- Evaluation Plan:
- 2018-2021, RBEC
- Evaluation Type:
- Final Project
- Planned End Date:
- 12/2020
- Completion Date:
- 12/2020
- Status:
- Completed
- Management Response:
- No
- Evaluation Budget(US $):
- 10,000
Terminal Evaluation of the “Reducing UPOPs and Mercury Releases from the Health Sector in Africa"
Share
Document | Type | Language | Size | Status | Downloads |
---|---|---|---|---|---|
![]() |
tor | English | 36.27 KB | Posted | 112 |
![]() |
report | English | 2609.81 KB | Posted | 13 |
Title | Terminal Evaluation of the “Reducing UPOPs and Mercury Releases from the Health Sector in Africa" | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Atlas Project Number: | 00090700 | ||||||||||||||
Evaluation Plan: | 2018-2021, RBEC | ||||||||||||||
Evaluation Type: | Final Project | ||||||||||||||
Status: | Completed | ||||||||||||||
Completion Date: | 12/2020 | ||||||||||||||
Planned End Date: | 12/2020 | ||||||||||||||
Management Response: | Yes | ||||||||||||||
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021) |
|
||||||||||||||
Evaluation Budget(US $): | 10,000 | ||||||||||||||
Source of Funding: | |||||||||||||||
Evaluation Expenditure(US $): | 10,000 | ||||||||||||||
Joint Programme: | No | ||||||||||||||
Joint Evaluation: | No | ||||||||||||||
Evaluation Team members: |
|
||||||||||||||
GEF Evaluation: | Yes
|
||||||||||||||
Key Stakeholders: | Ministry of Health in Ghana, Madagascar, Tanzania, Zambia; WHO; HCWH; |
Lessons | |
---|---|
Findings |
Recommendations | |
---|---|
1 | UNDP IRH should ensure maintenance of the web repository containing the project knowledge products after closure of the project. |
2 | UNDP IRH should collect all technical reports, market studies and other results of the Lighthouse Projects and make them available through the web repository of the knowledge products. |
3 | For preparation of multi country projects with sizeable and staged equipment procurement components UNDP should plan minimum 5-years implementation period. |
4 | For preparation of future multi-country projects with regional and national components, UNDP should follow the standard Objective-Outcome-Output-Activity pattern and construct project logframe matrix according to substantive topics and assign national or regional responsibility for implementation of individual Outcomes in the results matrix without clustering them according to the implementation responsibility. |
5 | UNDP should ensure that updated information on actually materialized co-financing for GEF projects is reported in the last two PIRs. |
6 | UNDP should carefully plan the conduct of Terminal Evaluations. In case TE mission is included in the TE plan, the TE mission should not be conducted earlier than three months before the project planned completion date. |