ESCO Moldova - Transforming the market for Urban Energy Efficiency in Moldova by introducing Energy Service Companies
Commissioning Unit: Moldova
Evaluation Plan: 2018-2022
Evaluation Type: Project
Completion Date: 11/2018
Unit Responsible for providing Management Response: Moldova
Documents Related to overall Management Response:
 
1. Recommendation:

UNDO CO to systematize and keep relevant materials related to the Green Urban Development Plan, developed by the ESCO Moldova project.

Management Response: [Added: 2019/01/16] [Last Updated: 2020/12/05]

Recommendation is well noted and agreed. The materials related to GUDP, are systemized in electronic files and available to:

  • projects implemented by UNDP CO in the area of  energy and environment infrastructure, as well as local development ( e.g. Green Cities)  
  • Municipality of Chisinau, Balti and other Local Public Authorities
  • interested donor institutions

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1.1 UNDP/GEF Green Cities project will apply the Practice Guide to Green Urban Development Planning while developing the Sustainable Urban Mobility Plan
[Added: 2019/01/16] [Last Updated: 2021/01/25]
UNDP CO, Environment, Energy and Climate Change Cluster 2020/12 Completed The elaboration of Sustainable Urban Mobility Plan (SUMP) for Chisinau is being finalized. The Practice Guide has been taken into consideration and its parts integrated in the draft SUMP. History
1.2. UNDP CO will inform interested partner institutions in the energy sector and relevant people in Chisinau City Hall, including current Mayor, on (i) Practice Guide to Green Urban Development Planning and (ii) Public Green Procurement Guideline and advocate for their application
[Added: 2019/01/16] [Last Updated: 2020/02/07]
UNDP CO, Environment, Energy and Climate Change Cluster 2019/12 Completed The Green City Action Plan designed by EBRD and the National Program of investments in energy efficiency drafted by EIB have considered the Guides designed by the ESCO project. Moreover, UNDP has shared this documents with the new Chisinau Mayor (elected in November 2019) and new staff in the City Hall, to be considered as basis for developing the Sustainable development concept of the Chisinau Municipality. History
2. Recommendation:

In the future, when the competitive market of the energy service providing companies will be created, the EE retrofits under the EPC likely will become the main modality (such trend is observed e.g. in Ukraine). Therefore, continuation of awareness raising campaign by the UNDP is recommended.

Management Response: [Added: 2019/01/16] [Last Updated: 2020/12/05]

The recommendation is well noted and agreed. ESCO Moldova project had a catalytical role for setting the foundations and better prepare the energy market for EPC and ESCO and will continue to promote the awareness on new financial mechanisms in energy efficiency

Key Actions:

Key Action Responsible DueDate Status Comments Documents
2.1. ESCO project final report with lessons learned, as well as main findings of Terminal Evaluation report will be shared through UNDP coporate, individual country office and other web sites
[Added: 2019/01/16] [Last Updated: 2019/03/22]
UNDP CO, Environment, Energy and Climate Change Cluster 2019/03 Completed Final Report of the ESCO Project was made publicly on UNDP corporate and CO web-sites ( please see the links: https://erc.undp.org/evaluation/evaluations/detail/9655 and http://www.md.undp.org/content/dam/moldova/docs/ESCO%20Final%20Report%20with%20lessons%20learned_%2017.12.2018_.pdf ). Additionally the lessons learned on ESCO model implementation and its further potential at national level has been discussed with various donors and IFIs in Moldova (WB, EIB, NEFCO). History
2.2 Further networking with interested partner institutions on EPC and ESCO mechanism will be explored
[Added: 2019/01/16] [Last Updated: 2021/01/25]
UNDP CO, Environment, Energy and Climate Change Cluster 2020/12 Completed A study has been developed in 2020 by UNDP on the most appropriate financial mechanism to apply ESCO in residential sector, along with the draft Energy Performance Contract. The application of ESCO mechanism is being tested within 1 multistorey residential building in Chisinau within the Green City Project in 2021. If the pilot is successful, it will be promoted for scaling up at national level. History