Terminal Evaluation Improving the energy efficiency of Lighting and other Building Appliances

Report Cover Image
Evaluation Plan:
2018-2022, Egypt
Evaluation Type:
Final Project
Planned End Date:
12/2018
Completion Date:
01/2020
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
18,180

Share

Document Type Language Size Status Downloads
Download document TOR TE EE.pdf tor English 489.33 KB Posted 76
Download document 4231 Egypt EE project - Terminal Evaluation Report signed.pdf report English 1882.37 KB Posted 81
Title Terminal Evaluation Improving the energy efficiency of Lighting and other Building Appliances
Atlas Project Number: 00060162
Evaluation Plan: 2018-2022, Egypt
Evaluation Type: Final Project
Status: Completed
Completion Date: 01/2020
Planned End Date: 12/2018
Management Response: Yes
UNDP Signature Solution:
  • 1. Energy
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021)
  • 1. Output 2.5.1 Solutions developed, financed and applied at scale for energy efficiency and transformation to clean energy and zero-carbon development, for poverty eradication and structural transformation
SDG Goal
  • Goal 13. Take urgent action to combat climate change and its impacts
  • Goal 7. Ensure access to affordable, reliable, sustainable and modern energy for all
SDG Target
  • 13.2 Integrate climate change measures into national policies, strategies and planning
  • 7.3 By 2030, double the global rate of improvement in energy efficiency
Evaluation Budget(US $): 18,180
Source of Funding:
Evaluation Expenditure(US $): 18,180
Joint Programme: No
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
Mr. Louis-Philippe LAVOIE Evaluator i.philippe.louis@gmail.com
GEF Evaluation: Yes
GEF Project Title: Improving the energy efficiency of lighting and other building appliances
Evaluation Type: Terminal Evaluation
Focal Area: Climate Change
Project Type: FSP
GEF Phase: GEF-4
GEF Project ID: 3832
PIMS Number: 4231
Key Stakeholders:
Countries: EGYPT
Lessons
Findings
Recommendations
1

Keep the focus on limited range of technologies

2

Secure the Sustainability of the Institutional Support to S&L Development and Enforcement

1. Recommendation:

Keep the focus on limited range of technologies

Management Response: [Added: 2020/01/14]

Agree.  The first GEF Energy Efficiency project in Egypt was focused on all aspects of Energy Efficiency in electricity sector and the results were not very tangible.  However, this project was focused on only two technologies which has yielded successful results towards the full market transformation

Key Actions:

Key Action Responsible DueDate Status Comments Documents
New GEF projects will be focused on market transformation to one or two technologies/approaches. Design a new GEF 7 Energy Efficiency Project for Egypt focused on technologies that would have larger opportunity to prevail over the coming years such A/C technology with invertor compressors
[Added: 2020/01/14]
UNDPCO / UNDP RTA 2020/07 Not Initiated
2. Recommendation:

Secure the Sustainability of the Institutional Support to S&L Development and Enforcement

Management Response: [Added: 2020/01/14]

Agree. UNDP will try to maintain the PMU with government funds as the main coordinator among key players in the sector until a new GEF 7 project is approved to

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1. Secure government sharing to keep the PMU
[Added: 2020/01/14]
UNDP CO &GoE 2018/12 Completed
2. Design a new GEF 7 Energy Efficiency Project to build on the success of the first phase
[Added: 2020/01/14]
UNDP CO/UNDP RTA 2020/07 Not Initiated