Final Evaluation of De-risking Renewable Energy (NAMA)
Commissioning Unit: Nigeria
Evaluation Plan: 2018-2022
Evaluation Type: Project
Completion Date: 12/2021
Unit Responsible for providing Management Response: Nigeria
Documents Related to overall Management Response:  
1. Recommendation:

Strengthen measures and instruments to address risks to renewable energy projects

Management Response: [Added: 2021/12/27] [Last Updated: 2021/12/27]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Advocate for stronger investors friendly policy and financial instruments to reduce / eliminate financial obstacles investors are facing
[Added: 2021/12/27] [Last Updated: 2022/06/13]
Federal Ministry of Environment, Federal Ministry of Power, Energy Commission of Nigeria, Nigerian Electricity Regulatory Commission 2022/04 No Longer Applicable [Justification: Implementation of related components stooped so key action no longer applicable ]
Implementation of related components stooped so key action no longer applicable History
2. Recommendation:

Invest in evidence building on the benefits of Rural Electrification Agency (RE) to support its adoption and institutionalization.

Management Response: [Added: 2021/12/27]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Integrate RE broader benefits analyses and projections into future project formulation
[Added: 2021/12/27]
UNDP, Federal Ministry of Environment, Federal Ministry of Power, Energy Commission of Nigeria, Nigerian 2021/12 Completed
3. Recommendation:

Put in place mechanisms for incentivizing private investment on decentralized RE solutions

Management Response: [Added: 2021/12/27]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Formulation of a clear policy and corresponding strategy promoting decentralized solutions, including interconnected mini-grids, and the integration of this strategy into future updates of the Nigeria Renewable Energy Master Plan (REMP).
[Added: 2021/12/27] [Last Updated: 2022/06/13]
Federal Ministry of Environment, Federal Ministry of Power, Energy Commission of Nigeria, Nigerian Electricity Regulatory Commission, UNDP, Rural Electrification Agency 2023/02 Initiated This process is still ongoing History
4. Recommendation:

Institutionalize knowledge management practices to facilitate sharing of knowledge

Management Response: [Added: 2021/12/27]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Government to institutionalize knowledge management practices to facilitate sharing of knowledge using communication and awareness materials e.g., infographics, audiovisual material, didactic material for children and teachers
[Added: 2021/12/27] [Last Updated: 2022/06/13]
Federal Ministry of Environment, Federal Ministry of Power, Energy Commission of Nigeria, Nigerian Electricity Regulatory Commission, National Orientation Agency. 2022/04 Completed Development and deployment of the “Nigeria Renewable Energy webGIS websiet for renewable energy resources in Nigeria completed. (https://nigeria.gestoenergy.com/) History