue-Not Initiated
5. Recommendation:

Establishment of an investment fund to support business start-ups and export oriented enterprises.

Management Response: [Added: 2017/10/04]

Recommendation will be discussed with Government of Gambia relevant departments