- Evaluation Plan:
- 2018-2022, Egypt
- Evaluation Type:
- Final Project
- Planned End Date:
- 12/2018
- Completion Date:
- 01/2020
- Status:
- Completed
- Management Response:
- Yes
- Evaluation Budget(US $):
- 18,180
Terminal Evaluation Improving the energy efficiency of Lighting and other Building Appliances
Share
Document | Type | Language | Size | Status | Downloads |
---|---|---|---|---|---|
![]() |
tor | English | 489.33 KB | Posted | 1123 |
![]() |
report | English | 1882.37 KB | Posted | 1403 |
Title | Terminal Evaluation Improving the energy efficiency of Lighting and other Building Appliances | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Atlas Project Number: | 00060162 | ||||||||||||||
Evaluation Plan: | 2018-2022, Egypt | ||||||||||||||
Evaluation Type: | Final Project | ||||||||||||||
Status: | Completed | ||||||||||||||
Completion Date: | 01/2020 | ||||||||||||||
Planned End Date: | 12/2018 | ||||||||||||||
Management Response: | Yes | ||||||||||||||
Focus Area: |
|
||||||||||||||
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021) |
|
||||||||||||||
SDG Goal |
|
||||||||||||||
SDG Target |
|
||||||||||||||
Evaluation Budget(US $): | 18,180 | ||||||||||||||
Source of Funding: | |||||||||||||||
Evaluation Expenditure(US $): | 18,180 | ||||||||||||||
Joint Programme: | No | ||||||||||||||
Joint Evaluation: | No | ||||||||||||||
Evaluation Team members: |
|
||||||||||||||
GEF Evaluation: | Yes
|
||||||||||||||
Key Stakeholders: | |||||||||||||||
Countries: | EGYPT |
Lessons | |
---|---|
Findings |
Recommendations | |
---|---|
1 | Keep the focus on limited range of technologies |
2 | Secure the Sustainability of the Institutional Support to S&L Development and Enforcement |
Key Action Update History
Keep the focus on limited range of technologies
Management Response: [Added: 2020/01/14]
Agree. The first GEF Energy Efficiency project in Egypt was focused on all aspects of Energy Efficiency in electricity sector and the results were not very tangible. However, this project was focused on only two technologies which has yielded successful results towards the full market transformation
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
New GEF projects will be focused on market transformation to one or two technologies/approaches.
Design a new GEF 7 Energy Efficiency Project for Egypt focused on technologies that would have larger opportunity to prevail over the coming years such A/C technology with invertor compressors
[Added: 2020/01/14] [Last Updated: 2020/11/15] |
UNDPCO / UNDP RTA | 2020/07 | Completed | UNDP Egypt has developed a GEF 7 project entitled Green Sharm El-Sheikh which will support energy efficiency and renewable energy in the hotel sector in the city. The UNDP-GEF draft project document is completed and will be submitted before end of the year to GEF Sec and accordingly the recommendation is now completed. History |
Secure the Sustainability of the Institutional Support to S&L Development and Enforcement
Management Response: [Added: 2020/01/14]
Agree. UNDP will try to maintain the PMU with government funds as the main coordinator among key players in the sector until a new GEF 7 project is approved to
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
1. Secure government sharing to keep the PMU
[Added: 2020/01/14] |
UNDP CO &GoE | 2018/12 | Completed | ||
2. Design a new GEF 7 Energy Efficiency Project to build on the success of the first phase
[Added: 2020/01/14] [Last Updated: 2020/11/15] |
UNDP CO/UNDP RTA | 2020/07 | Completed | UNDP Egypt has developed a GEF 7 project entitled Green Sharm El-Sheikh which will support energy efficiency and renewable energy in the hotel sector in the city. The UNDP-GEF draft project document is completed and will be submitted before end of the year to GEF Sec and accordingly the recommendation is now completed. History |